PUGALUR MUNICIPALITY
PUGALUR MUNICIPALITY
Renewal of BT Road and Formation of CC Road at Highschool veethi West (187004R083),East west 1st street highschool veethi (187004R084),Bazzar II 2nd street (187007R127),Gandhi nagar 5th street (187010R157),Pugalur Railway Gate North, Alagapuri (1870
2023_MAWS_342843_1
E1/985/2023/SFC ARR-3
Open Tender
Civil Works - Roads
Works
90 days
PUGALUR MUNICIPALITY
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹50,000
Yes
PUGALUR MUNICIPALITY
21 Jul 2023
13 Jul 2023
19 Jul 2023
13 Jul 2023
18 Jul 2023
13 Jul 2023
13 Jul 2023
Amount
Preparing the Existing surface to laying the road to Proper Gradient and remove the loose soil without damage the Water Supply and other Pipe lines. The Rate inclusive of all charges such as Earth work and remove the same away from the site etc, complete as per standard specifications
Providing and Laying, Spreading and compacting graded stone aggregates to Wet Mix Macadam specification including premixing the materials with waterat OMC in mechnanical mix plant carriage of mixed material by tipper to site laying inuniform layers with paver sin Sub Base/Base course on well prepared surface and compacting with vibratory roller to acheive the desired density including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 406 of MORTH Rev-5
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion (SS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Rev-5 Specifications
Providing and Laying Tack Coat over WMM surface (treated with primer) using 2.5Kg of Bitumen Emulsion (RS1) per 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per Clause 503 of MORTH Rev-5
Providing and laying Tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying 50 mm compacted thick dense bituminous macadam using 0.24 cum of 26.5-13.2 mm graded metal and 0.25 cum of 13.2-2.36 mm graded metal and 0.23 cum of 2.36 mm & below metal with 53.20 kgs of 60/70 bitumen for premixing per 10 sqm including cost and conveyance of all materials to C M P site, heating the bitumen and agregates to required temperature and mixing them in required temperature in central hot mix plant 20- 30 tonnes capacity conveying the mix by tipper trucks to paver site,spreading the mix in required temperature for uniform thickness of 50mm with mechanical paver to the specified grades and cross sections and compaction by Vibratory roller to the required density etc.,including labour charges for loading bitumen in to bitumen tank and metal to feeder unit,labour for attending to paver site etc., including hire charges and fuel charges for 20-30t C M P with bitumen boiler,tipper trucks, paver finisher, vibratory rollers and all other tools and plants required,including all other incidental charges etc.,complete using C M P clause 505 of MORTH Rev-5 specifications.
Providing and Laying Bituminous Concrete 30mm Consolidated thick using 0.13 cum of 19.00 – 9.50mm,0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 mm & below with 50.30 kgs of 60/70 Grade Bulk bitumen per 10 Sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20 – 30 ton capacity, Conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40 mm with mechanical pavers to the specified grades and cross sections and compaction by Vibratory/Pneumatic rollers to the required density etc., including labour for loading bitumen into bitumen tank and Metal to feeder unit, labour for attending to paver site etc., including hire charges and fuel charges for 20 – 30 ton CMP With bitumen boiler tipper,trucks, paver Finisher/9M, Vibrator rollers and all other tools and plants required,including all other incidental charges etc., complete as per standard specification using CMP Clause 507 of MORTH Rev-5
Providing and laying of hot applied thermoplastic compound 2.5mm thick including reflectorising glass beads @ 250 grams per area, thickness of 2.5mm exculisive of surface applied glass beads as per IRC : 35 The finished surface to be level, uniform and free from streaks and holes.
Plain Cement Concrete 1:4:8 (one part of cement, four part of Crushed Stone Sand (M- Sand) and eight part of coarse aggregates) using 40mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges and all incidential charges such as water providing etc., complete as per standard specification
Centering for soffits of RCC slabs of plane surface like lintels, beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.S angles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cm c/c )and supported dy casurina props of 10cm to 13cm dia (spaced of 75cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38
Plain Cement Concrete 1:1.5:3 (One part of Cement, one and half part of Crushed Sand (M- Sand), three coarse aggregates) using 20mm size ISS HBG metal including cost and conveyance of all materials to site and including for the mixing, laying and labour charges etc., complete as per standard specification
VVR CONSTUCTION
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .