Tender Value
₹7.3 L
EMD Value
₹14,667
Closing Date
10 Oct 2026, 3:00 pm
Executive Engineer
Bidhannagar Municipal Corporation
Development of Sewerage and drainage system at Sasthitala from Om Krishna Niwas to Proyanti Niwas within Ward no. 12 Within Bidhannagar Municipal Corporation. (Fund- U.D. and M.A Fund)
2026_MAD_1043130_2
NIT No- 575/PWD/ROAD/BMC, Dated- 25/09/2026
Open Tender
CIVIL WORKS
Percentage
25 days
Bidhannagar Municipal Corporation
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹14,667
25 Sept 2026
25 Sept 2026
12 Oct 2026
25 Sept 2026
10 Oct 2026
25 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling R.C. floor, roof, beams etc. Including cutting rods and removing rubbish as directed within a lead of 75 m. including stacking of steel bars. (a) In ground floor including roof. | 6.84 | Cum | 1,956 | ₹13,379.04 |
| 2 | Dismantling all types of plain cement concrete works, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. In ground floor including roof. (a) upto 150 mm. thick | 10.26 | Cum | 939 | ₹9,634.14 |
| 3 | Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge | 17.1 | Cum. | 166 | ₹2,838.6 |
| 4 | Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches, levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | 44.46 | Cum | 173.9 | ₹7,731.59 |
| 5 | Constructing Inspection pit to a depth of 1.5 metre (inside), 250 mm thick 1st class
brick work (1:4) in all sides over a layer of jhama brick soling and 150 mm thick cement concrete with stone chips (1:3:6) including necessary earth work, fitting and fixing approved type S.W. master trap, constructing masonry invert with cement concrete (1:1.5:3) with stone chips, plastering inside and outside (outside upto 300 mm below G.L.) with 20 mm thick cement plastering (1:4) and neat cement punning, including supplying,fitting and fixing one 560 mm. dia R.C.C. manhole cover of approved make with R.C.C. slab of 100 mm thick with cement concrete (1:1.5:3) with stone chips including necessary reinforcement (upto 1%) and shuttering and necessary corbelling brick work (1:4) so that the R.C.C. cover slab rests 150 mm above adjucent G.L., cement plaster (1:4) 10 mm thick on all external surfaces of the top slab as directed complete in all respect and removal of surplus earth with all costs of labour and materials (excluding the cost of master trap only).
(i) 900 mm X 750 mm (inside) chamber including fitting and fixing S.W. master trap of 150 mm dia. of approved make A) With Pakur variety. (SAIL/TATA/RINL) | 10 | Each | 11,859 | ₹1,18,590 |
| 6 | Supplying & laying Double Wall Corrugated (with external annular corrugation and smooth internal walls) High Density Polyethelene Pipes conforming to IS 16098 (Part-II):2013 having Stiffness Class of SN 8 with Ring Stiffness not less than 8.00 KN/Sqm. and Impact Resistance TIR value not more than 10% including necessary jointing materials for non- pressure underground Drainage, Sewerage & Cross drainage application. (vi) 500mm internal dia. | 70 | Mtr. | 3,663 | ₹2,56,410 |
| 7 | (i) 150mm internal dia | 52 | Mtr. | 420 | ₹21,840 |
| 8 | Earth work in filling in foundation trenches or plinth with good earth, in layers not exceeding 150 mm. including watering and ramming etc. layer by layer complete. (Payment to be made on the basis of measurement of finished quantity of work)
(a) With earth obtained from excavation of foundation. | 50.4 | % Cum. | 7,754 | ₹3,90,801.6 |
| 9 | (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity) | 7.88 | % Cum. | 93,621 | ₹7,37,265.38 |
| 10 | Supplying, fitting and fixing in position FRP/GRP/COMPOSITE UV stabilizer Gully Pit Cover with high abrasion surface of 7mm top thicknes, density of 2KG/m³ of approved make with rim of approved make (Heavy type) (iii) 10 M.T. Gully pit cover (yard gully) with arrangement for opening of size
Frame Clear Opening
640 mm X 240 mm.
Cover Out to Out
700 mm X 300 mm | 26 | Each | 3,917 | ₹1,01,842 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.38 MB
BOQ_2559835.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .