Loading…
Loading…
Tender Value
₹79.9 L
EMD Value
₹2.0 L
Closing Date
9 Sept 2026, 3:00 pm
SA, ASI, Rajkot
Office of the SA, ASI, Rajkot, Jublee Bagh, Kasturba Road, Rajkot - 360001
SPECIAL REPAIR AND CONSERVATION OF TALAJA BUDDHIST CAVES INCLUDING STRUCTURAL STABILIZATION RESTORATION OF MISSING PILLARS and FLOORING WORKS
2026_ASI_923103_1
3C/1(11)/SR/RJT/2026-27/C
Open Tender
Civil Works
Works
180 days
Talaja caves junagadh
as per tender doc
2 documents required · 2 mandatory
₹0
₹2.0 L
Yes
20 Aug 2026
20 Aug 2026
10 Sept 2026
20 Aug 2026
9 Sept 2026
20 Aug 2026
20 Aug 2026 - 9 Sept 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Provision for Surface Dressing of Ground including
Removing Vegetation Clearance and In-equlities not
exceding 15 cm deep AND Disposal of rubbish, Lead up
to 50 m and 1.5 m lift ect complete. | 1,850 | M2 | - | - |
| 1.02 | Desalting/ Removal of sludge and silt consisting of
slushy earth, algae, boulders and other foreign material
by necessary excavation , disposting off the sludge by
lifting from bottoms to top of tank throught help of pulleys or any mechanical device up to a height of 8 meter and throwing the same away from the monument by wat of trator trolley etc complete | 68 | cum | - | - |
| 1.03 | Demolishing cement concrete manually/ by mechanical
means including disposal of material within 50 metres
lead as per direction of Engineer - in - charge.. | 32.37 | cum | - | - |
| 1.04 | Supply of stone pillars and stone beams for caves
restoration, matching the original stone in type, colour,
texture, size and workmanship, including loading,
transportation to site, loading/ unloading, & manual
shifting Very Carefully through hilly stepped approach up
to 1,200 meters lead and 500 metres lift to the main
caves, stacking at the specified location, and all labour,
tools & plants, incidental charges, royalty, taxes and
other operations complete as directed by the Engineer in-
Charge | 35.73 | cum | - | - |
| 1.05 | Providing,& fixing the Pillar with carving, dressing, stone
pillar in approved matching stone, conforming to the
original size, profile, mouldings, carvings, colour, texture
and finish of the existing historic pillar, including
preparation of contact surfaces, drilling holes, providing
and fixing stainless steel (SS-316) 12mm dowel pins of
approved diameter and length, fixing with high-strength
non-staining structural stone epoxy adhesive, aligning
the pillar accurately in its original position, filling joints
with colour-matched stone repair mortar where required,
, lifting, finishing, cleaning and disposal of debris,
complete in all respects as per approved conservation
drawings and the directions of the Engineer-in-Charge. | 35.73 | cum | - | - |
| 1.06 | Laying of well mixed base cement concrete (1:3:6) (1
Cement : 3 coarse sand : 6 Stone aggregates of 40 mm
nominal size) in proper gradient with compacting, curing,
all materials, labors, necessary tools etc. all complete | 32.37 | cum | - | - |
| 1.07 | Providing & Laying of Sand Stone 50 mm Thick fine
dressed sand stone flooring over 20 mm average thick
base of cement mortor 1:6 ( 1 Cement : 6 C.Sand ) Joing
finished flush Pointing as per matching with original
Taxture of Monument etc complete in all respect | 562.28 | M2 | - | - |
| 1.08 | Provision for supplying water by water tanker up to the
First Steps and thereafter manually transporting water
from the stock yard near the First Steps to the work site
through a steep stepped approach, including loading,
unloading, handling, hanging/carrying water containers
manually over an approximate lead of 1.20 km with an
elevation of about 500 feet, complete as directed by the
Engineer-in-Charge. | 30 | Each | - | - |
| 1.09 | Provision for Hiring Charge of Erection of steel Centering
shuttering ( Scaffolding ) Very carefully with taking
precaution to avoide any mishappening & damage at a
height upto 10 mts having vertical support of adjustable
height system for leveling with bracing & shuttering with
Plain Surface by sal wood Plank etc including loading,
transportation to site, loading/ unloading, & manual
shifting Very Carefully through hilly stepped approach up
to 1,200 metres lead and 500 metres lift to the main
caves, stacking at the specified location, and all labour,
tools & plants, incidental charges, royalty, taxes and
other operations complete as directed by the Engineerin-
Charge | 30 | Each | - | - |
| 1.1 | Providing and fixing G.I. Pipe Hand Railing for safety and
security of tourists, consisting of 50 mm dia hot-dip
galvanized G.I. pipe for top rail and vertical posts, with
intermediate horizontal rails of approved diameter,
complete with cutting, welding, grinding, M.S. base
plates, anchor fasteners, excavation where required,
fixing in RCC/stone surface, applying one coat of zincrich
primer and two coats of approved synthetic enamel
paint (where galvanizing touch-up is required), including
all materials, labour, tools & plants, loading, unloading,
carriage, scaffolding, and all incidental charges,
complete in all respects. as per the approved drawing
and the directions of the Engineer-in-Charge. | 137 | RMT | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 17.38 MB
signedtenderdoctalaja.pdf
Tender Documents • 17.36 MB
BOQ_970035.xls
BOQ • 0.26 MB
corrigendum.pdf
PDF • 0.65 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].