Tender Value
₹31.4 L
EMD Value
₹64,000
Closing Date
21 Oct 2026, 3:00 pm5d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer
office of executive engineer head works division agra canal okhla
Revitalization of the main entrance gate at Okhla Barrage in Delhi State
2026_UPIDC_1196843_3
09/EE/2026-27
Open Tender
Civil Works
Item Rate
45 days
at Okhla Barrage in Delhi State
Please refer Tender documents.
2 documents required · 2 mandatory
₹354
₹64,000
15 Oct 2026
15 Oct 2026
21 Oct 2026
15 Oct 2026
21 Oct 2026
15 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Earth work in excavation in foundation in ordinary soil ( loamy clay or sand ) i/c. lift upto 1.5 metre and lead upto 30 metre and i/c. back filling,watering and ramming of excavated earth into trenches and disposal of surplus earth as directed by Engineer-in-charge with cost of labour and T&P etc.required for proper completion of work. | 87.75 | Cum. | - | - |
| 1.02 | Providing & laying 80 mm. thick factory made C.C. Interlocking tiles/paver including 50mm. Thick compacted bed of fine sand proper embedding/laying of interlocking tiles leveling and dressing of surface to required level and slope,filling joints with fine sand and below it laying 0.10m. thick base concrete in 1:3:6 with cost of all materials,labour and T&P etc required for proper completion of work. | 128 | Sqm. | - | - |
| 1.03 | Providing & laying of Cement Concrete in 1:3:6 (1 cement:3 coarse sand:6 stone grit 20-40 mm.size) including cost all materials ,labour and T&P etc. required for proper completion of work. | 5.63 | Cum. | - | - |
| 1.04 | Providing & fixing Centering & Shuttering for C.C. Work i/c. rent of shuttering material ,labour and T&P etc. required for proper completion of work. | 5.3 | Sqm. | - | - |
| 1.05 | Steel Reinforcement for R.C.C. Work i/c. it's straightening, cutting, bending, binding, cutting and placing in position and cost of binding wire with cost of all materials, labour and T&P etc. required for proper completion of work. | 4.64 | MT | - | - |
| 1.06 | Providing & laying R.C.C. 1:1.5:3 (1 Cement :1.5 Coarse sand : 3 Grit 12-20 mm.size) i/c. cost of all materials, labour and T&P etc. but excluding cost of reinforcement required for proper completion of work. | 43.39 | Cum. | - | - |
| 1.07 | Providing & fixing Centering & Shuttering for R.C.C. Work i/c. rent of shuttering material ,labour and T&P etc. required for proper completion of work. | 236.73 | sqm. | - | - |
| 1.08 | Brick work in 1:4(1cement:4coarse sand) cement coarse sand mortar including cost of all materials,labour and T&P etc. required for proper completion of work. | 20.97 | Cum. | - | - |
| 1.09 | 12.50mm thick cement plaster in 1:4 (1Cement:4Coarse sand) cement mortar i/c. cost of all materials, labour, and T&P etc . Required for proper completion of work. | 383.01 | sqm. | - | - |
| 1.1 | Sal wood work in chaukhat frame with M.S. hold fast i/c. cost of all materials,labour and T&P etc. required for proper completion of work. | 0.27 | Cum. | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.40 MB
lot3.pdf
Tender Documents • 2.35 MB
BOQ_2261051.xls
BOQ • 0.27 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .