| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹9.9 LAccepted-Finance | ₹9.9 L | L1 | Accepted-Finance Lowest Rate i.e. L1 |
| 2 | L2₹10.1 LRejected-Finance | ₹10.1 L | L2 | Rejected-Finance Not L1 |
| 3 | L3₹10.3 LRejected-Finance | ₹10.3 L | L3 | Rejected-Finance Not L1 |
Tender Value
₹9.9 L
EMD Value
₹19,895
Closing Date
7 Mar 2026, 3:30 pmClosed
Executive Engineer, PWD, Barasat Division
O/o EE, PWD, Barasat Division, Champadalimore, Barasat, Kolkata-700124
Civil works for construction of Gplus 2 storied building for 50 bedded Critical Care Block at Barasat Government Medical College and Hospital, North 24 Parganas Auxiliary work of 3 nos. of Lift Shaft.
2026_WBPWD_1013106_1
WBPWD/BSTD/EE/NIT55e/25-26
Open Tender
CIVIL WORKS
60 days
Barasat Sub Division
Please refer Tender documents.
7 documents required · 7 mandatory
₹19,895
17 Apr 2026
23 Feb 2026
9 Mar 2026
23 Feb 2026
7 Mar 2026
23 Feb 2026
Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof.
B) In 1st floor
c) In 2nd floor
d) In 3rd floor
Dismantling R.C. floor, roof, beams etc. including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars. (a) In ground floor including roof.
b) In 1st floor
c) In 2nd floor
d) In 3rd floor
Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
Ordinary Cement concrete (mix 1:1.5:3) with graded stone chips (20 mm nominal size) excluding shuttering and reinforcement if any, in ground floor as per relevant IS codes. (i) Pakur Variety
b) In 1st floor
c) In 2nd floor
d) In 3rd floor
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) (c) Steel shuttering or 9 to 12 mm thick approved quality ply board shuttering in any concrete work
B) In 1st floor
c) In 2nd floor
d) In 3rd floor
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. (a) For works in foundation and upto roof of ground floor/upto 4 m (i) Tor steel/Mild Steel I.SAIL/ TATA/RINL
B) In 1st floor
c) In 2nd floor
d) In 3rd floor
Brick work with 1-st class bricks in cement mortar (6:1) b) In superstructure, Ground floor
B) In 1st floor
c) In 2nd floor
d) In 3rd floor
Supplying, fitting & fixing granite slabs 15mm to 18 mm. thick with uniform texture & without decorative veins in columns, wall, facia,rise etc. with 15 mm thick [avg] cement mortar (1:2) including making suitable arrangements to hold the stones properly by brass / copper hooks including pointing in cement mortar (1:2) (1 white cement : 2 marble dust) with admixture of pigment matching the stone shades all complete as per direction of the Engineer-in-charge including cost of all materials, labours, scaffolding, staging, curing and roughening of concrete surface complete. [Using cement slurry at back side of granite @ 4.4 kg/sq.m & white cement slurry for joint filling @ 1.8 kg/sq.m] In ground floor (b) Area of each Granite slab above 1.00 Square meter.
b) Iin 1st floor
c) In 2nd floor
Extra cost of labour for prefinished and premoulded Nosing to treads of steps, railing, window sill etc. of Marble Stone.
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] (i) With 1:6 cement mortar (c) 15 mm thick plaster
B) In 1st floor
B) In 2nd floor
B) In 3rd floor
Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m.
Rendering the Surface of walls and ceiling with White Cement base WATER PROOF wall putty of approved make & brand.(1.5 mm thick)
Applying Interior grade Acrylic Primer of approved quality and brand on plastered or cencrete surface old or new surface to receive Distemper/ Acrylic emulsion paint including scraping and preparing the surface throughly, complete as per manufacturer's specification and as per direction of the EIC. (In Ground Floor) (a) One Coat i) Water based interior grade Acrylic Primer
Applying Acrylic Emulsion Paint of approved make and brand on walls and ceiling including sand papering in intermediate coats including putty (to be done under specific instruction of Superintending Engineer) : (Two coats) ii) Luxury Quality
M.S. structural works in columns, beams etc. with simple rolled structural members (e.g. joists, angle, channel sections conforming to IS: 226, IS: 808 & SP (6)- 1964 connected to one another with bracket, gussets, cleats as per design, direction of Engineer-incharge complete including cutting to requisite shape and length, fabrication with necessary bolting, metal arc welding conforming to IS: 816- 1969 & IS: 1995 using electrodes of approved make and brand conforming to IS:814- 2004, haulage, hoisting and erection all complete. The rate includes the cost of rolled steel section, consumables such as electrodes, gas and hire charge of all tools and plants and labour required for the work including all incidental chages such as electricity charges, labour insurance charges etc. Payment to be made on the basis of calculated weight of structural members only in finished work as per IS specified weight. Payment for gusset, bracket, cleat, rivets, bolts and nuts may be make by adding the actual weight of such items with the weight of finished structural members or 7% of weight for finished structural members weighing not less than 22.5 Kg. / m. or 15 % of weight for finished structal members weighing less than 22.5 Kg. / m. may be increased allow for bracket, cleat, rivet, bolts and nuts etc. and no seperate payment being made for these items, as per direction of Engineer In Charge. The rates are considered for a height of erection 8m. / 2nd floor level from the ground. Add 1.5% extra over the rate for each additional floor or 4m. beyond initiial 8m. or part thereof. II) For Structural Works in Roof Trusses etc. using joists, channels and angles of specified section weighing less than 22.5 kg/ m
Labour for Chipping of concrete surface before taking up Plastering work.
Hire and labour charges for shuttering with centering and necessary staging upto 4 m using approved stout props and thick hard wood planks of approved thickness with required bracing for concrete slabs, beams and columns, lintels curved or straight including fitting, fixing and striking out after completion of works (upto roof of ground floor) (When the height of a particular floor is more than 4 m the equivalent floor height shall be taken as 4 m and extra for works beyond the initial 4 m ht. shall be allowed under 12 (e) for every 4 m or part thereof) (e) Extra for staging beyond 4 m in any floor (Mode of measurement: area in plan x mean height of staging upto soffit of shuttering above initial 4 m)
Labour for making Bore-Holes of 150mm to 250mm dia. by any standard method to any depth below ground level / bed level in all kinds of soil like clay, , silt, sand, stiff clay, mixed soils etc. except rocks (for the purpose of collecting Disturbed & Un disturbed soil samples, conducting Standard Penetration Test at suitable intervals etc.) including preparation and submission of bore-log as per IRC : 75 and 78 and Clause 2400 of pecifications for Road & Bridge Works (5th Revision), Published by IRC, and also including hire charges of tools and plants complete as per the direction of Engineer-in-Charge. B Field Investigation: iv) Collection of Undisturbed Samples by core cutter method
Add: SGST 9 % + CGST 9% = 18 %
Labour Wellfare Cess 1%
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
technical_2488666.pdf
techsummary_2488666.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.85 MB
2911iiason01122019.pdf
Tender Documents • 0.46 MB
AllNotificationason01072024.pdf
Tender Documents • 2.35 MB
BOQ_2488666.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid