Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.4 LAdmitted-Finance C O GAURAV CHAUDHARY S O SH MAN SINGH R O V P O RATTI TEH BALH DISTT MANDI H P 175008 | RATTI | MANDI | HIMACHAL PRADESH | 175008 | +4.90% | ₹3.4 L | L1 | Admitted-Finance |
| 2 | L2₹3.4 L+₹321.52 (0.10%)Admitted-Finance | +5.00% | ₹3.4 L+₹321.52 (0.10%) | L2 | Admitted-Finance |
| 3 | Rejected-Technical | - | - | - | Rejected-Technical Bidder disqualified |
Tender Value
₹3.2 L
EMD Value
₹6,500
Closing Date
25 Jun 2026, 11:00 amClosed
Manager Civil RTDC US Club Shimla
RTDC US Club Shimla-1
Additional work at existing terminal building of Heliport Mandi Distt. Mandi H.P.
2026_RTDCH_136951_1
RTDC/Heliport Mandi Balance Work/2026/1273 dt 18/06/2026
Open Tender
Repair and Maintenance Services
Percentage
120 days
Heliport Kangnidhar Mandi
Please refer Tender documents.
7 documents required · 7 mandatory
₹590
Executive Engineer (Civil), RTDC
₹6,500
6 Jul 2026
19 Jun 2026
25 Jun 2026
19 Jun 2026
25 Jun 2026
19 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Providing and fixing double scaffolding system (cup lock type) on the exterior side, up to seven story height made with 40 mm dia M.S. tube 1.5 m centre to centre, horizontal & vertical tubes joining with cup & lock system with M.S. tubes, M.S. tube challies, M.S. clamps and M.S. staircase system in the scaffolding for working platform etc. and maintaining it in a serviceable condition for the required duration as approved and removing it there after .The scaffolding system shall be stiffened with bracings, runners, connection with the building etc wherever required for inspection of work at required locations with essential safety features for the workmen etc. complete as per directions and approval of Engineerin- charge .The elevational area of the scaffolding shall be measured for payment purpose .The payment will be made once irrespective of duration of scaffolding. | 151 | Sqm | 224.73 | ₹33,934.23 |
| 2 | Designing, fabricating, testing, installing and fixing in work gang saw cut (polished and machine cut) of position Curtain Wall with Aluminium Composite Panel Cladding, with open grooves for linear as well as curvilinear portions of the building , for all heights and all levels etc. including: (a) Structural analysis & design and preparation of shop drawings for pressure equalisation or rain screen principle as required, proper drainage of water to make it watertight including checking of all the structural and functional design. (b) Providing, fabricating and supplying and fixing panels of aluminium composite panel cladding in pan shape in metalic colour of approved shades made out of 4mm thick aluminium composite panel material consisting of 3mm thick FR grade mineral core sandwiched between two Aluminium sheets (each 0.5mm thick). The aluminium composite panel cladding sheet shall be coil coated, with Kynar 500 based PVDF / Lumiflon based fluoropolymer resin coating of approved colour and shade on face # 1 and polymer (Service) coating on face # 2 as specified using stainless steel screws, nuts, bolts, washers, cleats, weather silicone sealant, backer rods etc. (c) The fastening brackets of Aluminium alloy 6005 T5 / MS with Hot Dip Galvanised with serrations and serrated washers to arrest the wind load movement, fasteners, SS 316 Pins and anchor bolts of approved make in SS 316, Nylon separators to prevent bi-metallic contacts all complete required to perform as per specification and drawing The item includes cost of all material & labour component, the cost of all mock ups at site, cost of all samples of the individual components for testing in an approved laboratory, field tests on the assembled working curtain wall with aluminium composite panel cladding, cleaning and protection of the curtain wall with aluminium composite panel cladding till the handing over of the building for occupation. Base frame work for ACP cladding is payable under the relevant aluminium item.s The Contractor shall provide curtain wall with aluminium composite panel cladding, having all the performance characteristics all complete , as per the Architectural drawings, as per item description, as specified, as per the approved shop drawings and as directed by the Engineer-in-Charge. However, for the purpose of payment, only the actual area on the external face of the curtain wall with Aluminum Composite Panel Cladding (including width of groove) shall be measured in sqm. up to two decimal places. | 1 | Sqm | 5,303 | ₹5,297.7 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.33 MB
Tendernotice_2.pdf
PDF • 5.08 MB
Tendernotice_3.pdf
PDF • 1.09 MB
BOQ_202713.xls
BOQ • 2.77 MB
AdoptionofCPWD.pdf
Additional Documents • 0.60 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .