| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹17.1 LAccepted-AOC GEETA COTTAGE NO 03 HOUSE NO 11 OPP CIVIL AIR PORT BHUJ KUTCH 370001 GUJARAT | KACHCHH | GUJARAT | 370001 | L1 | Accepted-AOC Being Lowest Bidder | |
| 2 | L2₹17.2 L+₹8,250 (0.48%)Rejected-Finance C O BHAGYODAY STORES BAZAR CHOWK NALIYA KUTCH 370 655 | KACHCHH | GUJARAT | 370655 | L2 | Rejected-Finance Not a Lowest Bidder |
Tender Value
₹20.8 L
EMD Value
₹41,500
Closing Date
26 Jun 2020, 6:00 pmClosed
GE (AF) NALIYA
GE AF Naliya Kutch 370 655
MANNING AND OPERATION OF DG SETS AT VARIOUS LOCATIONS TECH AREA AT AF STN NALIYA
2020_MES_348482_1
8696/E8
Open Tender
Miscellaneous Works
Item Rate
330 days
GE (AF) NALIYA
As per NIT
8 documents required · 8 mandatory
₹500
Yes
GE (AF) NALIYA
₹41,500
Yes
27 Jul 2020
30 May 2020
29 Jun 2020
30 May 2020
26 Jun 2020
13 Jun 2020
Amount
Manning and operation of diesel engine driven generator set installation including periodical maintenance consisting of LT Panels, AMF Panel, change over switch and other equipments of installation for contineous operation with 01 (One) FGM in each shift of 8 hours on three shifts a day (24 hours round the clock operation) including Sundays and Holidays including general cleaning of surrounding area of DG set of capacity 160 KVA, 3 Phase with AMF panel at MAFI PS-II Sub Station complete all as specified and as directed.In addition serviceability of DG Set 30 KVA of S/S No 5 Alpha(Security Light) will be checked including its fuel level,coolant level,Engine oil condition and its operation if required and the same be intimated to JE on daily basis all as directed by Engineer-in-charge.
All as per Item No.1.00 here in before, but DG set of capacity 100 KVA, 3 phase with AMF panel at ATC Sub Station No. 10.In addition serviceability of DG Set 50 KVA near S/S No 19(For Blast pens) will be checked including its fuel level,coolant level,Engine oil condition and its operation if required and the same be intimated to JE on daily basis all as directed by Engineer-in-charge
All as per Item No. 1.00 here in before, but DG set of capacity 40 KVA, 3 phase with AMF panel at ORP-06 End Runway..
All as per Item No. 1.00 here in before, but DG set of capacity 100 KVA, 3 phase with AMF panel at ORP-24 End Runway.In addition serviceability of DG Set 40 KVA of 24 ACRR,50 KVA of DSS and 20 KVA of S/S No 20 will be checked including its fuel level,coolant level,Engine oil condition and its operation if required and the same be intimated to JE on daily basis all as directed by Engineer-in-charge.
All as per Item No. 1.00 here in before, but DG set of capacity 62.5 KVA, 3 phase with AMF panel at Base Ops Installation.
Note for item Nos. 1 to 5 (i) Necessary fuel and lubricants will be provided by the Deptt. free of cost under Sch 'B' stores and the same shall be required to be collected by the contractor from MES Store Yard. (ii) The contractor will maintain log sheets of each plant for recording the running period and fuel consumption. These log sheets shall be produced to the Deptt. before claiming any payment/ RAR/ Final Bill duly signed by all concerned. (iii) The contractor will employ (Electrician/ FGM) in each shift (ITI certificate holder from Government/ Government recognised Institute having minimum 04 years of working experience in the trade only). Necessary experience certificate and qualification certificate shall be submitted by the contractor after Acceptance of contract. (iv) The contractor shall ensure that all equipments (as mentioned under Item Nos. 01 to 05 above) are in proper working condition. If any item is required repair for proper functioning of system, the contractor shall inform to concerned JE/ AGE immediately via telephone and in writing.
(v) The contractor is responsible for smooth functioning of installations and if any minor/ consumable items are required, the same shall be arranged by the contractor. (vi) The contractor shall be responsible to communicate the concerned JE/ AGE/ GE regarding any type of break down/ fault within 20 minutes of the incident. (vii) The contractor shall be responsible for maintaining the installation neat and clean position. All necessary materials and T&P for washing/ cleaning of equipments will be arranged by the contractor at their own cost. (viii) The contractor shall provide protective clothing and jackets, helmet and shoes as approved by the Accepting Officer, to all operators on duty and the cost of the same is deemed to be included in the quoted rate.
(ix) The contractor shall provide first aid box with all items at each installation. (x) All operators shall be paid their salary/ wages through Bank Account only ant the proof thereof shall be produced strictly by the contractor while claiming RAR/ Final Bill. (xi) If the quoted amount is less than the estimated cost of the work, then the lowest bidder will have to deposit FDR/ BGB in favour of Accepting Officer within 07 days of opening of Financial Bid for the difference in estimated cost & quoted amount. In case the said FDR/ BGB is not submitted within stipulated period as mentioned above, the contractor shall be banned for 06 months and his bid will be rejected. FDR/ BGB shall be released only after satisfactory completion of work including defect liability period of contract whenever applicable.
Krishna Engineering
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .