Tender Value
₹34.4 L
EMD Value
₹68,700
Closing Date
31 Aug 2026, 4:00 pm6d left
Xen RnB Division Kargil
Xen RnB Division Kargil
Construction of 2nd Story at Middle School Sanjak (By way of construction of Balance work). (Under Capex).
2026_PWD_19426_1
E tender 32 of 2026-27 PW RnB Division 2nd Kargil
Open Tender
Civil Works - Buildings
Percentage
45 days
Kargil
Please refer Tender documents.
3 documents required · 3 mandatory
₹500
Xen RnB Division Kargil
₹68,700
24 Aug 2026
24 Aug 2026
1 Sept 2026
24 Aug 2026
31 Aug 2026
24 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Earth work in excavation by manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides a ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. | |||||
| 1.1 | AllKind of Soil @ 60 % | 204.46 | Cum | 433.78 | ₹88,690.66 |
| 1.2 | Ordanary Rock @40% | 136.3 | Cum | 960.53 | ₹1,30,920.24 |
| 2 | Providing and fixing up to floor five level precast cement concrete solid block,including hoisting and setting in position with cement mortar 1:6 (1 cement : 6 coarse sand), cost of required centering, shuttering complete :
1:3:6 (1 Cement: 3 coarse sand(zone-III) : 6 graded stone aggregate 20 mm nominal size). | 18.12 | cum | 13,729.2 | ₹2,48,773.1 |
| 3 | Reinforced cement concrete work in beams,columna pillar , suspended floors ,roofs having slope up to( 15 degree)landings ,balconies ,shelves up to floor five level excluding the cost of centering ,shuttering ,finishing and reinforcement with 1:1.5:3(1cem | 5.31 | cum | 11,238.73 | ₹59,677.66 |
| 4 | Reinforcement for RCC work including straightening, bending, cutting, placing in position and binding all complete.Hot rolled deformed bars.including carriage complete. | 1,002.45 | cum | 106.37 | ₹1,06,630.61 |
| 5 | Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering All works upto plinth level 1:3:6(1cement:3 coarse sand : 6 graded stone agg 20mm nominal size) Nallah | 251.22 | cum | 6,243.92 | ₹15,68,597.58 |
| 6 | Proviidng and laying 50mm thoick factory made cement concrete interlocking tile M-30 grade made by block making machine with strong vibaratory compacted of approved size, design and shape laid in required clour and pattern over and including 50 mm thick compacted bed of course sand, filling the joint with line sand etc all complete as per direction | 37.17 | Sqm | 2,267.38 | ₹84,278.51 |
| 7 | Centering and shuttering including strutting, propping etc. and removal of form for foundation and B Wall etc. | 320.82 | Sqm | 297.86 | ₹95,559.45 |
| 8 | Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers | 53.44 | Sqm | 585.69 | ₹31,299.27 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.84 MB
BOQ_46068.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].