Assistant Executive Engineer, NH subdivision, Kol
O/o the Assistant Executive Engineer, NH subdivision, Kollam
NH 744 GENERAL Restoration estimate for rectifying damaged BT surface after laying UG cable by KSEB at Mukkada jn on NH 744 General Civil Work-General Civil Work
2026_PWD_880552_1
PWD/NH/TR/14018/2024_5_1_1/1
Open Tender
Civil Works - Highways
Item Rate
O/o the Assistant Executive Engineer, NH subdivisi
Please refer Tender documents.
8 documents required · 8 mandatory
₹335
Yes
Yes
16 Oct 2026
16 Oct 2026
29 Oct 2026
16 Oct 2026
26 Oct 2026
16 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1Restoration | |||||
| 1.001 | 3.6:Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m | 4.7 | cum | - | - |
| 1.002 | OD103868/2024-2025:Driving down sand piles 200 mm Dia. 75mm c/c to approved lines and levels through various pipes with cc shoes at bottom after keeping the shoe and removing the steel pipe and filling the space with sand and consolidated well for required depth , compacting layer by layer with dptl. officers at site. | 14.14 | metre | - | - |
| 1.003 | 4.1.B.1:Construction of granular sub-base by providing graded material, spreading in uniform layers with a motor grader on a prepared surface, mixing by mix in-place method with rotavator at OMC, and compacting with a vibratory roller to achieve the desired density, complete as per clause 401. Grading-V - For sub-base cum drainage layer - Mix in Place Method | 2.4 | cum | - | - |
| 1.004 | 4.12:Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density. | 1.44 | cum | - | - |
| 1.005 | 5.1.a:Providing and applying primer coat with bitumen emulsion ( SS) on prepared surface of granular Base including clearing of road surface and spraying primer at the rate of 0.70 - 1.0 kg/sqm using mechanical means. | 9.6 | sqm | - | - |
| 1.006 | 5.2.a:Providing and applying tack coat with bitumen emulsion( RS) using emulsion pressure distributor at the rate of 0.20 - 0.30 kg per sqm on the prepared bituminous surface cleaned with mechanical broom. | 27 | sqm | - | - |
| 1.007 | 5.4.2a:Dense Graded Bituminous Macadam:- For Grading II (26.5 mm nominal size) Providing and laying dense graded bituminous macadam with 80-100 TPH HMP producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder (VG 30) @ 4.0 to 4.5 percent by weight of total mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRTH specification clause No. 505 complete in all respects. | 0.6 | cum | - | - |
| 1.008 | OD152302/2026-2027:Providing and laying bituminous concrete with 80-100 TPH hot mix plant producing an average output of 75 tonnes per hour using crushed aggregates of specified grading, premixed with a bituminous binder( VG 30) @ 5.4 percent of mix and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher with sensor control to the required grade, level, and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH specification clause No. 507 complete in all respects For Grading - II (13.2 mm Nominal Size) | 0.6 | cum | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.04 MB
viewsbd.pdf
Tender Documents • 1.63 MB
BOQ_1497502.xls
BOQ • 0.30 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .