| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹40.9 LAdmitted-Finance ANGUL ODISHA 759147 UDYAM OD 01 0001580 | ANUGUL | ODISHA | 759147 | L1 | Admitted-Finance | |
| 2 | L2₹66.5 L+₹25.6 L (62.5%)Admitted-Finance D 13 R D AGA ROAD MIDC INDUSTRIAL AREA CHINCHWAD PUNE PUNE MAHARASHTRA 411019 | PUNE | MAHARASHTRA | 411019 | L2 | Admitted-Finance | |
| 3 | Rejected-Technical 29 GOBRA GORISTHAN ROAD KOLKATA 700046 | KOLKATA | KOLKATA | WEST BENGAL | 700046 | - | Rejected-Technical Not qualified |
| Sl No | Description | Qty | Unit | P C JOSEPH ENGINEERING AND CONTRACTOR L1 | Thermax Limited L2 |
|---|---|---|---|---|---|
| 1.00U#4 ESP OVERHAULING JOB | |||||
| 1.01 | DRY CLEANING WORK
Thorough Dry cleaning of ESP starting from ESP inlet funnel up to ESP outlet funnel, all ESP hoppers, Gas distribution Screens, all emitting electrodes and collecting plates and other allied zones.
Suspension zones in between CERM/EERM Frame and ESP ceiling to be checked and cleaned properly. After de-synchronization of Unit, all hopper doors (288 Nos.) are to be opened for smooth removal of ash. After completion of total overhauling job, all hoppers must be checked finally and cleaning & removal of ash/clinker or any other foreign material if persist. Then all hopper manholes have to be boxed up properly by total replacement of old gaskets with new ones with adhesive and tightness checking.
Stipulated Period of Work: Day-2 to Day-4- 04 Number of separate manpower gangs to be engaged for working at a time in 04 ESP Passes. Report to be submitted to department by 4th day evening or 5th day morning. | 1 | LUMPSUM | 50,000 ₹50,000 Lowest | 83,800 ₹83,800 |
| 1.02 | WATER JET CLEANING WORK
Thoroughly HP Water Jet washing from top to Bottom of ESP internals (72 Nos Fields), including all hoppers, collecting plates, emitting electrodes and other allied zones till metallic surface exposed and completely free of ash deposits. Four number HP Pumps must be put in service in parallel from 04 (Four) different Water outlet points provided at site. At the time of water washing if any chocking found in the hoppers, same shall be cleared immediately. Suspension zone in between CERM/EERM Frame and ESP ceiling to be checked and cleaned properly. All necessary equipment including sufficient number of hose, nozzles and four nos booster pumps (discharge pressure of 4-5 Kg/sq.cm) will be arranged by party.
Stipulated Period of Work: Day-3 to Day-9 - Two separate groups of manpower should be engaged at a time by round the clock without fail until finish this job within stipulated time. Daily work progress and respective checking report to be submitted within 48 Hrs of Unit De-Synchronise. After water washing of all the ESP internals, detailed field inspection of all fields to be carried out by the party along with experts engaged by departmental authority and share the findings to departmental authority. | 1 | LUMPSUM | 1,60,000 ₹1,60,000 Lowest | 2,52,800 ₹2,52,800 |
| 1.03 | INTERNAL CHECKING AND RECTIFICATION
Field gauging of each Collecting Plate to maintain a gap of 400mm by Go Gauge (72 Nos of ESP fields in A, B, C & D Path). Job to be carried out by specialized separate manpower, experienced to perform identical job at ESP. Re-fitting of new spacers if required. Each & Every emitting frame alignment shall
be checked thoroughly.
Stipulated Period of Work: Day -6 to Day-20 -Simultaneous work must be going on in 02 passes at a time by two separate expert team. Everyday findings and its rectification report to be submitted. Rectification job to be strictly carried out as per reports/findings of expert engaged by departmental authority. | 72 | NUMBER | 72,000 ₹72,000 Lowest | 1,22,400 ₹1,22,400 |
| 1.04 | CERM SYSTEM CHECKING
The complete collecting electrode rapping mechanism with all its plain bearing, inner arm, outer arm, shock bar, shock pad, Shock Bar Guide Plate, shock bar guide assembly (Rapping and non-rapping side) and its attachment, rapping shafts, Pin wheel, hammer assembly, Anvil Bar and corresponding fasteners, Guide angle, PL attachments of Rapping and non-rapping sides are to be thoroughly inspected and necessary replacement/ modification/Fitting of missing components and tack welding of bolts are to be done as per the instruction of experts engaged by departmental authority.
The Rapping shaft straightness are to be checked and if necessary, the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done as per expert engaged by departmental authority. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective shock bar position correctly for CRM. Straightening of misaligned shock bar and its assembly are to be done and gap between the electrodes to be maintained as per expert engaged by departmental authority. The clearance between the shock bar and guide assembly should
be measured and modifications to be carried if required.
Stipulated period of Work: Day -6 to Day-20 - Work has to be going on in 02 passes parallelly by two separate expert team. These teams are separate than the manpower engaged in field gauging job. Daily observation report and corresponding rectification status to be submitted. Rectification job has to be
carried out as per reports/findings of experts engaged by departmental authority. | 72 | NUMBER | 72,000 ₹72,000 Lowest | 1,22,400 ₹1,22,400 |
| 1.05 | EERM SYSTEM CHECKING
The complete emitting electrode rapping mechanism including its pin wheel, thrust pad, bottom bearing, hammer assembly etc are to be thoroughly inspected. Replacement / Fitting of missing components, bearings, Pin wheel, thrust bearing, thrust pad, bottom bearing, hammer assembly of all the rapping mechanism, if required after checking for ESP Fields. The shaft straightness are to be checked and if necessary the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done as per expert engaged by departmental authority. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective Emitting frame position correctly.
Stipulated Period of Work: Day -6 to Day-20 # The work has to be going on in 02 passes simultaneously by two separate expert team. These teams are separate than the manpower engaged in field gauging job. Each day findings and its rectification report has to be submitted. Rectification job to be strictly carried out as per reports/observations of expert engaged by departmental authority. | 72 | NUMBER | 72,000 ₹72,000 Lowest | 1,22,400 ₹1,22,400 |
| 1.06 | GDRM SYSTEM CHECKING
Checking and rectification of GD Screen rapping system thoroughly. Replacement, Repair & Alignment of rapping shafts, bearings, hammer assembly of all the rapping mechanism, if required after checking. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective shock bar position correctly for GDRM. The shaft straightness are to be made and if necessary the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done.
Stipulated Period of Work: Day -10 to Day-16 - The work has to be going on in 02 passes simultaneously by two separate expert team. Daily report and respective rectification status to be
submitted to controlling department. Rectification job has to be strictly carried out as per reports/findings of experts engaged by departmental authority. | 8 | NUMBER | 16,000 ₹16,000 Lowest | 24,800 ₹24,800 |
| 1.07 | SHAFT INSULATOR SYSTEM CHECKING
Cleaning & inspection of all Shaft insulator and its heater thoroughly & replacement or repair if found damaged. Heater resistance to be recorded. Proper box up after the job with gasket replacement if found damaged. Cleaning of shaft insulators to be done in 02 phases (after water washing and again before final box up by petrol).
Stipulated Period of Work: Day -8 to Day-18 - Thorough cleaning by petrol to ensure full dryness. Separate group of electricians is to be engaged. Each day finding report and necessary rectification
report to be submitted. Rectification job to be strictly carried out as per reports of expert engaged by departmental authority. | 72 | NUMBER | 1,08,000 ₹1,08,000 Lowest | 1,72,800 ₹1,72,800 |
| 1.08 | SUPPORT INSULATOR SYSTEM CHECKING
Cleaning & inspection of all Support insulator and its heater thoroughly & replacement or repair if found damaged. Heater resistance to be recorded. Proper box up after the job with gasket replacement if found damaged. Cleaning of Support insulators to be done in 02 phases (after water washing and again before final box up by petrol).
Stipulated Period of Work: Day -8 to Day-18 - Thorough cleaning by petrol to ensure full dryness. Separate group of electricians is to be engaged. Each day finding report and necessary rectification
report to be submitted. Rectification job to be strictly carried out as per reports of expert engaged by departmental authority. | 288 | NUMBER | 72,000 ₹72,000 Lowest | 1,29,600 ₹1,29,600 |
| 1.09 | HOPPER HEATER CHECKING
Hopper Heater field junction box cleaning, inspection, tightness of terminals. Hopper heater. Replacement / Repair & Cleaning of Hopper Heater. Hopper heater IR checking, resistance measurement, current measurement etc. & all the final readings (after overhauling) to be submitted to departmental authority. Replacement of Hopper heater if found damaged OR faulty with new one. Checking of heater jackets for any ash accumulation and damage followed by repairing of the same. Replacement of Hopper heater power cable from field junction box to support insulator JB if found faulty OR damaged. Cable will be provided by WBPDCL.
Stipulated Period of Work: Day-10 to Day-20. Same electrician groups to be engaged as for Support & Shaft insulators. Each day finding report and simultaneous rectification report to be submitted. Rectification job to be strictly carried out as per reports/findings of expert engaged by departmental authority. | 400 | NUMBER | 1,00,000 ₹1,00,000 Lowest | 1,80,000 ₹1,80,000 |
Tender Value
₹40.9 L
EMD Value
₹81,852
Closing Date
17 Jun 2026, 3:00 pmClosed
The General Manager, SGTPP WBPDCL
Administrative Building, SgTPP, PO-Manigram, Dist- Murshidabad, Pin-742237
Service contract for Overhauling job of Unit-4 ESP (4 passes, 72 Nos. Fields) in 2026 at SGTPP.
2026_WBPDC_1000738_2
WBPDCL/SGTPP/NIT/E3883/25-26
Open Tender
Support/Maintenance Service
Lump-sum
25 days
SgTPP, WBPDCL
Qualification required as per NIT and Tender documents signed and stamped in each page as a token of acceptance.
3 documents required · 3 mandatory
₹0
₹81,852
Yes
Contract Cell, SGTPP
27 Aug 2026
23 May 2026
19 Jun 2026
23 May 2026
17 Jun 2026
23 May 2026
1 Jun 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1U#4 ESP OVERHAULING JOB | |||||
| 1.01 | DRY CLEANING WORK
Thorough Dry cleaning of ESP starting from ESP inlet funnel up to ESP outlet funnel, all ESP hoppers, Gas distribution Screens, all emitting electrodes and collecting plates and other allied zones.
Suspension zones in between CERM/EERM Frame and ESP ceiling to be checked and cleaned properly. After de-synchronization of Unit, all hopper doors (288 Nos.) are to be opened for smooth removal of ash. After completion of total overhauling job, all hoppers must be checked finally and cleaning & removal of ash/clinker or any other foreign material if persist. Then all hopper manholes have to be boxed up properly by total replacement of old gaskets with new ones with adhesive and tightness checking.
Stipulated Period of Work: Day-2 to Day-4- 04 Number of separate manpower gangs to be engaged for working at a time in 04 ESP Passes. Report to be submitted to department by 4th day evening or 5th day morning. | 1 | LUMPSUM | 52,000 | ₹52,000 |
| 1.02 | WATER JET CLEANING WORK
Thoroughly HP Water Jet washing from top to Bottom of ESP internals (72 Nos Fields), including all hoppers, collecting plates, emitting electrodes and other allied zones till metallic surface exposed and completely free of ash deposits. Four number HP Pumps must be put in service in parallel from 04 (Four) different Water outlet points provided at site. At the time of water washing if any chocking found in the hoppers, same shall be cleared immediately. Suspension zone in between CERM/EERM Frame and ESP ceiling to be checked and cleaned properly. All necessary equipment including sufficient number of hose, nozzles and four nos booster pumps (discharge pressure of 4-5 Kg/sq.cm) will be arranged by party.
Stipulated Period of Work: Day-3 to Day-9 - Two separate groups of manpower should be engaged at a time by round the clock without fail until finish this job within stipulated time. Daily work progress and respective checking report to be submitted within 48 Hrs of Unit De-Synchronise. After water washing of all the ESP internals, detailed field inspection of all fields to be carried out by the party along with experts engaged by departmental authority and share the findings to departmental authority. | 1 | LUMPSUM | 1,57,000 | ₹1,57,000 |
| 1.03 | INTERNAL CHECKING AND RECTIFICATION
Field gauging of each Collecting Plate to maintain a gap of 400mm by Go Gauge (72 Nos of ESP fields in A, B, C & D Path). Job to be carried out by specialized separate manpower, experienced to perform identical job at ESP. Re-fitting of new spacers if required. Each & Every emitting frame alignment shall
be checked thoroughly.
Stipulated Period of Work: Day -6 to Day-20 -Simultaneous work must be going on in 02 passes at a time by two separate expert team. Everyday findings and its rectification report to be submitted. Rectification job to be strictly carried out as per reports/findings of expert engaged by departmental authority. | 72 | NUMBER | 1,020 | ₹73,440 |
| 1.04 | CERM SYSTEM CHECKING
The complete collecting electrode rapping mechanism with all its plain bearing, inner arm, outer arm, shock bar, shock pad, Shock Bar Guide Plate, shock bar guide assembly (Rapping and non-rapping side) and its attachment, rapping shafts, Pin wheel, hammer assembly, Anvil Bar and corresponding fasteners, Guide angle, PL attachments of Rapping and non-rapping sides are to be thoroughly inspected and necessary replacement/ modification/Fitting of missing components and tack welding of bolts are to be done as per the instruction of experts engaged by departmental authority.
The Rapping shaft straightness are to be checked and if necessary, the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done as per expert engaged by departmental authority. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective shock bar position correctly for CRM. Straightening of misaligned shock bar and its assembly are to be done and gap between the electrodes to be maintained as per expert engaged by departmental authority. The clearance between the shock bar and guide assembly should
be measured and modifications to be carried if required.
Stipulated period of Work: Day -6 to Day-20 - Work has to be going on in 02 passes parallelly by two separate expert team. These teams are separate than the manpower engaged in field gauging job. Daily observation report and corresponding rectification status to be submitted. Rectification job has to be
carried out as per reports/findings of experts engaged by departmental authority. | 72 | NUMBER | 1,020 | ₹73,440 |
| 1.05 | EERM SYSTEM CHECKING
The complete emitting electrode rapping mechanism including its pin wheel, thrust pad, bottom bearing, hammer assembly etc are to be thoroughly inspected. Replacement / Fitting of missing components, bearings, Pin wheel, thrust bearing, thrust pad, bottom bearing, hammer assembly of all the rapping mechanism, if required after checking for ESP Fields. The shaft straightness are to be checked and if necessary the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done as per expert engaged by departmental authority. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective Emitting frame position correctly.
Stipulated Period of Work: Day -6 to Day-20 # The work has to be going on in 02 passes simultaneously by two separate expert team. These teams are separate than the manpower engaged in field gauging job. Each day findings and its rectification report has to be submitted. Rectification job to be strictly carried out as per reports/observations of expert engaged by departmental authority. | 72 | NUMBER | 1,020 | ₹73,440 |
| 1.06 | GDRM SYSTEM CHECKING
Checking and rectification of GD Screen rapping system thoroughly. Replacement, Repair & Alignment of rapping shafts, bearings, hammer assembly of all the rapping mechanism, if required after checking. Rapping shaft rotation to be checked and ensure for every hammer hitting position with respective shock bar position correctly for GDRM. The shaft straightness are to be made and if necessary the bend/worn out shaft to be repaired/replaced and complete alignment of the shaft to be done.
Stipulated Period of Work: Day -10 to Day-16 - The work has to be going on in 02 passes simultaneously by two separate expert team. Daily report and respective rectification status to be
submitted to controlling department. Rectification job has to be strictly carried out as per reports/findings of experts engaged by departmental authority. | 8 | NUMBER | 1,930 | ₹15,440 |
| 1.07 | SHAFT INSULATOR SYSTEM CHECKING
Cleaning & inspection of all Shaft insulator and its heater thoroughly & replacement or repair if found damaged. Heater resistance to be recorded. Proper box up after the job with gasket replacement if found damaged. Cleaning of shaft insulators to be done in 02 phases (after water washing and again before final box up by petrol).
Stipulated Period of Work: Day -8 to Day-18 - Thorough cleaning by petrol to ensure full dryness. Separate group of electricians is to be engaged. Each day finding report and necessary rectification
report to be submitted. Rectification job to be strictly carried out as per reports of expert engaged by departmental authority. | 72 | NUMBER | 1,449 | ₹1,04,328 |
| 1.08 | SUPPORT INSULATOR SYSTEM CHECKING
Cleaning & inspection of all Support insulator and its heater thoroughly & replacement or repair if found damaged. Heater resistance to be recorded. Proper box up after the job with gasket replacement if found damaged. Cleaning of Support insulators to be done in 02 phases (after water washing and again before final box up by petrol).
Stipulated Period of Work: Day -8 to Day-18 - Thorough cleaning by petrol to ensure full dryness. Separate group of electricians is to be engaged. Each day finding report and necessary rectification
report to be submitted. Rectification job to be strictly carried out as per reports of expert engaged by departmental authority. | 288 | NUMBER | 255 | ₹73,440 |
| 1.09 | HOPPER HEATER CHECKING
Hopper Heater field junction box cleaning, inspection, tightness of terminals. Hopper heater. Replacement / Repair & Cleaning of Hopper Heater. Hopper heater IR checking, resistance measurement, current measurement etc. & all the final readings (after overhauling) to be submitted to departmental authority. Replacement of Hopper heater if found damaged OR faulty with new one. Checking of heater jackets for any ash accumulation and damage followed by repairing of the same. Replacement of Hopper heater power cable from field junction box to support insulator JB if found faulty OR damaged. Cable will be provided by WBPDCL.
Stipulated Period of Work: Day-10 to Day-20. Same electrician groups to be engaged as for Support & Shaft insulators. Each day finding report and simultaneous rectification report to be submitted. Rectification job to be strictly carried out as per reports/findings of expert engaged by departmental authority. | 400 | NUMBER | 255 | ₹1,02,000 |
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.15 MB
TD2.pdf
Tender Documents • 0.82 MB
BOQ_2518215.xls
BOQ • 0.38 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .