| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹24,175.50Accepted-AOC | ₹24,175.50 | L1 | Accepted-AOC 1st lowest bidder. |
| 2 | L2₹24,506Rejected-Finance 74 1 EAST CHANDMARI 3RD LANE PO NONA CHANDANPUKUR KOLKATA 700122 | 24 PARAGANAS NORTH | WEST BENGAL | 700122 | ₹24,506 | L2 | Rejected-Finance 2nd lowest bidder. |
| 3 | L3₹36,329Rejected-Finance | ₹36,329 | L3 | Rejected-Finance 3rd lowest bidder. |
| Sl No | Description | Qty | Unit | M/S BISHWAKARMA DECORATORS L1 | R.B. ENTERPRISE L2 | GHOSH AND CO L3 |
|---|---|---|---|---|---|---|
| 1.00FOR STRONG ROOM | ||||||
| 2.00 | Removal of existing table, chair,benches & other materials from the proposed commissioning counting halls & placing benches to different places and replacing as before after completion of programme. After completion of counting programme ( any floor to ground level ) including protection the materials with covering a tarpoline. | 1 | per sq. mtr. for one day | 98 ₹98 | 99 ₹99 | 100 ₹100 |
| 3.00 | Supply labour for cleaning rooms, premises, jungles etc. & levelling the ground removal of existing materials, drainage of water as necessary on daily basis. | 1 | per sq. mtr. for one day | 19 ₹19 | 20 ₹20 | 500 ₹500 |
| 4.00 | Temporary sealing work with 125 mm thick brick work with cement sand Mortar with Top and Inside Roughj Finishing & dismentling & Removal of entire brick work as earlier Original situation ( Rate assume on 50.00 % less rate than the basis of PWD Schedule excluding of GST & Cess & Deduction of Rate Due to Not Permanent in Nature ) & Removal as precondition ( Analysis over the rate Rs 736.00 /Sq. m rate included breaking loss and resealing value. | 1 | per sq. mtr. for one day | 248 ₹248 | 250 ₹250 | 20 ₹20 |
| 5.00 | Temporary sealing work with 75 mm thick brick work with cement sand Mortar with Top and Inside Roughj Finishing & dismentling & Removal of entire brick work as earlier Original situation ( Rate assume on 50.00 % less rate than the basis of PWD Schedule excluding of GST & Cess & Deduction of Rate Due to Not Permanent in Nature ) & Removal as precondition ( Analysis over the rate Rs 736.00 /Sq. m rate included breaking loss and resealing value. | 1 | per sq. mtr. for one day | 495 ₹495 | 496 ₹496 | 40 ₹40 |
| 6.00 | Hire & labour charges for G.C.I sheet walling fixed vwith nail from inside of strong room for patition of strong room door window as required and removal as precondition. | 1 | per sq. mtr. for one day | 92 ₹92 | 93 ₹93 | 60 ₹60 |
| 7.00 | Strong Room wooden Rack making with 65 mm x 65 mm strong prop with necessary bracing and tie top finishing with strong ply board 10.00 mm thick including site placing and fitting, fixing in different floor at earmarks strong room and removal as precomndition ( Considering a unit CU, BU & VV PAT ) | 1 | per sq. mtr. for one day | 489 ₹489 | 490 ₹490 | 1,000 ₹1,000 |
| 8.00 | Strong Room Steel Rack making with 65 mm x 65 mm strong prop with necessary bracing and tie top finishing with strong steel board 20.00 mm thick including site placing and fitting, fixing in different floor at earmarks strong room and removal as precomndition ( Considering a unit CU, BU & VV PAT ) | 1 | per sq. mtr. for one day | 648 ₹648 | 650 ₹650 | 120 ₹120 |
| 9.00 | Fitting and fixing of collapsable gate for strong room and other'son Hiring Basis as necessary & Removal as precondition. | 1 | per sq. mtr. for one day | 194 ₹194 | 195 ₹195 | 120 ₹120 |
| 10.00 | Hire charges for wooden rack prepared with Bamboo, wooden plank, batters etc. having multiple setf on wooden plank base and two sides covered with wooden p.lank with sites follows – (Height of total rack – 7’-6” Height of each shed of – 1”-8” No. of shed of = 4 Nos. width of Rack – 2’-6” Wooden plank thick nos. =1" (minimum) ).The rack structure should have sufficient ties, bracing etc. so as to make it strong enough to with -stand the load of EVMs stored on it in the required space. The rate should be qouated considering all the material fitting & fixing all fixture, labour and removal of the same after the election process and as per direction of authority . The payment will be made on the basis of length of the structure in running ft | 1 | per r. mtr. for one day | 47 ₹47 | 50 ₹50 | 360 ₹360 |
Tender Value
Refer Docs
EMD Value
₹10,000
Closing Date
14 Apr 2026, 3:00 pmClosed
EE
BMC
Civil Infrastructural Works i.e. erection of different temporary pandals, partitions etc. for Strong Room preparation..............in connection to the ensuing West Bengal Legislative Assembly General Election 2026 (WBLAGE - 2026).
2026_MAD_1023545_1
NIQ No.2560/PWD(BMC) dt.06/04/2026
Open Tender
Miscellaneous Services
12 days
Bidhannagar Municipal Corporation
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹10,000
25 Jun 2026
7 Apr 2026
16 Apr 2026
7 Apr 2026
14 Apr 2026
7 Apr 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | FOR STRONG ROOM | - | - | - | - |
| 2 | Removal of existing table, chair,benches & other materials from the proposed commissioning counting halls & placing benches to different places and replacing as before after completion of programme. After completion of counting programme ( any floor to ground level ) including protection the materials with covering a tarpoline. | - | per sq. mtr. for one day | - | - |
| 3 | Supply labour for cleaning rooms, premises, jungles etc. & levelling the ground removal of existing materials, drainage of water as necessary on daily basis. | - | per sq. mtr. for one day | - | - |
| 4 | Temporary sealing work with 125 mm thick brick work with cement sand Mortar with Top and Inside Roughj Finishing & dismentling & Removal of entire brick work as earlier Original situation ( Rate assume on 50.00 % less rate than the basis of PWD Schedule excluding of GST & Cess & Deduction of Rate Due to Not Permanent in Nature ) & Removal as precondition ( Analysis over the rate Rs 736.00 /Sq. m rate included breaking loss and resealing value. | - | per sq. mtr. for one day | - | - |
| 5 | Temporary sealing work with 75 mm thick brick work with cement sand Mortar with Top and Inside Roughj Finishing & dismentling & Removal of entire brick work as earlier Original situation ( Rate assume on 50.00 % less rate than the basis of PWD Schedule excluding of GST & Cess & Deduction of Rate Due to Not Permanent in Nature ) & Removal as precondition ( Analysis over the rate Rs 736.00 /Sq. m rate included breaking loss and resealing value. | - | per sq. mtr. for one day | - | - |
| 6 | Hire & labour charges for G.C.I sheet walling fixed vwith nail from inside of strong room for patition of strong room door window as required and removal as precondition. | - | per sq. mtr. for one day | - | - |
| 7 | Strong Room wooden Rack making with 65 mm x 65 mm strong prop with necessary bracing and tie top finishing with strong ply board 10.00 mm thick including site placing and fitting, fixing in different floor at earmarks strong room and removal as precomndition ( Considering a unit CU, BU & VV PAT ) | - | per sq. mtr. for one day | - | - |
| 8 | Strong Room Steel Rack making with 65 mm x 65 mm strong prop with necessary bracing and tie top finishing with strong steel board 20.00 mm thick including site placing and fitting, fixing in different floor at earmarks strong room and removal as precomndition ( Considering a unit CU, BU & VV PAT ) | - | per sq. mtr. for one day | - | - |
| 9 | Fitting and fixing of collapsable gate for strong room and other'son Hiring Basis as necessary & Removal as precondition. | - | per sq. mtr. for one day | - | - |
| 10 | Hire charges for wooden rack prepared with Bamboo, wooden plank, batters etc. having multiple setf on wooden plank base and two sides covered with wooden p.lank with sites follows – (Height of total rack – 7’-6” Height of each shed of – 1”-8” No. of shed of = 4 Nos. width of Rack – 2’-6” Wooden plank thick nos. =1" (minimum) ).The rack structure should have sufficient ties, bracing etc. so as to make it strong enough to with -stand the load of EVMs stored on it in the required space. The rate should be qouated considering all the material fitting & fixing all fixture, labour and removal of the same after the election process and as per direction of authority . The payment will be made on the basis of length of the structure in running ft | - | per r. mtr. for one day | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.63 MB
Tendernotice_2.pdf
PDF • 1.46 MB
BOQ_2515885.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid