Tender Value
₹4.3 L
EMD Value
₹4,300
Closing Date
21 Apr 2026, 6:00 pmClosed
Deputy Municipal Commissioner Gandhidham Municipal Corporation
Construction of Rain basera At Maheswari (Meghvad)Samajvadi near Area , Navjivan Society Sector-7 ,Gandhidham.(2nd Attempt)
291993
2025-26
Open
Civil Works - Buildings
Kutch
3 documents required · 3 mandatory
₹600
Municipal Commissioner, GANDHIDHAM Municipal Corporation
₹4,300
31 Mar 2026
31 Mar 2026
31 Mar 2026
21 Apr 2026
31 Mar 2026
Quantities Estimated Rates
Item estimated but In Figure
Item of work Unit According to
No. may be more or In Figure With
less Estimated Quantities
[1] 4.060 Excavation for foundation up to 1.5 Meter depth including sorting out and stacking of 121.72 122.94 Cum
useful materials and disposing of excavated stuff up to 50 Meter lead (a) For Loose or
[2] 4.560 Excavation for foundation up to 1.5 Meter depth including sorting out and stacking of 155.77 157.33 Cum
useful materials and disposing of excavated stuff up to 50 Meter lead
(b) Dense or hard soil
[3] 4.560 Excavation for foundation upto 1.5 m depth including sorting out and stacking of 264.44 267.08 Cum
useful materials and disposing off the excavated stuff upto 50 Meter lead.(C) Hard
[4] 1.010 Excavation for foundation upto 1.5 m depth including sorting out and stacking of 621.26 627.47 Cum
useful materials and disposing off the excavated stuff upto 50 Meter lead.(D) Soft
rock not requiring Blasting
[5] 6.180 Filling available excavated earth (excluding rock) in trenches. plinth, sides of 135.56 136.92 Cum
foundations etc. in layers not exceeding 20 cm. in depth consolidating each
disposited layer by ramming and watering.
[6] 14.160 Filling in foundation and plinth with murrum or selected soil in layers of 20cm. 267.08 269.75 Cum
thickness including watering, ramming and consolidating etc. complete
[7] 2.960 Providing and laying cement concrete 1:3:6 (1 Cement : 3- coarse sand :6- crushed 3219.00 3251.19 Cum
stone aggregate 40 mm. Nominal size) and curing complete excluding cost of form
work in :(a) Foundation and plinth
[8] 5.790 Providing and laying controlled cement concrete M.250 and curing complete 4385.00 4428.85 Cum
including the cost of formwork and reinforcement for reinforced concrete work in
(A) Foundations, footings, Base of columns and Mass concrete. (upto 10 ton)
RCC Column Footin
[9] 0.800 Providing laying Controlled cement concrete M-200 and curing complete including 6058.00 6118.58 Cum
the cost of form work and excluding cost of reinforcement for reinforced concrete
RCC Lintels Ground Floor
[10] 3.640 Providing and laying controlled cement concrete M.200 and curing complete 6193.32 6255.25 Cum
including the cost of formwork and reinforcement for reinforced concrete work in
(C) Slabs,landing,shelves,Balconies Lintels, Beams, Girders and Cantilever upto
[11] 3.450 Providing laying Controlled cement concrete M-200 and curing complete including 6376.00 6439.76 Cum
the cost of form work and excluding cost of reinforcement for reinforced concrete
work in : RCC Slabs & Landings Ground Floor
[12] 1.100 Providing laying controlled cement concrete M-200 and curing complete including 6682.00 6748.82 Cum
the cost of form work and excluding cost of reinforcement for reinforced concrete
work in : RCC Chhajja/Sill Ground Floor
[13] 1390.800 Providing TMT Bar FE 500/500D reinforcement for R.C.C. work including bending, 76.52 77.29 Kg.
binding, and placing in position complete upto floor two level. Ground Floor
[14] 2.700 Providing and laying controlled cement concrete M.200 and curing complete 7516.00 7591.16 Cum
including the cost of formwork and reinforcement for reinforced concrete work in
(D) Columns, Pillars posts and struts upto floor two level. (upto 10 ton)
[15] 0.360 Brick work using common burnt clay building bricks having crushing strength not 4203.06 4245.09 Cum
less than 35 kg./Sq.Cm. in foundation and plinth in Cement Mortar 1:5. (1- Cement : 5 -
fine sand)(B) Conventional
[16] 16.620 Brick work using common burnt clay building bricks having crushing strength not 4481.99 4526.81 Cum
less than 35 kg./Sq.Cm. in superstructure above plinth level upto floor two level in
Cement Mortar 1:5. (1- Cement : 5 -fine sand)(B) Conventional
[17] 57.300 Providing 15 mm thick cement plaster in single coat on fair side Brick/concrete walls 209.72 211.82 Sqm
for interior plastering up to floor two level and finished even and smooth in & Extra
over items for finishing with a floating coat of neat cement slurry. (ii) Cement mortar
1:4 ( 1 cement : 4 sand) Ground Floor
[18] 32.160 Providing 10 mm thick cement plaster in single coat on ceiling and soffit of stair for 171.17 172.88 Sqm
interior plastering up to floor two level and finished even and smooth in & Extra over
items for finishing with a floating coat of neat cement slurry for plastering on ceiling
and soffits of stairs up to floor two level instead of plastering on walls. (ii) Cement
mortar 1:4 ( 1 cement : 4 sand) Ground Floor
[19] 93.020 20 mm thick sand faced cement plaster on walls upto height 10 meters above ground 312.56 315.69 Sqm
level consisting of 12 mm thick backing coat of c.m. 1:3 (1:cement - 3:sand) and 8 mm
thick finishing coat of c.m. 1:1 (1:cement - 1:sand) etc. complete
[20] 2.730 Providing and laying polished kota stone slab 25mm thick in risers of steps,skirting 1132.82 1144.15 Sqm
Dedo and pillars laid on 10mm thick cement mortar 1:3 (1-Cement : 3 coarse sand)
and jointed with gray cement slury mixed with pigment to match the shade of slab
including rubbing and polishing etc. complete. (upto 10 ton)
[21] 22.750 Providing and laying Vitrified tiles 8 to 10 mm thick , 24'' x 24'' in flooring treads of 1109.27 1120.36 Sqm
steps and landing laid on a bed of 12mm thick cement mortar 1:3 (1-cement :
coarse sand ) finishing with flush pointing in white cement.
[22] 1.900 Providing and laying white glazed tiles of 6 mm thick in skirting of steps and dado on 1116.32 1127.48 Sqm
10 mm thick cement plaster 1:3 (1:Cement - 3-Coarse Sand) and jointed with white
[23] 2.100 Provoding and fixing flush door shutters, solid core construction with frame of first 1811.62 1829.74 Sqm
class hardwood with cross board and face veneer or plywood face panels, including
anodised alluminium butt hinges with necessary screws. (B) Non-decorative typ and
block board core anodised alluminium butt hinges in flush door shutters (2) 35 mm
Quantities Estimated Rates
Item estimated but In Figure
Item of work Unit According to
No. may be more or In Figure With
less Estimated Quantities
[24] 7.200 Providing and fixing standared extruded of alluminium section of size 63.50 x 38.10 x 1278.03 1290.81 Sqm
1.95 mm @ Wt 1.094Kg / Rmt with colour anodized alluminium frame with 5 mm
thick transparent bronze colour tinted float glass with colour anodized alluminium
frame for ventilation with 5 mm thick frosted glass as details etc complete
[25] 89.460 Applying two coats of Birla or Asian acrylic lapy ( putty) & two coats of primer of 40.19 40.59 Sqm
approved brand and manufacture on new wall surface to give an even shade
including thoroughly brushing the surface free from mortar dropping and other
foreign matter and sand papered smooth.
[26] 57.300 Wall painting (two coats) with plastic emulsion paint of approved brand and 83.53 84.37 Sqm
manufacture on undecorated wall surface to give an even shade including throughly
brushing the surface free from mortar droppings and other foreign matter and sand
papered smooth.
[27] 32.160 Wall painting (two coats) with plastic emulsion paint of approved brand and 89.00 89.89 Sqm
manufacture on undecorated wall surface to give an even shade including throughly
brushing the surface free from mortar droppings and other foreign matter and sand
papered smooth. for ceiling and Soffit
[28] 93.020 Finishing wall with weather proof exterior emulsion paint on wall surface (two coats) 119.07 120.26 Sqm
to give an required shape even shade after thoroughly brushing the surface to remove
all dirt, and remains of loose powdered materials.etc complete
[29] 6.000 Point wiring for Light / Fan/ Bell/ Primary Point with 2-1.5 sq. mm & earth wire of 326.00 329.26 Pt
1.5 sq. mm (green) both are of ISI marked 1.1 kv grade FRLS PVC insulated multi
strand copper wires upto max length of 10 mt, in below type of pipe erected with 6A
Tissino Type ISI marked flush type switch / bell push and accessories erected on
Metal / PVC/Wooden Box covered with 3 mm thick PC(Polycarbonate)
/Acrylic/Laminated sheet. with necessary Lamp holder/ceiling rose / H.D.Connector
as directed. (a) with medium class Rigid PVC pipe and accessories erected flushed on
wall/ceiling complete
[30] 1.000 [III] For 16A Plug and 16 amp switch with 2-4 sq.mm Cu. Wire with 2.5 sq.mm ( 782.00 789.82 Pt
green) earthing wire from mcb d b board.(a) with medium class Rigid PVC pipe and
accessories erected flushed on wall/ceiling complete, CAT-III
[31] 2.000 Providing and erecting Approved make Ceiling fan with double ball bearing ISI mark 1581.00 1596.81 Pt
with condenser A.C. 23OV.50 c/s.1200 mm. sweep complete, canopy erected on
existing hook or clamp with earthing. [Make shall be approved by Engineer in charge]
[32] 4.000 Supplying and erecting LED indoor fittings with LEDs of wattage 0.2 Watt to 0.5 Watt 293.00 295.93 Each
assembled on single MCPCB, with housing used as a heat sink shall be made of thick
sheet Steel conforming to IS: 513/CRCA/ aluminium die cast powder coated and high
U.V. & corrosion resistance with diffuser with company mark/name 160V to 270V,
Power Factor more than 0.95, THD < 15%,
CCT 3000 K to 6500K, Luminaire efficacy> 85 lumens/watt ,LED LED driver
efficiency > 85 % ( fitting required LM-79 & LM-80 Certificates)(NOTE: Below
description have shown ranges of Wattage capacity of LED fittings.The Engineer
incharge may select any wattage capacity between the ranges shown.) (A) Tube Light
with integral driver (iii) 18-20 Watts, Surge - 2KV,IP-20, conventional 4 feet Cat-lll
I / We am/are willing to carry out the work at % above / below (in figure) percent above / below (in words) the estimated rates
mentioned above amount of my/our tender works out as under :-
Estimated amount put to Tender
Deduct _______% Below
Rupees in Words
Estimated amount put to Tender
Add _______% above
Rupees in Words
I/We hereby declare that I/We have visited the site and fully acquianted self / ourselves with the local situation regarding
I/We hereby declare that I/We have carefully studied the conditions of contract, detailed technical specifications and other tender
Dated Signature CITY ENGINEER
the Contractor. GANDHIDHAM MUNICIPAL
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
04. GR ALL.pdf
05. GR ARC.pdf
06. BUILDING SPECIFICATIONS.pdf
07. TEST REQUIRE FOR CONSTRUCTION MATERIAL.pdf
08. Self Declaration Format.pdf
09. Non-Blacklisted Format.pdf
10. SD EMD GR 25-26.pdf
01. SBD.pdf
02. SCHEDULE B.pdf
Download all tender documents and submit your bid