Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.6 LAccepted-AOC | L1 | Accepted-AOC L1 BIDDER | |
| 2 | L2₹3.6 L+₹2.4 L (14.7%)Accepted-AOC | L2 | Accepted-AOC L1 BIDDER | |
| 3 | L4₹3.6 L+₹9.3 L (57.8%)Accepted-AOC | L4 | Accepted-AOC L1 BIDDER | |
| 4 | L5₹3.6 L+₹21.9 L (135.6%)Accepted-AOC | L5 | Accepted-AOC L1 BIDDER | |
| 5 | L3₹24.5 L+₹8.3 L (51.6%)Rejected-Finance | L3 | Rejected-Finance L3 BIDDER |
| Sl No | Description | Qty | Unit | R BROS L4 | VASANTH L2 | KBR ENGG & PAINTING L3 | N ASOKAN PAINTING CONTRACTOR L1 | DEVIBALA ENGINEERING CONTRACT L5 |
|---|---|---|---|---|---|---|---|---|
| 1.00Standardization of rates (SR) for Painting of MS Structurals, Pipelines and Equipments at TNPL Main Site & LSFM for the year 2025-2026 (The rate quoted is exclusive of GST) | ||||||||
| 1.01 | Taking delivery of paint, erection of scaffolding if necessary,cleaning the existing surfaces, applying One coat of Red Oxide Primer paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels. | 25,000 | SQUARE METRE | 33 ₹8,25,000 | 31.5 ₹7,87,500 | 35 ₹8,75,000 | 26 ₹6,50,000 Lowest | 50 ₹12,50,000 |
| 1.02 | Taking delivery of paint, erection of scaffolding if necessary,cleaning the existing surfaces, applying Two Coats of Red Oxide Primer paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels. | 1,500 | SQUARE METRE | 60 ₹90,000 | 29.5 ₹44,250 Lowest | 50 ₹75,000 | 30.5 ₹45,750 | 80 ₹1,20,000 |
| 1.03 | Taking delivery of paint,erection of scaffolding if necessary,cleaning the existing surfaces, applying one coat of Synthetic Enamel paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels. | 2,000 | SQUARE METRE | 35 ₹70,000 | 25.5 ₹51,000 Lowest | 35 ₹70,000 | 28 ₹56,000 | 60 ₹1,20,000 |
| 1.04 | Taking delivery of paint,erection of scaffolding if necessary,cleaning the existing surfaces, applying Two Coats of Synthetic Enamel paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels. | 18,000 | SQUARE METRE | 65 ₹11,70,000 | 41.5 ₹7,47,000 | 60 ₹10,80,000 | 36 ₹6,48,000 Lowest | 90 ₹16,20,000 |
| 1.05 | Taking delivery of paint,erection of scaffolding if necessary,cleaning the surfaces, applying One Coat of Aluminium paint conforming to IS 2932-1974 to withstand heat 60-120 Degree centigrade.Cost includes labour&incidental at all levels. | 2,230 | SQUARE METRE | 35 ₹78,050 | 27.5 ₹61,325 Lowest | 35 ₹78,050 | 28 ₹62,440 | 90 ₹2,00,700 |
| 1.06 | Taking delivery of paint,erection of scaffolding if necessary,cleaning the surfaces, applying Two Coats of Aluminium paint conforming to IS 2932-1974 to withstand heat 60-120 Degree centigrade.Cost includes labour&incidental at all levels. | 4,500 | SQUARE METRE | 70 ₹3,15,000 | 36 ₹1,62,000 | 60 ₹2,70,000 | 34 ₹1,53,000 Lowest | 110 ₹4,95,000 |
| Sl.NoBidder Name | ||||||||
| 1 | R BROS (BID ID -1282420) | 15,08,009 | Not Quoted | - | - | - | - | - |
| 2 | DEVIBALA ENGINEERING CONTRACT (BID ID -1282054) | 15,08,009 | Not Quoted | - | - | - | - | - |
Tender Value
Refer Docs
EMD Value
₹7,500
Closing Date
1 Apr 2025, 3:00 pmClosed
GM (TOS and Stores)
TOS Kagithapuram
Standardization of rates (SR) for Painting of MS Structurals, Pipelines and Equipments at TNPL Main Site and LSFM for the year 2025-2026
2025_TNPL_533435_1
TNPL / TOS / U 1/242513006851
Open Tender
Painting works
Tender cum Auction
365 days
TOS Kagithapuram
Kindly upload the documents substantiating the PQ criteria
3 documents required · 3 mandatory
₹0
₹7,500
13 Aug 2025
18 Mar 2025
2 Apr 2025
18 Mar 2025
1 Apr 2025
18 Mar 2025
Amount
Standardization of rates (SR) for Painting of MS Structurals, Pipelines and Equipments at TNPL Main Site & LSFM for the year 2025-2026 (The rate quoted is exclusive of GST)
Taking delivery of paint, erection of scaffolding if necessary,cleaning the existing surfaces, applying One coat of Red Oxide Primer paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels.
Taking delivery of paint, erection of scaffolding if necessary,cleaning the existing surfaces, applying Two Coats of Red Oxide Primer paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels.
Taking delivery of paint,erection of scaffolding if necessary,cleaning the existing surfaces, applying one coat of Synthetic Enamel paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels.
Taking delivery of paint,erection of scaffolding if necessary,cleaning the existing surfaces, applying Two Coats of Synthetic Enamel paint conforming to IS with brush.Cost includes labour and other incidental charges etc at all levels.
Taking delivery of paint,erection of scaffolding if necessary,cleaning the surfaces, applying One Coat of Aluminium paint conforming to IS 2932-1974 to withstand heat 60-120 Degree centigrade.Cost includes labour&incidental at all levels.
Taking delivery of paint,erection of scaffolding if necessary,cleaning the surfaces, applying Two Coats of Aluminium paint conforming to IS 2932-1974 to withstand heat 60-120 Degree centigrade.Cost includes labour&incidental at all levels.
Bidder Name
Amount in Words
R BROS (BID ID -1282420)
DEVIBALA ENGINEERING CONTRACT (BID ID -1282054)
N ASOKAN PAINTING CONTRACTOR (BID ID -1280310)
KBR ENGG & PAINTING (BID ID -1280994)
VASANTH (BID ID -1276389)
VASANTH (BID ID -1276389)
KBR ENGG & PAINTING (BID ID -1280994)
R BROS (BID ID -1282420)
DEVIBALA ENGINEERING CONTRACT (BID ID -1282054)
stage.html
html • 0.05 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .