Building Department, Bhavnagar Municipal Corporation, Sir Mangalsinhji Road, Kalanala, Bhavnagar - 364001
CONSTRUCTION OF COMPOUND WALL, APPROCH PAVER BLOCK ROAD, AND STORAGE ROOF FITTING WORK AT SINDHUNAGAR MOX MANDIR, SINDHUNAGAR AT BHAVNAGAR.
275130
BUILDING/SINDHUNAGAR MOX MANDIR/2025-26
Open
Civil Works - Buildings
Works
Bhavnagar
8 documents required · 8 mandatory
₹1,500
Commissioner,Bhavanagar Municipal Corporation,
₹36,111
10 Feb 2026
10 Feb 2026
10 Feb 2026
18 Feb 2026
10 Feb 2026
Item Quantities Item Description Estimated Rates Unit Total Amount
1 Providing and laying in position Ready Mixed M-250 grade
concrete for reinforced cement conctere work, using cement
content as per approved Design Mix manufactured in fully
automatic batching plant and transported to site of work in
transit mixer for a lead up to 10 kms having continuous
agitated mixer, manufactured as per mix design of specified
grade for reinforced cement concrete work including pumping
of R.M.C. from transit mixer to site of laying, excluding the
cost of centering shuttering finishing and reinforcement
including cost of admixtures in recommended proportions as
per IS: 9103 to accelerate/ retard setting of concrete,
improve workability without impairing strength and durability Rupees Eight Hundred
as per direction of the Engineer-in-charge. Without Fly Ash Forty Five and Thirty
(Min cement level as per latest IS 456 shall be maintained) To Seven Paise
carry a safe working load not less than specified, excluding the
cost of steel reinforcement but including the cost of boring
with bentonite solution and the length of the pile to be
embedded in pile cap etc. all complete. (Length of pile for
payment shall be measured up to the bottom of pile cap): For
212.00 300 mm dia. pile for all inclusive Labour & materials etc. 845.37 Rmt
2 Excavation for foundation upto 3.00 m depth including sorting Rupees Three Hundred
out and stacking of useful materials and disposing off the Eighty Nine and Fifty
excavated stuff upto any lead and any kind soil Eight Paise
3 Filling available excavated earth (excluding rock) in trenches. Rupees One Hundred
plinth, sides of foundations etc. in layers not exceeding 20 cm. Thirty Seven and Forty
in depth consolidating each disposited layer by ramming and Seven Paise
155.12 watering. 137.47 Cum
4 Filling in foundation and plinth with murrum or selected soil in Rupees Three Hundred
layers of 20cm. thickness including watering, ramming and Four and Sixty Paise
consolidating etc. complete.
5 Providing and laying cement concrete 1:3:6 (1-Cement : 3- Rupees Three Thousand
coarse sand : 6- hand broken stone aggregates 40 mmnominal One Hundred Six and
size) and curing complete excluding cost of formwork in (A) Sixty Seven Paise
7.53 Foundation and Plinth 3106.67 Cum
6 Providing and laying controlled cement concrete M.250 and Rupees Five Thousand
curing complete excluding the cost of formwork and Six Hundred Twenty
reinforcement for reinforced concrete work in (C) RCC Column and Ninety Six Paise
67.50 Footings 5620.96 Cum
7 Providing and laying controlled cement concrete M.250 and Rupees Five Thousand
curing complete excluding the cost of formwork and One Hundred Forty One
reinforcement for reinforced concrete work in (C) RCC Column and Four Paise
2.86 up to plinth level 5141.04 Cum
8 Providing and laying controlled cement concrete M.250 and Rupees Five Thousand
curing complete excluding the cost of formwork and Six Hundred Eighty Two
21.08 reinforcement for reinforced concrete work in (C) Plinth Beam 5682.32 and Thirty Two Paise Cum
9 Providing and laying controlled cement concrete M.200 and Rupees Seven Thousand
curing complete excluding the cost of formwork and Six Hundred Thirteen
reinforcement for reinforced concrete work in (C) RCC Column and Sixty Paise
10 Providing and laying cement concrete 1:3:6 (1-Cement : 3- Rupees Seven Thousand
Coarse sand : 6-crushed stone aggregates 20 mm nominal Three Hundred Sixty
size) and curing complete including cost of formwork in (A) Seven and Forty Nine
Wall Caps / Coping Paise
11 Providing TMT Bar FE 500D reinforcement for R.C.C. work Rupees Seventy Seven
including bending, binding and placing in position complete and Twenty Nine Paise
upto floor two level
12 Brick work using common burnt clay building bricks having Rupees Four Thousand
crushing strength not less than 35 kg./Sq.Cm. in Cement Five Hundred Ninety
Mortar 1:5. (1- Cement : 5 -fine sand) (B) Conventional for Nine and Sixteen Paise
75.72 Foundation or Super Structure 4599.16 Cum
13 Providing 20mm thick cement plaster in single coat on single Rupees Two Hundred
or half brick walls for interior plastering upto floor two level Twenty Four and Two
and finished even and smooth in (ii) Cement mortar 1:4 (1- Paise
805.60 cement :4-sand) 224.02 m2
14 Finishing wall with weather proof exterior emulsion paint on Rupees Eighty Four and
wall surface (two coats) to give an required shape even shade Eighty Two Paise
after thoroughly brushing the surface to remove all dirt, and
805.60 remains of loose powdered materials.etc complete 84.82 Sqm
15 Painting two coats including priming coat on new steel and Rupees One Hundred
other metal surface with enamel paint, brushing, interior to Thirty Two and Two
give an even shade including cleaning the surface an even Paise
shade including cleanicn the surface of all dirt, dust and other
34.61 foreign matter. 132.02 Sqm
16 Providing and fixing 0.70 Metre high fencing with 0.80 Metre Rupees Seventy Three
long M.S. Angle posts 50mm x 50 mm x 6 mm fixed at 3.40 and Seventy Three Paise
Mt, C/c. with three Horizontal lines of galvanised steel barbed
wire weighting 9.38 Kg. per 100 Metre, strained and fixed to
posts with G.I, staples including fixing the posts in RCC
Columns and etc complete.
17 Fabrication for railings, gates etc using MS square pipes of 12 Rupees One Hundred
gauge of Asian, TATA or equivalent make Twenty One and Twenty
18 Box cutting the road surface to proper slope and camber for Rupees One Hundred
making a base for road work including removing the excavated Twelve and Two Paise
stuff and depositing on the road side slope as directed up to
19 Providing and laying granular sub base Grade-I C.B.R. not less Rupees Seven Hundred
than 30% by providing close graded materials, consisting of Fourteen and Seven
B.T. crushed stone aggregates 53 mm to 26.5mm@ 50% Paise
26.5mm to 4.75mm @ 20%, 2.36mm to below @ 30% coarse
sand combination and stone dust/grit spreading in uniform
layers with motor grader on prepared surface, mixing by mix
in place method with rotovator at O.M.C to required dry
density including filling the depressions which occurred during
the process using vibratory roller 8-10T Complete as per
20 Providing and laying WBM sub-base required as providing Rupees Nine Hundred
course graded material grading-I in one layer using BTMC Seventy Four and
metal 45 mm to 63 mm including using 22% Stone screening Ninety Two Paise
13.2 mm size and 7% stone dust as filler Gradation including
conveying the materials at the site of work, mixing and
spreading in to grade and camber, watering and consolidation
at OMC with vibratory roller incl. the cost of materials labours
80.00 etc. and all complete. 974.92 m3
21 Providing and laying cement concrete 1:3:6 (1-cement : 3 Rupees Three Thousand
Coarse sand : 6 Graded stone aggregate 40mm nominal size) One Hundred Six and
and curing complete excluding cost of form work in. (A) Sixty Seven Paise
foundation and Plinth
22 Providing and fixing pre-cast Rubber Dye / steel Dye inter Rupees Seven Hundred
locking concrete block 60mm thick with grade of concrete Seven and Fifty Five
M300 pneumatic compressed / vibrated mechanically and as Paise
per approved design Confirming to IS 15658 : 2006 including
35 mm Sand layer for levelling and filling the joint with sand in
proper line and level as per guidelines of IRC : SP 63-2018 etc.
Wood Storage Roof
23 Dismantling of sheet roofing including ridges, Hips, Valleys, Rupees Fifty and
Gutters etc. stacking of serviceable materials and disposal of Twenty Eight Paise
unserviceable materials with all lead and lift.
24 Providing corrugated G.I. sheet of class-3 roofing fixed with Rupees Seven Hundred
galvanised iron J or L Hooks, Bolts and nuts 8mm diameter Thirty Four and
with bitumen and G.I. limpet washer or G.I. limpet washer. Nineteen Paise
filled with white lead complete excluding the cost of purlins,
Rafters and Trusses. (1) 0.80 mm thick sheet.
25 Applying priming coat over new steel and other metal surface Rupees Thirty Seven
after and including preparing the surface by thoroughly and Sixty Three Paise
cleaning, oil, grease, dirt and other foreign matter and scoured
with brushes fine steel wood, scrapers and sand paper with
ready mixed priming paint brushing red lead.
26 Painting two coats (excluding priming coat) on new steel and Rupees Sixty Nine and
other metal surface with synthetic enamel paint, brushing to Sixteen Paise
give an even shade including cleaning the surface of all dirt,
dust and other foreign matter.
One percent of the Estimated cost of work put to tender shall be recovered from the running bills of the contractor as testing charges,
after deducting the cost of material proposed in scheduled-B at basic rate. One percent labour cess will be deducted from contractor’s
I/ We am/are willing to carry out the work at _____________________% above / below _____________________________%
(should be written in figure and words)
below / above the estimated rates mentioned above amount of my / our tender works out as under :-
Estimated amount put to tender : Estimated amount put to tender :
1) All the work shall be carried out as per specification on the division or as directed.
2) Rates quoted includes clearance of site (prior to commencement of work and at its closed) in all respects and held gross for under all
conditions, site moisture weather etc.
3) The Contractor shall exhibits a board as per Govt. circular No. 2DK – 3277 / 1657 N Dt. 26–01-73 with detail of specification and details of
work and amount involved at site without any payment as directed by the Engineer in charge.
4) Testing of materials be as per statement attached with the Specifications, the materials shall be tested at least 10% in G.E.R.I. Bill for testing
shall be paid by Contractor.
5) One precent of estimated cost put to tender for this work shall be recovered from the contract payments as "LABOUR CESS". In terms of the
Gujarat Government Gazette Extra ordinary dated 12.12.04. Implementation of building and other construction workers regulation of
equipment and conditions of service Act-1996)
6) Photographs of before work and after work will be submitted by the contractor at the time of each bill submission.
7) The contractor is solely responsible to bare all applicable taxes. exempt GST. and department will not entertain any contractor representation
to reimburse any financial burden due to applicable taxes : exempt GST.
8) The contractor shall submit all paid taxes, royalty challans at the time of the final bill.
Signature of contractor EXECUTIVE ENGINEER
BUILDING DEPARTMENT
BHAVNAGAR MUNICIPAL CORPORATION
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
01. SBD.pdf
02. NIT.pdf
03. SCH-B.pdf
04. INTRODUCTION OF FORM.pdf
05. CIVIL SPECIFICATIONS.pdf
06. ELECTRIC SPECIFICATION.pdf
07. CHECKLIST FOR TWO BID TENDER (CRITERIA).pdf
08. Material Testing Schedule.pdf
09. vendor list merged.pdf
10. OTHER TENDER CONDITIONS.pdf
11. PARIPATRA.pdf
12. BUILDING_SPECIFICATIONS.pdf
13. ROAD WORK SPECIFICATIONS.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .