Loading…
Loading…
Tender Value
₹15.8 L
EMD Value
₹15,800
Closing Date
5 Sept 2026, 6:00 pm
The Executive Engineer, Public Health Works Division, GWSSB, Bhuj
Construction of 2 Nos. RCC Pump Room at Mau HW, Construction of 5 Nos. Pump Cabin at Various TW/S.H. W, Lowering, Laying and Jointing PVC Pipeline for Technical Villages Under Mandvi Part-2 RWSS (Under M & R 2026-27
337292
08/2026-27
Open
Civil Works - Water Works
Works
Kutch
7 documents required · 7 mandatory
₹900
Executive Engineer, Public Health Works Division, Bhuj
₹15,800
20 Aug 2026
20 Aug 2026
20 Aug 2026
5 Sept 2026
20 Aug 2026
Estimated Cost: - Rs. –
Executive Engineer
Public Health Works Division,
Gujarat Water Supply & Sewerage Board
Volume-III, PRICE BID
Bid Documents for “Construction of 2 Nos. RCC Pump Room at Mau HW, Construction
of 5 Nos. Pump Cabin at Various TW/S.H. W, Lowering, Laying and Jointing PVC
Pipeline for Technical Villages Under Mandvi Part-2 RWSS (Under M & R 2026-27.)”
SCHEDULE C .......................................Error! Bookmark not defined.
BREAK UP FOR INTERIM PAYMENTS...............................................
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
Name of Work: - “Construction of 2 Nos. RCC Pump Room at Mau HW, Construction of
5 Nos. Pump Cabin at Various TW/S.H. W, Lowering, Laying and Jointing PVC Pipeline
for Technical Villages Under Mandvi Part-2 RWSS (Under M & R 2026-27.)”
The bidder shall quote his firm and fixed price for the entire work under this Contract,
defined in more details in various sections of this bid document.
(1) The rates and prices shall be submitted in the electronic formats given by n-
procure which is called Schedule-B. Rates and prices received in any other
formats will be rejected and the Bids will be disqualified.
(2) It will be entirely at the discretion of the Employer to accept or reject the
bidder’s proposal, without giving any reasons whatsoever and the bidder shall
not be permitted to withdraw his bid on this account.
free supplied from the by client.
(4) In Schedule-B the Bidder shall quote prices for the items on lump sum / unit
rate as called for against the BOQ item.
in Schedule-B only will be considered for price evaluation & shall form a part of
the Contract Agreement.
(7) Wherever for a particular item the quantities have been specified payment
shall be on unit rate basis and unit variation in quantity will be paid with pro
(8) Each item is to be individually priced online and the amounts shall be added up
prices shall be left blank except where the item description requires the item
to be priced on "as applicable” basis. The item shall not be priced if it is “not
applicable” to the bidder’s design, in which case the bidder shall add the
words “NOT APPLICABLE”. The wording in the item description is for subject
matter guidance only; clause references are indicative only and all other
relevant clauses shall also be referred to. The prices shall allow for all the
works covered under the bid and all liabilities and contractual obligations
whether separately specified or not. Items against which no prices are quoted
shall not be separately paid for and the bidder shall be deemed to have
covered the cost of execution of such items (according to the requirements of
the bid document) in the prices quoted for other items.
for satisfactory working/safety of the system as specified, will not be
separately paid for by the Employer when executed and shall be deemed to be
already covered by other items and rates listed in the price sheets No extra
payment shall be given for any item which is required to complete and perform
fixed, during the pendency of the Contract. In case of any discrepancy noted in
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
carried over and arithmetic corrections if any will be considered for financial
evaluation of the bid.
(11) Schedule ‘D gives the basis of interim payment for construction of works.
(12) The bidder shall be deemed to have allowed in his price for provision,
maintenance and final removal of all temporary works of whatsoever nature
required for construction including temporary bunds, diverting water, pumping,
de-watering etc. for the proper execution of works. The rates shall also be
deemed to include any works and setting out that may be required to be
carried out for laying out of all the works involved.
(13) Prices shall be filled online only.
Contract, the Specifications and other sections of these bid documents and
these documents are to be taken as mutually explanatory of one another.
(15) The bidder shall interpret the data furnished and carry out any additional
survey work, or investigation work required at his own cost.
(16) The prices quoted shall also include the cost of materials utilized for testing.
(17) The bidder should acquaint himself with the site conditions including the
access to Work site. The successful bidder shall have to make suitable access to
work sites at his own cost. These accesses will be used by the other contractors
working for GWSSB.
and the prices shall include all the equipment’s / materials / accessories and
services required as per the specifications. The bidder shall fill in the price
schedule furnished.
(19) 1% of the value of work will be deducted from the Running bill against labour
cess which is non-refundable.
(20) Third Party Inspection / CSC agency will be deployed by GWSSB and charges of
the same will be borne by GWSSB.
(21) Any expenditure incurred by inspection/ CSC agency for the work misinformed
by the contractor and charges of inspection/ CSC agency without any work due
to misinformation shall be recovered from the contractor.
(22) The rates should be quoted Exclusive of GST, but inclusive of all other taxes and cess
or levies or duties which shall not be paid extra. While GST will be paid for
admissible part of actual work done at the approved tender rates and tender
conditions of price variation. GST shall be paid as per prevailing rates at the
time of payment. The TDS shall be deducted at source as per provision of IT
rules and GWSSB Policy.
(23) The rates should be quoted Exclusive of GST and all other taxes as per Volume-I
(B), General Conditions of Contract, Clause No.
(24) The rates quoted shall be Exclusive of GST, which shall be paid extra. The TDS
shall be deducted at source as per provision of IT rules and GWSSB policy.
(25) The Bidders shall have to quote the rates in this tender keeping in view of the
GST. The Complete responsibility of taxes, duties, levies rests with the
Contractor/Agency only.
(26) The process requires that the bidder shall quote his price for the work
shall remain firm and fix during the entire period of performance of the
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
contract except price variation allowed for supply of MS/DI/PVC/GI pipe as per
Volume-IB Clause No. 59, General Conditions of Contract.
(27) Payment shall be made for the components for which lump sum prices are
quoted, as per the schedule of payment. Total cost will be worked out on the
basis of work done of individual items and rates quoted against those particular
(28) Royalties: The contractor shall be liable to pay the royalty of the quarried
materials/ minerals used in the construction of works at the rates specified in
the Narmada Water Resources, Water Supply & Kalpsar Dept. Resolution No.
GEN-2010-595- (6)- M.I.Cell ( K-1) Dt. 29-4-2011 ( Gujarati Version Copy
enclosed) and shall be recovered from the running bills of the work from time
to time and remaining amount if any shall be recovered from the final bill
before releasing the security deposit of the work. The contractor shall furnish
the statement showing the quantity of quarried materials / minerals from
whom purchased (with full address of the seller) and copies of the bills for
purchase to the Executive Engineer of the in charge of the work. The
contractor shall also furnish such additional information as regards royalty
payment to the competent authority.
(29) Agency shall have to take Insurance policy and intimate to GWSSB along with
the evidence within time limit. In case of noncompliance entire responsibility
shall be rest with the agency and required amount shall be recovered from any
due amount of the agency.
(30) GWSSB can recover penalty amount from the agency for not taking the
insurance. Though the penalty amount is recovered, responsibility of the
agency for taking insurance shall be continued and will not be escaped from
the responsibility.
(31) The contractor shall apply fair means of stock maintenance and shall adopt
accounting standard as may be prescribed under GST Act as applicable in the
state of Gujarat. For arriving at the difference in procurement prices due to
introduction of GST it will be open for the Board to ask for original invoices,
lorry receipt, weigh bridge slips, payment details and such other documents as
may be required for the purpose.
(32) The claim of contractor regarding GST shall have to be backed by documentary
evidence substantiating the actual payment of tax duly certified by the
competent tax authority. The final decision regarding the quantum of claim
amount to be recovered or reimbursed shall be of the competent authority of
the GWSSB and shall be binding on the contractor.
Signature of contractor Executive Engineer
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
Bidders are required to fill up all the blank spaces in this Bid Form.
THE EXECUTIVE ENGINEER,
PUBLIC HEALTH WORKS DIVISION,
SUB “Construction of 2 Nos. RCC Pump Room at Mau HW, Construction of 5 Nos.
Pump Cabin at Various TW/S.H. W, Lowering, Laying and Jointing PVC Pipeline for
Technical Villages Under Mandvi Part-2 RWSS (Under M & R 2026-27.)”
The bidder shall quote his firm and fixed price for the entire work under this Contract,
defined in more details in various sections of this bid document.
1. Having visited the site and examined the Bid Documents, Drawings, Conditions of
Schedules etc. including Addenda/Amendments to the above, for the execution of the
above Contract, we the undersigned offer to design, Engineer, procure, construct,
complete, commission, operate and maintain the whole of the said works for 5 years
from the date of commissioning including defects liability period as given in Conditions
of Contract and in conformity with the drawings, conditions of Contract, specifications,
Nos.__________ (insert numbers) for Lump sum fixed price of
for Construction including free trial run for three months or such other sum as may be
ascertained in accordance with the conditions.
2. I/We agree that
a) if we fail to provide required facilities to the Employer’s representative or any other
person/Agency by the Employer to perform on his behalf for carrying out the
inspection and testing of materials and workmanship.
b) if we incorporate into the Works, materials before they are tested and approved by
the Engineer’s representative.
c) if we fail to deliver pure water of required quantity according to the
conditions/stipulations of the Contract, the Engineer will be at liberty to take any
action including termination of Contract and impose at his absolute discretion any
penalties, and/or reject the work.
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
3. We undertake, if our Bid is accepted, to complete and deliver the works in accordance
with the Contract within _________ months, inclusive of monsoons, from the date or
receipt of Letter of Acceptance issued to us by you.
4. We agree to abide by this Bid for a period of 180 days from the Last date of submission
of the bill and it shall remain binding upon us and may be accepted at any time before
the expiry of that period.
5. In the event of our Bid being accepted, we agree to enter into a formal Contract
Agreement with you incorporating the conditions of Contract there to annex but until
such agreement is prepared this Bid together with your written acceptance thereof
shall constitute a binding Contract between us.
6. We agree, if our Bid is accepted, to furnish performance /Security in the forms and of
value specified in the Clause 1 of Volume-IB, “General Conditions of Contract”.
7. We have independently considered the amounts of liquidated damages shown in
Appendix to Bid and agree that they represent a fair estimate of the damages likely to
be suffered by you in the event of the work not being completed by us in time.
8. We understand that you are not bound to accept the lowest or any Bid you may
(Name of the Person)
Company Seal _____________________
Duly authorized to sign Bid for and on behalf of (fill in block capitals)
Witness Signature ___________________________
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
NAME OF SCHEME –
“Construction of 2 Nos. RCC Pump Room at Mau HW, Construction of 5 Nos. Pump
Cabin at Various TW/S.H. W, Lowering, Laying and Jointing PVC Pipeline for Technical
Villages Under Mandvi Part-2 RWSS (Under M & R 2026-27.)”
The bidder shall quote his firm and fixed price for the entire work under this Contract,
defined in more details in various sections of this bid document.
Schedule showing the approximately the materials to be supplied to the contractor from
government stores for the work to be executed and the rate at which they are to be
Description Quantity Unit delivery of
1. The contractor submitting the Tender shall see that the rate in Schedule-A are filled in
by the Engineer in Charge at the time of issue tender.
2. The contractor while submitting the tender shall provide his own arrangement at his
own cost for loading, unloading, and transporting safety to the site of work the cement
stipulated in Schedule-A
3. Binding wire of 15 gauge of thinner gauge required for placing the reinforcement in
position shall be provided at his own cost.
4. All the materials required for the items other than labour in Schedule-A but available
with the dept. will be issued on request to the contractor. (for use in this contract only)
at prevailing market rates or departmental issue rates whichever is higher.
5. All the surplus materials supplied by the deptt. As mentioned in schedule-A should be
handed over to the Department by the contractor at the Govt. stores as directed.
6. The materials mentioned in schedule-A shall have to be checked for their correctness
and soundness by the contractor before taking the delivery of the materials from the
7. Necessary cement will be purchased by the agency at their own cost from open market.
8. The persons of firm submitting the Tender should see that rates in the above schedule
are filled up by the Executive Engineer, on the issue of form prior to the submission of
9. Carting of above materials should be done by contractor at his own cost.
10. Contractor should return the balance materials in good and acceptable condition,
otherwise recovery at the double rates will be affected in view of Clause 12.4.
Signature of contractor Executive Engineer
P. H. Works Dn., G.W.S.S.B
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
AS per Attached Schedule-B
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
1. As mentioned in the Conditions of contract, the Contract being a lump sum type
turnkey Contract on EPC basis, the provision of measurement will be applicable only for
the assessment of value of work done for inclusion in any interim certificate for part
payment to the Contractor.
2. The Schedule specifies the procedure for all such assessment of the items specified in
3. Each item of Schedule-B has been divided into broad components. The Employer's
Representative shall assess the value of each component as indicated in paragraph
4. Percentages are indicated against each component of each items specified in Schedule
B, based on the Employer's best appreciation of the value of the component as related
to the total costs of the concerned item as whole. A head titled (any other item(s)) is
included in each breakdown of schedule and the tenderer shall at the time of tendering
indicate any additional items which he considers necessary but cannot be covered by
any of the heads indicated in the breakup.
5. The percentage breakup as indicated in the Schedule may differ from that
corresponding to the tenderer’s scheme and design and he should take this into account
while quoting his lump sum prices for the items specified in Schedule-B.
6. The contractor shall, after approval of his detailed designs and drawings furnish to the
Employer's Representative an initial bill of quantities to all major items, to be reviewed
and updated periodically with the Employer's Representative. This bill of quantities will
be used for assessment of percentage progress of the component at any stage. By
measurement jointly taken by the Employer's Representative and the Contractor,
mutually agreed and entered in the measurement books in the form and by the method
approved by the Employer's Representative, and signed jointly by both the parties.
7. Before carrying out the work by the contractor in this tender, the actual survey-based
pipeline hydraulics for the pipeline network has to be approved at the competent level,
and the quantity of pipes has to be obtained accordingly. Payment will not be made for
the quantity of additional pipes other than the approved quantity i.e., Excess pipes
that do not have to be laid.
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
BREAK UP FOR INTERIM PAYMENTS
(CIVIL, MECHANICAL, INSTRUMENTATION & ELECTRICALWORKS)
Item Description of Items Percentage Payment to
a On receipt of materials at project site 65 % of Quoted rate
b On Excavation, Lowering, laying and Jointing 20 % of Quoted rate
c On Hydraulic testing 5 % of Quoted rate
d On refilling and disposal of surplus stuff 5 % of Quoted rate
e After commissioning 5 % of Quoted rate
g On receipt of materials on site 70 % of Quoted rate
h On erection 20 % of Quoted rate
i On Hydraulic testing 5 % of Quoted rate
j After commissioning 5 % of Quoted rate
3 PUMPING STATION / STAFF QUARTERS /
MATERIAL SAFETY ROOM / PUMP ROOM
a. On approval of Designs 2.0 % of Quoted rate
b. On completion of Excavation & base slab 18.0 % of Quoted rate
c. On completion of vertical wall up to plinth 20.0 % of Quoted rate
d. Full supporting structure incl. ring beam and top 15.0 % of Quoted rate
e. On completion of pump house incl. fixing doors 10.0 % of Quoted rate
f. Plastering inside & outside with epoxy paint etc 10.0 % of Quoted rate
(completed with all respects)
g. Painting of letters, MS ladder pipe, railing and all 15 % of Quoted rate
miscellaneous items such as snowcem paints in
three coats etc. (completed with all respects)
h. After Completion 10 % of Quoted rate
4 GROUND (UNDERGROUND) LEVEL SERVICE
RESERVOIRS/SUMPS
a. On approval of designs 2 % of Quoted rate
b. On completion of excavation and base slab 18 % of Quoted rate
c. On completion of vertical wall and braces 20 % of Quoted rate
d. Full supporting structure including column, ring 15 % of Quoted rate
beam and completion of top slab / dome
e. Plastering inside & outside with epoxy etc. 10 % of Quoted rate
f. Procurement and fixing of inlet, outlet, washout, 15 % of Quoted rate
overflow pipes, valves, specials, chambers, lighting
arrester conductor and specials at site
g. Water level indictor, painting of letters, M.S 10 % of Quoted rate
ladder, pipes, railing and all miscellaneous items
such as snowed paint in three coats etc (Completed
with all respect) including water tightness test
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
h. On hydraulic testing 10 % of Quoted rate
5 Elevated Storage Reservoir
a On submission of Designs 2.5% of Quoted rate
b On approval of Designs 2.5% of Quoted rate
c On Completion of excavation 7.5% of Quoted rate
d On completion of staging height up to reservoir 22.5% of Quoted rate
e On Completion of Floor Reservoir 22.5% of Quoted rate
f On Completion of walls of Reservoir 22.5% of Quoted rate
g On Completion of Roof of reservoir with all related 20.0% of Quoted rate
6 All Electro-mechanical works and
Instrumentation
a. On supply of material at work site in good 65% of Quoted rate
b. On erection of Equipment 25% of Quoted rate
c. On completion of Testing & Commissioning of 5% of Quoted rate
d. Satisfactory running of system. 5% of Quoted rate
7 WATER TREATMENT PLANT (CONVENTIONAL)
(I) Site survey and subsoil investigations 1% of Quoted rate
Completion of field surveys and subsoil 25%
investigations and de-mobilization from site of
Submission of surveys and soil investigation reports 75%
and acceptance by the Engineer
(II) Detailed designs and construction documents 2% of Quoted rate
Substantial completion, submission and approval by 60%
the Engineer of the designs, drawings and
construction documents for all major items of work
Submission and approval by the Engineer of the 40%
final designs and construction documents for all
remaining and miscellaneous construction details
and working drawings
(III) Inlet chamber 4% of Quoted rate
Excavation 5.0%
Works up to Ground Level 10.0%
RCC works up to top including all supply and fixing 60%
of related materials
Finishing all surfaces including painting 15.0%
Hydraulic test 5.0%
Commissioning 5.0%
(IV) Raw water channel from inlet chamber To 2%
1 Excavation for supporting structure 5.0%
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
Works up to G.L. 15.0%
All RCC works including all supply and fixing of 30.0%
related materials upto floor level
Completion of all civil works including all supply 35.0%
and fixing of related materials
Hydraulic test 10.0%
Commissioning 5.0%
V) Flash Mixer 4 % Quoted rate
Excavation 5.0%
Works up to Ground Level 10.0%
R.C.C. works up to top including all supply and 60.0%
fixing of related materials
Finishing all surfaces including painting 15.0%
Hydraulic test 5.0%
Commissioning 5.0%
VI) Clariflocculator Works 2 0 % Quoted rate
RCC wall upto flooring including all supply and 30%
fixing of related materials
RCC wall upto 1st lift (50% of the design height) 5%
RCC wall lupto 2nd lift (100% of the design height) 10%
RCC wall upto top including all supply and fixing of 20%
related materials
Remaining all works including all supply and fixing 15%
of related materials
Hydraulic testing of water retaining structures 5%
Finishing of all surfaces and painting coating etc. 5%
Commissioning 5%
VII) RCC Channel from Clariflocculator to Filter Bed 5% Quoted rate
RCC Works for floor slab including all supply and 40%
fixing of related materials
Completion of all works and finishing all surfaces 50.0%
including painting, supply and fixing of related
Hydraulic test 5.0%
Commissioning 5.0%
VIII ) Filtration Works 40% Quoted rate
RCC wall upto filter floor level including pure 10%
water channel floor slab
Up to operating platform 15%
RCC wall upto top slab including all laboratory and 30%
Completion of all the remaining works including 30%
back wash tank and related arrangements; all
supply and fixing of related materials
Price Bid – Mandvi Part-2 RWSS
Volume-III, PRICE BID
Hydraulic testing/liquid retaining structures 5%
Commissioning 5%
IV ) Chemical Works 15%Quotedrate
Excavation 5.0%
RCC/Masonry work below plinth 15%
RCC work upto 1st floor 30%
RCC works upto roof slab 20.0%
Completion of the remaining works including 30%
painting, finishing; supply and fixing of related
X Miscellaneous Works
THESE WORKS INCLUDES
By pass CI pipeline from Inlet chamber to clear
CI pipeline from flash mixer to clariflocculator.
Pure water CI pipeline from filter beds to clear
water sump. 5% Quoted rate
Bye pass CI pipeline from clariflocculator to clear
CI wash water pipeline from proposed wash water
tank to filter beds.
Wash water CI pipeline from filtration bed to
XI All other related and required works as directed 2% of Quoted rate
Submission of as built drawings and training to staff
8 Valve chambers
A On completion works as per approved drawings 95% of Quoted rate
B After commission of system 5% of Quoted rate
9 Miscellaneous work
A All other items such as encasing, columns support 80% of quoted rate on
for culvert, pipe bridges for Canal /Drain/Khadi completion of works
crossing, internal roads, railway/highway crossing,
Anchor/thrust blocks, steel bridge for pipe
crossing, Construction of Compound Wall &
Repairing and Renovation work etc.
B On commissioning of the system 20% of quoted rate
10 Operation and Maintenance
A Every month in equal instalment based on quoted
prices of O & M will be paid
Note: - Any Changes to be made in all above Payment Schedule can be decided by Chief
Engineer, Zone - 4, Kachchh and it shall be binding to the contractor.
Price Bid – Mandvi Part-2 RWSS
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
NIT mau mandvi part-2.pdf
2.VOL 1 A Technical Bid.pdf
3 VOL 1 B GCC.pdf
4 VOL 2 A Extent of Work (1).pdf
5 VOL 2 B Tech Spec Civil (1).pdf
7 VOL 2 D Data Sheet (1).pdf
8 VOL 3 Price bid.pdf
9 VOL 4 Drawings.pdf
schedule B.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].