| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹32.6 LAccepted-AOC | ₹32.6 L | L1 | Accepted-AOC AOC |
| 2 | L2₹35.8 L+₹3.2 L (9.95%)Rejected-Finance | ₹35.8 L+₹3.2 L (9.95%) | L2 | Rejected-Finance Second Lowest |
| 3 | L3₹36.3 L+₹3.7 L (11.3%)Rejected-Finance | ₹36.3 L+₹3.7 L (11.3%) | L3 | Rejected-Finance Third Lowest |
Tender Value
₹40 L
EMD Value
₹80,000
Closing Date
8 Mar 2024, 5:00 pmClosed
Executive Engineer
Office of the Executive Engineer Construction Division Uttarakhand Peyjal Nigam Rudraprayag
Giwala water supply Scheme of Block Augustmuni
2024_MDPEY_70319_1
758/Nivida/45 Dated 22.02.2024
Open Tender
Civil Works
Item Rate
60 days
Block Augustmuni
Please refer Tender documents.
3 documents required · 3 mandatory
₹3,540
Executive Engineer Construction Division UKPJN
₹80,000
Rudraprayag
17 Jun 2025
24 Feb 2024
11 Mar 2024
24 Feb 2024
8 Mar 2024
27 Feb 2024
27 Feb 2024
Amount
Supply and fixing of MS Intake chamber to fulfill the requierment of water demand including Supply of all materials, labour,carting of material T&P etc complete as per direction of Engineer in charge
supply, carting , laying true to aligment and gradient, jointing and fixing of following GI (M) pipe lines including all specials fittings, white lead, hemp and other appurtenant works etc. making necessary connections with existing laid pipe line including connecting with existing Private & Othe house hold Tap Connections with control plate/ferrule devices etc complete and make proper functioning, confirming to IS:1239 at site of works.. On completion of work the laid length of pipe will be deemed eligible for supply. The respective amount for quantity of surplus supply of pipes (which remained unlaid or unutilized) will be deducted from final bill and surplus quantity of pipes will be the property of contractor.)
15 mm dia - GI (M)
20 mm dia - GI (M)
25 mm dia - GI (M)
32 mm dia - GI (M)
40 mm dia - GI (M)
Excavation of earth for pipeline in following strata lift upto 1.5 m lead upto 30 m including refilling, watering, ramming of excavated earth into the trenches and removal of surplus earth upto a distance of 60 m from trenches including supply of labour, T & P etc.all complete assuming that 90% pipe line is laid in trenches, it is estimated that 75% excavation will be in soil mixed with shingle, bajari and boulders and rest 25% will be in medium rock
Soil mixed with boulder (SMB)
Medium Rock (MR)
Supply and fixing of Wheel Valve/ Gate Valve of the following sizes including cartage of materials, labour, T&P etc. complete
25 mm dia
40 mm dia
Supply of all materials,labours ,T.&P. etc. and making ferrule connection to provide FHTC to the consumers from existing w/s scheme including all material, labour, T&P etc. complete excluding water meter & pipe as per instruction given by Engineer - In-charge.
Constructing Wheel Valve Chamber 60x60x75 cm, inside with 75 class designation brick work in cement mortar 1:4 (1 cement :4 coarse) including supply, cartage of all material, labour, T&P etc complete for Sluice Valve/Air Valve with C.I. surface box 100 mm. as per standard design. with locking arrangement.
Construction of following capacity RCC semi sunk reservoir, including testing and commissioning for water tightness, with supply of all materials Labour, T&P etc and construction of RCC CWR of following capacities (in kiloliters) with M.S. ladder outside & inside of the tank, M.S. M.H. Cover with locking arrangement, supply and fixing of outlet, inlet, over flow and wash out pipes with necessary sluice valves, pipe pieces (including cost of materials) flooring 0.60 M wide apron, painting on tank body vertical pipes, ladder, M.S. M.H. cover etc. complete with approved water proofing (apex)/enamel paint, testing, filling water for testing purpose etc. including supply of vertical pipes and specials, assuming bearing capacity as 8 MT/M2
Supply cartage and fixing of Bucket type chlorinator of 25 Liter capacity at top of service raservoirs.
Concrete with 2 Cm gauge stone ballast, local sand and cement in proportion of 1:2:4 in foundation and floors including supply of all materials, labour and T&P etc.required for proper completion of work.
Concrete with 4 Cm gauge stone ballast, local sand and cement in proportion of 1:4:8 in foundation and floors including supply of all materials, labour and T&P etc.required for proper completion of work.
R.R. Stone masonary with 1:6 cement and sand mortar including cartage and supply of all materials, labours, T&P etc. complete for proper completion of work.
R.R.Stone masonry laid in dry including cartage and supply of all materials,labours,T&P etc. required for proper completion of work.
HIMMAT SINGH RAWAT
LAKHPAT SINGH BARTWAL
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_84464.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .