Ship Repair Complex,HSL,Visakhapatnam
Overhauling of STP rotory vane air compressors and Removal and refitment of Sewage discharge pumps and dirty water discharge pumps on MV Swaraj Dweep
2021_HSL_86585_1
20/21997/045/2021-22
Open Tender
Miscellaneous Services
Service
25 days
HSL Visakhapatnam
Please refer Tender documents.
7 documents required · 7 mandatory
₹0
Exempted
24 Jul 2021
12 Jul 2021
22 Jul 2021
12 Jul 2021
22 Jul 2021
12 Jul 2021
Amount
STP Plants Pumps and Air Compressores: The firm is to execute the complete below mentioned SoW and as per conditions mentioned in Annexure-A and finally Satisfactoy Operational trials to be shown to SS, Class & HSL.
Overhauling of STP rotory vane air compressors: STP rotary vane Air Compressors along with motor to be removed, overhauled and replaced damaged parts, refitted in position, satisfactory trials to be showned to ship staff and sureyor. Material: Wear rings / bushes, gaskets, fasterners are procure, supply and fitment, consumables, machining works, welding and brazing works are in contractor scope.
Removal and refitment of Sewage discharge pumps and dirty water discharge pumps: Sewage discharge pumps and Dirty water discharge pumps along with motors to be removed, refitted after steel renewals, alignment to be carried out in between pumps and motors with reference to new foundations. Satisfactory operation of pumps to be shown to surveyors. Material: Fasteners are procure, supply and fitement, consumables, machining works, welding and brazing works are in contractor scope.
Consumables / Components / Items / Spares / Material: For executing of the above mentioned jobs, Contractor has to procure, supply all items and fitted in its place. Contractor has to quote lumpsum cost for required Consumables / Components / Items / Spares / Material mentioned at S.Nos. 1 to 1.2 for above scope of work. The taxes will be paid as per actuals. The cost of spares quoted by the contractor will be considered " on not exceeding basis of total lumpsum cost mentioned in the BOQ for this line item'' for satisfactory completion of the specified SoW. Payment will be made at actuals on not exceeding quoted cost of this Serial (1.3) against third party/OEM invoice.
SRI SRINIVASA ENGINEERING WORKS
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .