Vijayawada Division - Replacement of Critical implantation OHE structures and less contact wire height OHE structures due to raising of track in connection with safety in DVD-BZA section.
B-E29-TRD-TNDR-28-2024-25
B-E29-TRD-TNDR-28-2024-25
Open
Works - General
12 Months
Ntr, Andhra Pradesh
₹0
₹1.8 L
26 Mar 2025
26 Mar 2025
Item Breakup - A-SOR Items
Per LABOUR/ERECTION location Total 14418.00 2(b) Concrete for foundations and plinth in other than hard soil and rock (including foundation for Item- 2 AT/BT masts) S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/ MATERIAL
LABOUR/ERECTION Total 565360.00 3 (a) Erection of traction masts and main masts of switching stations & LT supply transformer Item- 3 station. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 13710.00 Item- 4 3 (b) Erection of fabricated steel work such as TTC, Portals, SPS etc. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 9252.00 Item- 5 3(e) Supply and Erection of Guy rod assembly. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 65310.00 Item- 6 4 (a) (i) Supply without insulator and erection of single bracket assembly for conventional OHE. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY / MATERIAL
LABOUR/ERECTION Total 284544.00 Item- 7 4(a)(ii) Extra on 4(a)(i) for supporting two OHEs. S No. Item Description of Item Unit Qty Rate Amount No VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY
SUPPLY / MATERIAL
LABOUR/ERECTION Total 5887.00 Item- 8 5(a)(i) Supply without insulator and erection of mounting arrangements for span wire. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 16816.00 Item- 9 5(a)(ii) Supply & Erection of span wire (1.30) S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 5661.00 Item- 10 11(a)(i) Supply without insulator and erection of 25 KV solid core cut-in insulator S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 10160.00 13(a) Supply without insulators and erection of 25 kKV single ole isolators without earth contact Item- 11 assembly S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 85790.00 Item- 12 15(a) Supply and erection of all types of jumpers S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 17180.00 Item- 13 16(a) Supply and erection of structure bonds. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL
LABOUR/ERECTION Total 19800.00 Item- 14 31(a) Transfer of equipment from one mast or support to other. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 55836.00 Item- 15 31(i) Dismantling of an isolator. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2990.00 Item- 16 31(j) Dismantling of a pedestal pin insulator S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 980.00 Item- 17 31(k)(i) Dismantlement of OHE mast/Structure by cutting. S No. Item Description of Item Unit Qty Rate Amount No VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY
LABOUR / ERECTION Total 55300.00 Item- 18 31(k)(ii) Dismantlement of upright of TTCs/Portals by cutting. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2000.00 Item- 19 31(l)(i) Retrieval of traction masts, main masts, TTC uprights etc. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 17500.00 Item- 20 31(n) Dismantlement of guy rod S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 3390.00 Item- 21 31(p) Dismantling of Drop arms/Booms/Temporary masts S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2314.00 Item- 22 31(r) Dismantling of Cantilever assemblies including insulators. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR / ERECTION Total 990.00 31(t)(i) Dismantling of a regulating equipment (Three pulley type) with counter weight assembly for Item- 23 conventional/composite OHE. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2975.00 Item- 24 31(t)(iii) Dismantling of Anticreep with galvanised Steel wire. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 630.00 Item- 25 31(t)(v) Dismantling of material of termination of double over head equipment conductor. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 560.00 Item- 26 39(a) Erection of released guy rod. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 1250.00 Item- 27 39(c) Erection of released regulating equipment. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 6545.00 Item- 28 39(d) Erection of released termination. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 1750.00 VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY Item- 29 39(f) Erection of released 25 KV post insulator S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 300.00 Item- 30 39(h) Erection of released 25KV single pole isolator S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 3430.00 Item- 31 39(j) Erection of released anticreep S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 1380.00 Item- 32 32/3 (a) Erection of traction structures consisting of rolled and fabricated under Power Block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR / ERECTION Total 13710.00 Item- 33 32/3(b) Erection of fabricated steel work other than masts under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 9252.00 Item- 34 32/3(e) Erection of Guy rod assembly under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 6780.00 Item- 35 32/4(a)(i) Erection of Single bracket assembly for conventional OHE under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 19008.00 Item- 36 32/4(a)(ii) Extra on 4(a) (1) for supporting two OHEs. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 413.00 Item- 37 32/5(a)(ii) Erection of span wire (1.30) under power block, S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 407.00 Item- 38 32/11(a)(i) Erection of 25 KV solid core cut-in insulator under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2700.00 Item- 39 32/15(a) Supply and erection of all types of jumpers under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 1160.00 Item- 40 32/31 (a) Transfer of equipment from one mast or support to other under power block. S No. Item Description of Item Unit Qty Rate Amount No VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY
LABOUR/ERECTION Total 55836.00 Item- 41 32/31(i) Dismantling of an isolator under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2990.00 Item- 42 32/31(j) Dismantling of a pedestal pin insulator under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 980.00 Item- 43 32/31(k)(i) Dismantlement of OHE masts/structures by cutting under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 55300.00 Item- 44 32/31(k)(ii) Dismantlement of upright of TTC's/portals by cutting under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2000.00 Item- 45 32/31(n) Dismantlement of guy rod under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 3390.00 Item- 46 32/31(p) Dismantling of Drop arms/Booms/Temporary masts under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2314.00 Item- 47 32/31(r) Dismantling of Cantilever assemblies including insulators under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 990.00 32/31(t)(i) Dismantling of a regulating equipment with counter weight assembly for conventional Item- 48 /composite OHE under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 2975.00 Item- 49 32/31(t)(iii) Dismantling of Anticreep with galvanised Steel wire under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 630.00 32/31(t)(v) Dismantling of material of termination of double over head equipment conductor under Item- 50 power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 560.00 Item- 51 32/39 (a) Erection of released guy rod under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY Total 1250.00 Item- 52 32/39 (c) Erection of released regulating equipment under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 6545.00 Item- 53 32/39 (d) Erection of released termination under power block S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 1750.00 Item- 54 32/39 (f) Erection of released 25 KV post insulator S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 300.00 Item- 55 32/39 (h) Erection of released 25KV single pole isolator S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 3430.00 Item- 56 32/39 (j) Erection of released anti creep under power block. S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 3450.00 Item- 57 33/3(a) Extra on erection rates for steel work done manually under item No. 3 (a) S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 6840.00 Item- 58 33/3(b) Extra on erection rate for steel work done manually under item No. 3 (b). S No. Item Description of Item Unit Qty Rate Amount No
LABOUR/ERECTION Total 4624.00
Item Breakup - B-NON-SOR ITEMS - PART-II: INSULATORS
SUPPLY / MATERIAL Total 220770.00 Item- 63 Supply of Porcelain stay insulator(1050 CD) S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL Total 217305.00 Item- 64 Supply of 25 kv Porcelain 9-Tone Insulator [Polluted Zone] 1050 mm CD. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL Total 137610.00
Item Breakup - B-NON-SOR ITEMS - PART-I: Steel Items
SUPPLY/MATERIAL VIJAYAWADA DIVISION-ELECTRICAL/SOUTH CENTRAL RLY Total 1724610.00 3(b) Supply of fabricated steel work other than masts such as TTC's , portal sets (with all Item- 60 components) etc as per latest RDSO drawings and IS specifications. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL Total 117224.00 3(c) Supply of Fabricated steel work other than mast, TTCs, portals, such as SPS, special fabricated Item- 61 steel etc. S No. Item Description of Item Unit Qty Rate Amount No
SUPPLY/MATERIAL Total 119474.00
B-NON-SOR ITEMS - PART-I: Steel Items
B-NON-SOR ITEMS - PART-II: INSULATORS
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .