| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹13.7 Laccepted-aoc | ₹13.7 L | accepted-aoc |
Tender Value
₹15.4 L
EMD Value
₹15,369
Closing Date
26 May 2026, 5:00 pmClosed
Executive Engineer, I & CAD, Irrigation Division, Srikakulam
Srikakulam
Improvements to Bellupada Groyne/ Channel on Bahuda River near Bellupada village in Ichapuram Mandal in Srikakulam District
931822
2T/2026-27 Dt.8.5.2026 (Item No.1)
OPEN - NCB
Civil Works
SRIKAKULAM
8 documents required · 7 mandatory · 1 optional
₹545
₹15,369
10 Jun 2026
12 May 2026
12 May 2026
Dewatering pump 5 Hp (Diesel)
Earth work in excavation in all kinds of soils of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material. Depth upto 3 m
Providing and laying insitu vibrated M-10 (28 dayscube compressive strength not less than 10 N/sq mm) grade cement concrete using 40 mm down size approved, clean, hard, graded aggregates for foundation filling including cost of all materials, machinery, labour, formwork, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Providing and laying insitu vibrated M-15 (28 days cube compressive strength not less than 15 N/sq mm) grade cement concrete using 20 mm down size approved, clean, hard, graded aggregates for sub structure/ super structure works including cost of all materials, machinery, labour, formwork, scaffolding, cleaning, batching, mixing, placing in position, levelling, vibrating, finishing, curing etc., complete with initial lead upto 50 m and all lifts.
Providing and constructing dry rock pitching for groynes/ platform using un-coursed rubble stone of size 300 mm thick from quarry to site of work including cost of all materials, machinery. Labour charge hand picking un coursed rubble stone to the designed profile with all leads and all lifts etc for above water level
Laying sand bags in the stipulated places including cost of empty cement bag, sand, thread, stiching charges and labour charges with 13.615% over head charges and contractor's profit (sand rate for filling is considered)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
BOQE.xlsx
TENDER_DOCUMENT • 0.64 MB
Budget Declaration.pdf
TENDER_DOCUMENT • 0.33 MB
schedule-A.xlsx
TENDER_DOCUMENT • 0.01 MB
Tender schedule - Correct.docx
TENDER_DOCUMENT • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .