| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.6 LAccepted-AOC ZARO SHAM TETULMARI SIJUA TETULMARI DHANBAD DHANBAD JHARKHAND INDIA | DHANBAD | DHANBAD | JHARKHAND | 828121 | ₹8.6 L | L1 | Accepted-AOC Approved |
| 2 | L2₹8.9 LRejected-Finance AT LOYABAD PO BANSJORA DIST DHANBAD | DHANBAD | JHARKHAND | 818142 | ₹8.9 L | L2 | Rejected-Finance L2 |
| 3 | L3₹9.2 LRejected-Finance 0 2 12 SIJUA TETULMURI DHANBAD DHANBAD JHARKHAND 828121 INDIA | DHANBAD | DHANBAD | JHARKHAND | 828121 | ₹9.2 L | L3 | Rejected-Finance L3 |
Tender Value
₹8.6 L
EMD Value
₹10,779
Closing Date
24 Mar 2026, 5:00 pmClosed
AM EnM Sijua Area
Sijua Area office
For repairing of damaged pipeline 4 inch dia at Jogta Coal dump under Kankanee Colliery. (B). For diversion of a section of the 1000 GPM pump delivery range (6 inch dia M.S pipeline) of length 600m, which falls under the proposed OB dump area at ASB
2026_BCCL_356651_1
GM/SA/AM(EnM)-NIT/2025-26/228
Open Tender
Miscellaneous Works
7 days
KNC and ASBNC under Sijua Area
Please refer Tender documents.
6 documents required · 6 mandatory
₹10,779
10 Apr 2026
13 Mar 2026
25 Mar 2026
14 Mar 2026
24 Mar 2026
14 Mar 2026
14 Mar 2026 - 21 Mar 2026
(A). Description of Work :-
Damaged pipe 4" dismantling & 60 miter Labour Cost :- (a). High skilled Man Power 01 head x 02 Shift
Damaged pipe 4" dismantling & 60 miter Labour Cost :- (a). Un-skilled Man Power 06 head x 02 Shift
Installation & flange welding & bend short piece fabrication 7 jointing 60 mtr pipe line. :- (a). High skilled Man Power 01 head x 03 Shift
Installation & flange welding & bend short piece fabrication 7 jointing 60 mtr pipe line. :- (b). Welder skilled Man Power 02 head x 03 Shift
Installation & flange welding & bend short piece fabrication 7 jointing 60 mtr pipe line. :- (c ). Un-skilled Man Power 06 head x 03 Shift
Materials Cost :- D.A Cylinder
Materials Cost :- Oxygen
Materials Cost :- MS Nut & Bolt, Washer (5/8" x 4")
Materials Cost :- Cost of Flange 4"
(B). Description of Work :-(a). (i). Manually carrying, transporting and laying for joining 6" Dia 75 nos pipes, 8 nos bends, tapper short piece. :- (a). Skilled 01 head x05 Shift
(b). Semi-skilled 02 head x 05 Shift
(c ). Un-skilled 05 head x 05 Shift
(ii). Joining 6" Dia 75 nos pipes, 8 nos bends, tapper short piece in level position. :- (a). Skilled 02 head x 10 Shift
(b). Semi-skilled 04 head x 10 Shift
(c ). Un-killed 04 head x 10 Shift
(iii). Manually carrying, transporting and laying in vertical position for joining. 6" Dia 15 nos pipes. 6 nos bends, tapper short piece. :- (a). Skilled 02 head x 03 Shift
(b). Semi-skilled 02 head x 03 Shift
(c ). Un-killed 05 head x 03 Shift
(iv). Joining 6" Dia 15 nos pipes, 6 nos bends, tapper short pieces in vertical position. :- (a). Skilled 03 head x 07 Shift
(b). Semi-skilled 03 head x 07 Shift
(c ). Un-killed 05 head x 07 Shift
(v). Manually carrying, transporting and laying in HAUL ROAD CROSSING for joining, 6" Dia 5 nos pipes, 4 nos bends, tapper short pieces. :- (a). Skilled 01 head x 02 Shif
(b). Semi-skilled 02 head x 02 Shift
(c ). Un-killed 04 head x 02 Shift
(vi). Joining 6" Dia 5 nos pipes, 4 nos bends tapper short pieces in HAUL ROAD CROSSING. :- (a). Skilled 02 head x 02 Shif
(b). Semi-skilled 02 head x 02 Shift
(c ). Un-skilled 04 head x 02 Shift
(vii). 6" Dia Flange welding for bend, tapper :- Skilled 02 head x 03 Shift
Semi-skilled 02 head x 03 Shift
Un-skilled 02 head x 03 Shift
Oxygen
Welding rod
(viii). 6" Dia bend, taper short piece making :- Skilled 02 head x 08 Shift
Semi-skilled 02 head x 08 Shift
Un-skilled 02 head x 08 Shift
Oxygen
Welding rod
(ix). Manually Carrying, Transporting and laying for flench welding, 6" Dia 20 Nos. new pipes and after welding removing pipes:- 01 No Skilled, 02 Nos. Semi-Skilled, 05 Nos. Un-Skilled, 3 Shift and storing at safe place and Preparing of new 6" Dia pipe 20 Nos. with flench welding - 02 No Skilled, 02 Nos. Semi-Skilled, 04 Nos. Un-Skilled,4 Shift :- (a).Skilled
(b).Semi-skilled
(c ). Un-skilled
(d). Oxygen
(e ). Welding rod
(ix). Loading, Transporting of 6" Dia pipe 20 Nos, 18 Nos. bends, tapper short pieces from workshop and unloading at mines:- 01 No Skilled, 02 Nos. Semi-Skilled, 05 Nos. Un-Skilled, 2 Shift and and Cutting 80 Nos. of 6" Joint from conveyer belt - 01 No Skilled, 02 Nos. Semi-Skilled, 02 Nos. Un-Skilled,4 Shift :- (a).Skilled
(b).Semi-skilled
(c ). Un-skilled
Supply of 60 Nos. of 6" MS Flench @582.05
Cost of Nut bolt (5/8x2.5") @ 85/Kg , 120 Kg
Cost of Nut bolt (5/8x3") @ 85/Kg , 95 Kg
Transporting Cost (Oxygen, DA, Welding Machine)
(b). (i). Dismantling of 6" Dia pipe 75 Nos. , 7 Nos bends, tapper short pieces from 1000 GPM pump range.:- Skilled 01 head x 10 Shift
Semi-skilled 02 head x 10 Shift
Un-skilled 04 head x 10 Shift
(ii). Transporting, loading on truck 75 Nos. 6" Dia pipes, 7 Nos tapper short pieces, bend unloading at safe places at NOCP for jointing:- Skilled 01 head x 06 Shift
Semi-skilled 02 head x 06 Shift
Un-skilled 06 head x 06 Shift
(C ). Description of Work :- (i). Dismantling all materials cutting for base frame multiple tiems 3000/2400/1000 GPM Pump.:- (a) Skilled 01 head x 10 Shift
(b). Semi-skilled 03 head x 10 Shift
(ii). Fabrication of New base palte frame for 3000/2400/1000 GPM Pump.:- (a) Skilled 01 head x 10 Shift
(b). Semi-skilled 03 head x 10 Shift
(iii). Making 10" Dia tapper band, Y shape short piece nipple reduced (8"x10") 01 No. both (with both side heavy welding) & Flange Welding. :- (a). Fitter 01 No.x @ Rs. 893/-
(b). Welder- 01 No. x @ Rs. 893/-
(b). Helper- 01 No. x @ Rs. 893/-
Cost of Making 10" Dia tapper band, short pieces, pipe, Foot Valve, Nipple, T, Reducer etc. Both side flange welding Rs. 2546/- eachx 18 No.
(iv). Fabrication of Electric Pole 10Nos. (9mtr /12mtr).:- (a). Welder 01 No. x 893/-
(b). Welder Helper 02. No. x 760/-
(c ). Rs. 2413/- x 09 Nos. Pole.
(v). Supply of 10" Dia M.S Flange :- High Skilled
(vi). Supply of 10" Dia M.S Flange- Material Cost.:- (a). D.A Cylinder
(b). Oxygen Cylinder
(c ). Welsding Rod
(d). Cost of Transporting
Total impact of GST for the purpose of CTC
Please Enable Macros to View BoQ information
stage.html
html • 0.05 MB
technical_369510.pdf
techsummary_369510.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.71 MB
BOQ_369510.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid