Loading…
Loading…
Tender Value
₹3.9 Cr
EMD Value
₹7.7 L
Closing Date
29 Aug 2026, 5:00 pmDue tomorrow
The Engineer-in-Chief, PR PMGSY, Vijayawada.
The Engineer-in-Chief, PR PMGSY, Z.P.P. Compound, Opp. PWD Grounds, Bandar Road, Vijayawada.
Package No. AP20PIVMLSB01, L023-Construction of Bridge on the road from 18 by 2 Km Andra R and B Road to Chakivalasa via lakshmipuram in Mentada Mandal of Vizianagaram District.Est. Cost Rs. 615.00 Lakhs and Rs. 13.00 Lakhs for Routine Mtc.
2026_ENCPR_149197_1
NIT No.177/2026-27, Dt.07.08.2026 of the Engineer-in-Chief, PR, PMGSY, Vijayawada.
National Competitive Bid
Civil Works - Bridge Construction
Percentage
545 days
Mentada Mandal of Vizianagaram District.
As per Bid Document
3 documents required · 3 mandatory
₹0
₹7.7 L
O/o the SE PR Circle Z.P.P. Compound,Vizianagaram.
15 Aug 2026
15 Aug 2026
1 Sept 2026
15 Aug 2026
29 Aug 2026
15 Aug 2026
15 Aug 2026 - 29 Aug 2026
18 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Bridge portion | - | - | - | - |
| 2 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including dewatering, contractors profit & Over head charges, but excluding GST and seigniorage etc., complete- For Foundations Ordinary soil Upto 3 m depth (including dewatering) | 1,185 | Cum | 141 | ₹1,67,085 |
| 3 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH, including dewatering, contractors profit & Over head charges, but excluding GST and seigniorage etc., complete- For Foundations Ordinary soil 3 m to 6 m depth (including dewatering) | 847 | Cum | 161 | ₹1,36,367 |
| 4 | Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD / 304 MORTH Ordinary rock (not requiring blasting) Upto 3 m depth (including dewatering) | 593 | Cum | 178 | ₹1,05,554 |
| 5 | Reinforced cement concrete M30 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in Foundations complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1203 MORD and 1500, 1700 & 2100 MORTH, including contractors profit & Over head charges, but excluding cost of reinforcement, GST and seigniorage etc., complete for Foundations For / Footings | 682 | Cum | 7,540 | ₹51,42,280 |
| 6 | Reinforced cement concrete M30 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH, including contractors profit & Over head charges, but excluding cost of reinforcement, GST and seigniorage etc., complete for Sub Structures For Bed Blocks, substructure - Height upto 5m | 407 | Cum | 8,010 | ₹32,60,070 |
| 7 | Reinforced cement concrete M30 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in substructure complete as per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1206 MORD and 1500, 1700 & 2200 MORTH, including contractors profit & Over head charges, but excluding cost of reinforcement, GST and seigniorage etc., complete for Sub Structures- For Bed Blocks, substructure Height (5m to 10m) | 7 | Cum | 8,240 | ₹57,680 |
| 8 | Providing and laying reinforced cement concrete M30 grade (Design Mix) using 20 & 10mm metal (HBG) mechanically mixed in superstructure as per drawing and technical specifications Clauses 800, 1401.4.1 and 1401.4.2 MORD / Sections 1500, 1600, 1700 & 2300 MORTH, including contractors profit & Over head charges, but excluding cost of reinforcement, GST and seigniorage etc., complete upto 5m height. - For Super Structure (T girder and slab) | 382 | Cum | 9,110 | ₹34,80,020 |
| 9 | P.C.C. M 15 ordinary grade (1:2.5:5) using 40,20 & 10mm metal (HBG) mechanically mixed leveling course below approach slab complete as per drawing and technical specifications Clauses 800 and 1404.4 MORD & 2704 MORTH, including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete | 8 | Cum | 6,390 | ₹51,120 |
| 10 | Reinforced Cement Concrete M 30 grade approach slab using 20 & 10mm metal (HBG) mechanically mixed excluding reinforcement complete as per drawing and technical specifications Clauses 800 and 1404.4 MORD / 1500, 1600, 1700 & 2704 MORTH, including contractors profit & Over head charges, but excluding GST and seigniorage etc., complete | 18 | Cum | 7,430 | ₹1,33,740 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.57 MB
SBD_AP20PIVMLSB01.pdf
Tender Documents • 1.57 MB
BOQ_234738.xls
BOQ • 0.40 MB
Schedule_AP20PIVMLSB01.pdf
Additional Documents • 5.35 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].