Tender ID
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹4.2 Cr
EMD Value
₹4.2 L
Closing Date
3 Dec 2026, 5:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer (Central Tender Cell)
Central Tender Cell, BMC, ICOMC Tower, Unit-9, Satyanagar
Construction and Improvement of Earthen Roads in Bhagabanpur, Bahania Sahi, Paradise Colony, Maruti Residency and Skytech Infinity Villa Road under Raghunathpur Jalli Gram Panchayat
2026_ORULB_146005_1
BMC-EE-Tender Cell-90/2026-27 dt. 11.11.2026
Open Tender
Civil Works - Others
Percentage
150 days
BMC AREA
Please refer Tender documents.
2 documents required · 2 mandatory
₹10,000
₹4.2 L
Yes
Office Chamber of EE(Central Tender Cell)
13 Nov 2026
13 Nov 2026
4 Dec 2026
13 Nov 2026
3 Dec 2026
13 Nov 2026
13 Nov 2026 - 19 Nov 2026
19 Nov 2026
120 days
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work excavation in Hard soil using one cum Bucket Hydraluc Excavator with all leads and lifts and transpotation of ecavated matiral by mechcanical means. and direction of Engg -in- charge. | 8,578.93 | Cum | 209.95 | ₹18,01,146.35 |
| 2 | Supply and filling in foundation and plinth with river sand, in layers including watering, with cost, conveyance, royalties, and taxes of all materials, cost of all labour, carriage of water, sundries T&P required for the work etc all complete as per the specification & direction of E-I-C | 49.77 | Cum | 519.79 | ₹25,869.95 |
| 3 | Cement concrete in prop. (1:4:8) in foundation using 4 cm size CBHG metal of quality from approved quarry washed and cleaned including hoisting, lowering, laying concrete, ramming, watering, curing etc lincluding cost, conveyance, royalties and taxes of all materials, with cost of all labours, sundries and T & P such as concrete mixer, concrete vibrator required for the work etc, complete as per specificationand direction of EIC | 49.77 | Cum | 5,775.39 | ₹2,87,441.16 |
| 4 | Labour for laying sub-base in layers not exceeding 100 mm. watering and compacting to required density in OMC with P.R.R. but excluding costs conveyance of sub-base materials. (SUB-BASE WITH STONE DUST) | - | cum | 1,883.96 | - |
| 5 | Providing, laying spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stagesto proper grade and camber applying and brooming requisite type of screening / binding materials to fill up the interstices of course agrregate watering and compacting to the required density as per clause 404 of MoSRT&H specificaton for Road & Bridge works. USING GRADE (I) (90 mm. to 45 mm.), USING STONE SCREENED DUST. | 1,807.1 | Cum | 3,347.2 | ₹60,48,725.12 |
| 6 | Providing, laying spreading and compacting stone aggregates of specific sizes to water bound macadam specification including spreading in uniform thickness hand packing, rolling with 3 wheeled steel roller 8-10 tonnes in stagesto proper grade and camber applying and brooming requisite type of screening / binding materials to fill up the interstices of course agrregate watering and compacting to the required density as per clause 404 of MoSRT&H specificaton for Road & Bridge works. USING GRADE (II) (63 mm. to 45 mm.), USING STONE SCREENED DUST | 1,355.18 | Cum | 3,438.58 | ₹46,59,894.84 |
| 7 | CC M-25 with 20mm size downgraded CBHG chips including all cost, conveyance, royalty and taxes etc. complete of all materials to work site as per the specificatiosn approved by the department and the directions of the Engineer-in-Charge | 2,710.57 | Cum | 6,634.78 | ₹1,79,84,035.62 |
| 8 | R.C.C M-25 with 20mm size downgraded CBHG chips including all cost, conveyance, royalty and taxes etc. complete of all materials to work site as per the specificatiosn approved by the department and the directions of the Engineer-in-Charge. | 499.34 | Cum | 6,634.78 | ₹33,13,011.05 |
| 9 | Labour charges for cutting, bending, binding and tying the grill including the cost of M.S. rod. | 161.25 | Qntl | 9,389.58 | ₹15,14,069.78 |
| 10 | Rigid smooth centering and shuttering for RCC or CC work(F&P) including false works, supplying of centering materials, its hire charges, cost of labour T & P and dismentalling after casting the concrete etc all complete as per direction of EIC | 5,614.64 | Sqm | 250.28 | ₹14,05,232.1 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.33 MB
DTCN_90.pdf
Tender Documents • 0.93 MB
BOQ_620328.xls
BOQ • 0.24 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .