| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.4 LAccepted-AOC | ₹5.4 L | L1 | Accepted-AOC Lowest bidder |
| 2 | L2₹5.7 L+₹22,437.13 (4.12%)Rejected-AOC CHETHAKUDAM HOUSE EAST KODALY NEAR WATER TANK MURIKKUNGAL P O VELLIKULANGARA THRISSUR | THRISSUR | THRISSUR | KERALA | ₹5.7 L+₹22,437.13 (4.12%) | L2 | Rejected-AOC Highest bidder |
Tender Value
₹5.6 L
EMD Value
₹14,100
Closing Date
14 May 2026, 3:00 pmClosed
ASSISTANT EXECUTIVE ENGINEER.ESD,KATTOOR
O/o Assistant Executive Engineer,Electrical Sub DivisionLattoor
LT STANDARDISATION WORK AT KALPAKA TRANSFORMER UNDER ELECTRICAL SECTION KATTOOR
2026_KSEB_849108_1
03/2026-27/ESD/KTR/30.04.2026
Open Tender
Electrical and Maintenance Works
Percentage
120 days
ELECTRICAL SECTION KATTOOR
Please refer Tender documents.
7 documents required · 7 mandatory
₹1,416
₹14,100
7 Jul 2026
2 May 2026
16 May 2026
2 May 2026
14 May 2026
2 May 2026
2 May 2026 - 14 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing Stay for LT poles including digging & back filling pit in ordinary soil. | 25 | No | 938.82 | ₹23,470.5 |
| 2 | Renewal of existing damaged/old LT stay with new stay in place including excavation of stay pit, erection of new stay, backfilling pit and refitting of all items and conveyance of all materials. | 20 | No | 1,191.82 | ₹23,836.4 |
| 3 | Dismantling (without damage) one km LT three phase 4 wire OH line conductor by dismantling cross arms, insulators and stacking the conductors in rolls properly. | - | km | 14,129.32 | - |
| 4 | Dismantling (without damage) one km LT additional conductor line by dismantling cross arms, insulators and stacking the conductors in rolls properly. | - | km | 3,351.73 | - |
| 5 | Disconnecting and lowering down the single phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work. | 300 | No | 96.18 | ₹28,854 |
| 6 | Disconnecting and lowering down the three phase WP service connection with guy wire from the OH line and reconnecting the same after completing the line work | 50 | No | 149.5 | ₹7,475 |
| 7 | Dismantling one ordinary street light/CFL/LED fitting from existing pole and refitting the same on newly erected pole including disconnecting and reconnecting wires. | 60 | No | 492.41 | ₹29,544.6 |
| 8 | Dismantling one section fuse from structure and bringing back to section store. | 21 | No | 192.36 | ₹4,039.56 |
| 9 | Erecting one LT PSC Pole in position including digging & back filling pit in ordinary soil. | 25 | No | 2,017.73 | ₹50,443.25 |
| 10 | Renewal of existing damaged/old LT PSC/RCC (three phase line) pole with new PSC pole in place including excavation of pole pit, erection of new pole, backfilling pit and refitting of all items except street light fitting etc. and conveyance of all materials except pole. | 22 | No | 3,904.77 | ₹85,904.94 |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
Tendernotice_2.pdf
PDF • 0.33 MB
NITKalpaka.pdf
Tender Documents • 0.29 MB
TenderDocumentsESDKTRkalpaka.pdf
Tender Documents • 0.31 MB
BOQ_1434844.xls
BOQ • 0.33 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .