Loading…
Tenderkart now works inside Claude and ChatGPT: search and analyse tenders right from your chat
Loading…
Tender ID
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance NEAR GURU NANAK I C RAJGARH PUNJABY COLONY GATE KHERI UTTAR PRADESH 262701 | KHERI | UTTAR PRADESH | 262701 | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
| 3 | Admitted-Finance | Admitted-Finance |
Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
4 Sept 2024, 12:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDC LAKHIMPUR
SE EDC Moh. Rajgarh Sitapur Road Lakhimpur
TENDER NO 30/EDCL/2024-25
2024_MVVNL_949845_1
30/EDCL/2024-25
Open Tender
Miscellaneous Works
Item Rate
180 days
LAKHIMPUR KHERI
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,180
SE EDC LAKHIMPUR
₹10,000
11 Sept 2024
27 Aug 2024
4 Sept 2024
27 Aug 2024
4 Sept 2024
27 Aug 2024
Amount
Loading, carriage & unloading of following materials from centre store to work site and its stacking. Distance approx (0-45) kms. Under work area of EDD-Mitauli.
(A) Line Material.
(B) PCC pole 8.5/9 Mtr long
(C) STP Pole 9/11 Mtr. long.
(D)- T/F 10/16/25/63/100 KVA
(E)ACSR Rabit/Dog /Racoon/weasel/ conductor
(F)ABC( 3x120/95/70/25/16) Sqmm.
(G)11 KV XLPE Cable (3x35/70/120/185/240)
(H) 11kv pilfer resistant metering cubical
(I)11 KV Pole mounted CT/PT
(K)DP Box 3 Phase
Fabrication, erection of sub-station type double pole on 8.5 mtr long PCC/11 mtr. Long ST pole along with fixing of necessary hardware of doble pole alongwith necessery pin insulators as per RESPO specification and direction of E/I.
Dragging of ST/PCC pole to pit site, digging of pit erection and grouting (As per RESPO norms) of 11KV 9/11/8.5 mtr long ST/PCC pole with fixing of necessary items, such as V-type X-arm, F-bracket, 11KV Pin/Disc insulator, guarding angle(1.8 mm65x65x6) with nut & bolts its ramming as per RESSPO Specification.
Dragging of ST/PCC Pole from dump store to pit site, digging of pit erection & grouting (As per RESPO norms) of LT support suitable for laying of ABC line on 8.5mtr long PCC pole by providing of necessary eye hook/LT shackle insulator with clamps and its accessories etc. as per RESPO specification. Only Pole will be provided by the department.
Fabrication, erection T-Off pole single section pole along with T-Off channel clamp disc fitting & pin accessories, grouting in 1:4:8 cement sand and brick ballast as per RESPO specification.
Providing and fixing of 11 KV DO fuse set along with clamps & nut bolts on existing of double pole.
Fixing of 11 KV TPMO along with clamps & nut bolts on existing of double pole.
Ordinary earthing by MS earth Rod 2500mm long as per RESPO Schedule. Only GI wire& Earth rod shall be supplied by the department.
Grouting and Nuzzling of stay set complete including fixing of necessary clamps. Accessories required including its grouting by civil material (Sand: brick ballast: cement). Only stay rod and Stay wire shall be supplied by the Department.
Laying and sagging of 3 phase 3 wire 11 KV line on ACSR weasel/rabbit/Raccoon/Dog conductor as per RESPO specification and direction of E/I.
Providing and fixing of guarding angle on existing 11 KV support with clamp and nut bolts.
Cradle guarding of HT line by GI wire. GI wire shall be supplied by the department.
Erection & commissioning of (3x120/95/70/25/16 Sq.mm) Aerial Bunched Conductor.
Laying of cable 11 KV XLPE cable (3x35/70/120/185/240) sqmm in pakka road by boring method laying cable as per RESPO specification & direction of E/I.
Laying of cable 11 KV Through piping .
Hoisting of 11 KV XLPE Cable will be passed through MS pipe of required size duly clamped with pole at the bottom, middle and top of the pole.
Supply and fixing of 11 KV Cable joining kit O/D and I/D.
Installation of 11 KV CT/PT on double pole connected with metering unit along with providing and fixing of all accessories such as S/S base, MS flat, clamps, nut and bolts its jumpering and commissioning.
Construction of brick masonry plinth suitable for Installation of 11 KV Pilfer metering cubical along with plastering.
Dragging of 11 KV Pilfer metering cubical inside the metering room, its installation and commissioning.
Fixing of 3 phase distribution box/kiosk on the LT poles including all clamps and material required for mounting connections and sealing.
Making section of 11 KV line by fixing of All necessaries accessories such as T-Off channel disc insulator with fitting pin insulator with pin along with sagging jumpering and binding etc only insulator shall be provided by the dept.
Cutting and chopping of tree branches for clearance of HT/LT Line. After clearance line throughout pieces of tree branches of site.
Safe installation & energisation of 10/16/25/63/100 KVA T/F on double pole by providing and fixing of L-piece, Lugs making HT/LT connections and its commissioning. Only Transformer shall be supplied by the deppt.
Supply of top Droper T-off clamp
Fabrication T-Off Top Droper S/s Base Grouting Engal and Cross Arm
Supply of Net-Bolt i-type
Supply of Holding Clamp for PCC/ST Pole
Supply of F-Clamp
M/s Mishra Traders
M/S JAISWAL INTERPRISES
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .