Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 CrAccepted-AOC | ₹4.9 Cr Quoted ₹4.4 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹4.9 Cr+₹53.2 L (12.2%)Rejected-AOC | ₹4.9 Cr+₹53.2 L (12.2%) | L2 | Rejected-AOC L2 |
| 3 | L3₹5.2 Cr+₹80.2 L (18.4%)Rejected-AOC | ₹5.2 Cr+₹80.2 L (18.4%) | L3 | Rejected-AOC L3 |
Tender Value
₹4.5 Cr
EMD Value
₹1 L
Closing Date
17 Jun 2020, 5:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, Irrigation South Circle, TVPM
Budget work 2018-19 Protecting the padasekharamsin Kainakary Panchayath -Improvements to the bunds of valiya thuruth padasekharam in Kainakary Panchayath in Kuttanadu
2019_Irrig_328653_3
62/SE/ISC/2019-20/S
Open Tender
Civil Works - Water Works
Item Rate
365 days
Kainakary Panchayath
Please refer Tender documents.
4 documents required · 4 mandatory
₹9,760
Yes
online
₹1 L
Yes
22 Sept 2020
5 Jun 2020
23 Jun 2020
5 Jun 2020
17 Jun 2020
8 Jun 2020
8 Jun 2020 - 17 Jun 2020
Amount
Earth work Excavation
2.6.1 : Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including disposal of excavated earth, lead up to 50 m and lift up to 1.5 m, disposed earth to be levelled and neatly dressed.All kinds of soil
60.7.3 : DISMANTLING DR - Dismanling , clearing away and carefully stacking materials useful for reuse for any thickness of walls in DR masonry including disposal of debris within a distance of 150m.
60.64.2 : Coconut Pile - Supplying and stacking well matured 1/2 split and straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
60.64.1 : Coconut Pile - Supplying and stacking well matured straight coconut post for driving down throug various strata bellow bed level including cost coveyance labour charges etc complete.
60.64.4 : Coconut Pile - Driving down coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end
60.64.5 : Coconut Pile- Driving down half split coconut pile to lines and levels through variuos strata including all hire charges and labour for fixing , staging platform and all other appliances necessary for pile driving down after pointing the bottom end
60.7.2 : DR PACKING Under foundation - Dry stone packing under foundation with good quality blasted rubble including conveyance of material and labour charges etc. complete as per direction of departmental officers at site.
60.7.8 : DR with Departmental. Stone - DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course using departmental rubble including packing to compactness to lines and levels, labour charges etc. complete as per direction of Departmental officers at site
60.7.1 : DRY RUBBLE MASONRY _ Dry rubble without concrete levelling course masonry with good quality blasted rubble including packing to compactness to lines and levels cost and conveyance of all materials labour charges etc. complete as per direction of Departmental officers at site
4.3.2 : Centering and shuttering including strutting, propping etc. and removal of form work for:Retaining walls, return walls, (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc.
5.22.6 : Steel reinforcement for R.C.C work including straightening, cutting, bending, placing in position and binding all complete upto plinth levelThermo - Mechanically Treated bars of grade Fe-500D or more
7.1.1 : Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20 mm nominal size) up to plinth level with:Cement mortar 1:6 (1 cement : 6 coarse sand)
4.1.5 : Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level:1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm nominal size)
od49536/2019_2020/IA : Strengthening the slopes of earthen bund using Coir Geo textiles (700-740 GSM) over a formed and completed bank with proper pinning with good quality Bamboo stick 20 cm length and 1m c/c and edges rolled and fixed the ground properly etc complete as per the direction of deptl. officers at site.
CHERIAN
Mon Joseph
Bidder Name
CHERIAN
Anchil Construction
Mon Joseph
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_511564.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .