| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹10.1 CrAdmitted-Finance B1 10 MUKUNDRAO AMBEDKAR ROAD SION MUMBAI MAHARASHTRA 400037 | MUMBAI | MUMBAI | MAHARASHTRA | 400037 | ₹10.1 Cr | L1 | Admitted-Finance |
| 2 | Rejected-Technical | - | - | Rejected-Technical Reject |
| Sl No | Description | Qty | Unit | Pyara Singh and Sons L1 |
|---|---|---|---|---|
| 1.00CIVIL WORK | ||||
| 1.01PART-A, ESTIMATE FOR THE CONSTRUCTION OF PORT STATION AT BADAYUN ROAD LOCATION ( BAREILLY NAGAR NIGAM ) AS PER DRAWING | ||||
| 1.02 | EXCAVATION IN FOUNDATION IN ORDINARY SOIL IN FOUNDATION & SUPERSTRUCTUREAS MENTIONED IN THE DRAWING ( 2.1 ) | 143.1 | CUM | 123.2 ₹17,629.92 |
| 1.03 | SUPPLY & LAYING OF PLAIN CEMENT CONCRETE WITH 40 MM BRICK BALLAST OR STONE BALLAST AND COARSE SAND 1:4:8 IN FOUNDATION AND FLOORS COMPLETED INCLUDING ALL MATERIAL AND LABOUR. ( 4.1.8 ) | 47.47 | CUM | 6,494 ₹3.1 L |
| 1.04 | SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS FOOTINGS & COLUMNS BELOW PLINTH ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE EXCLUDING CENTERING , SHUTTERING, & REINFORCEMENT STEEL ( 5.1.2 ) | 11.07 | CUM | 8,636.5 ₹95,606.06 |
| 1.05 | SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS, FLOORS ABOVE PLINTH LEVEL ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE SHUTTERING, CENTERING & BINDING OF STEEL BUT EXCLUDING THE SUPPLY CUTTING & BENDING OF STEEL ( 5.2.2 ) | 59.46 | CUM | 10,360.5 ₹6.2 L |
| 1.06 | CENTERING & SHUTTERING WORK IN COLUMNS FOOTING INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.1 ) | 28.8 | SQM | 371 ₹10,684.80 |
| 1.07 | CENTERING & SHUTTERING WORK IN FLOORS & SLABS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.3 ) | 33 | SQM | 859 ₹28,347 |
| 1.08 | CENTERING & SHUTTERING WORK IN COLUMNS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.6 ) | 64.8 | SQM | 859 ₹55,663.20 |
| 1.09 | SUPPLY AND FIXING OF 450 X 450 X 12 THK ANCHOR PLATES WITH SUITABLE SIZE OF HOLD FAST, EMBEDDED IN CONCRETE OF COLUMN AND BEAM PORTIONS TO ATTACH THE 50 X 50 SQUARE PIPE SUPPORT ( 10.16.1 ) | 228 | KG | 185.2 ₹42,225.60 |
Tender Value
Refer Docs
EMD Value
₹42 L
Closing Date
13 Feb 2026, 4:00 pmClosed
RAJEEV KUMAR RATHI
NAGAR NIGAM BAREILLY
Request for Proposal (RFP) for Construction, Supply, Installation and Commissioning of 4 Solid Waste Transfer Stations with 1-Year Defect Liability, and for Operation, Maintenance and Waste Transportation to Sathrapur Site for 5 Years in Bareilly Cit
2026_DOLBU_1111542_1
27/P.A./S.W.M./N.N./2025-26 Date-29.01.2026
Open Tender
Miscellaneous Services
1825 days
BAREILLY
Please refer Tender documents.
2 documents required · 2 mandatory
₹11,800
Bareillye-tender.com
₹42 L
RAJEEV KUMAR RATHI (EXECUTIVE ENGINEER)
17 Mar 2026
2 Feb 2026
13 Feb 2026
2 Feb 2026
13 Feb 2026
6 Feb 2026
4 Feb 2026
CIVIL WORK
PART-A, ESTIMATE FOR THE CONSTRUCTION OF PORT STATION AT BADAYUN ROAD LOCATION ( BAREILLY NAGAR NIGAM ) AS PER DRAWING
EXCAVATION IN FOUNDATION IN ORDINARY SOIL IN FOUNDATION & SUPERSTRUCTUREAS MENTIONED IN THE DRAWING ( 2.1 )
SUPPLY & LAYING OF PLAIN CEMENT CONCRETE WITH 40 MM BRICK BALLAST OR STONE BALLAST AND COARSE SAND 1:4:8 IN FOUNDATION AND FLOORS COMPLETED INCLUDING ALL MATERIAL AND LABOUR. ( 4.1.8 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS FOOTINGS & COLUMNS BELOW PLINTH ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE EXCLUDING CENTERING , SHUTTERING, & REINFORCEMENT STEEL ( 5.1.2 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS, FLOORS ABOVE PLINTH LEVEL ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE SHUTTERING, CENTERING & BINDING OF STEEL BUT EXCLUDING THE SUPPLY CUTTING & BENDING OF STEEL ( 5.2.2 )
CENTERING & SHUTTERING WORK IN COLUMNS FOOTING INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.1 )
CENTERING & SHUTTERING WORK IN FLOORS & SLABS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.3 )
CENTERING & SHUTTERING WORK IN COLUMNS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.6 )
SUPPLY AND FIXING OF 450 X 450 X 12 THK ANCHOR PLATES WITH SUITABLE SIZE OF HOLD FAST, EMBEDDED IN CONCRETE OF COLUMN AND BEAM PORTIONS TO ATTACH THE 50 X 50 SQUARE PIPE SUPPORT ( 10.16.1 )
SUPPLY & FIXING OF 25 MM DIA & 750 LONG FOUNDATION BOLTS WITH 03 NOS NUTS TO BE FIXED DURING CONCRETING WITH THE HELP OF TAME PLATE COMPLETE WITH ALL MATERIAL & REQUIRED LABOUR. ( 10.16.1 )
SUPPLY & LAYING OF BRICK WORK 450 THICK WITH 1:4 CEMENT SAND MORTAR IN FOUNDATION AND PLINTH INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.1.1 )
SUPPLY & LAYING OF BRICK WORK THICK WITH 1:4 CEMENT SAND MORTAR IN SUPERSTRUCTURE AND INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.4.1 )
12 MM THICK PLASTER WITH 1:4 CEMENT SAND MORTAR ON WALLS INCLUDING THE SUPPLY OF ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER & SMOOTH FINISHING OF WORK. ( 13.4.1 )
SUPPLY, CUTTING & BENDING OF REINFORCEMENT STEEL IN COLUMNS , FOOTINGS , FLOORS & SLABS ALL COMPLETE AT ITS PROPER LOCATION AS PER DRAWING ( 5.22.6 )
SUPPLY & FIXING OF GLAZED WALL TILES OF SUITABLE SIZE UP TO THE HT OF 2 MTR COMPLETE IN ALL RESPECT & IN PROPER LINE AND LEVELS ( 11.37 )
SUPPLY FEBRICATION & FIXING OF MS SQ PIPE 50 X 50 SIZE TO PREPARE STRUCTURAL COLUMNS & BEAMS ( 200 X 200 ) , TRUSS, PURLINS , MAIN GATES ETC INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK. ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 300 X 300 ) SIZE AT COLUMNS & BEAMS JUNCTION POINT INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 200 X 200 ) SIZE AT FOR JOINING ALL 4 PIPES OF COLUMNS & BEAMS FROM OUTER SIDE INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY OF PPGI / CGS SHEETS FOR COVERING ALL AROUND THE PORT STATION WALLS & ALSO FOR ROOF COVERING ABOVE TRUSS PORTION INCLUDING PROPER OVERLAPPING COMPLETE IN ALL RESPECT AS PER REQUIREMENTS ( 12.1.3 )
SUPPLY , FEBRICATION AND FIXING OF 12 MM THK M.S PLATES FOR MOVING PORTABLE COMPACTOR INSIDE THE PORT STATION ( 10.16.1 )
SUPPLY AND GROUTING OF CHEMICAL ANCHOR FASTENERS TO HOLD THE CHEQURED PLATES AT ITS PLACE AS PER DRAWING COMPLETE IN ALL RESPECTS
SUPPLY FEBRICATION AND FIXING OF GRATING ( 25 X 5 ) MS FLATS WITH GRATING SUPPORTS ( MS 50 X 50 X 5 ANGLE ) FOR LEACHATE DRAIN INSIDE PORT STATION ( 10.16.1 )
SUPPLY , FEBRICATION AND FIXING OF MS PLATE ( 2 M X 2 M ) COVER WITH ITS SUPPORT ( MS 50 X 50 X 5 ANGLE ) OVER MAIN HOLE OF PORT STATION ( 10.16.1 )
PAINTING ALL AROUND PORT STATION OVER PLASTERED SURFACE WITH 2 COATS OF WATER PROOF CEMENT PAINT FOR PROVIDING SMOOTH FINISH INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR PROPER COMPLETION OF WORK ( 13.44 )
ELECTRICAL WORK INSIDE THE PORT STATION / OFFICE / GUARD ROOM / TOILET ETC INCLUDING THE SUPPLY AND FIXING OF PANELS / MCB / CHANGEOVER / OPEN WIRING / PREPARING OF CIRCUITS / ALL LIGHTS & FANS ETC COMPLETE IN ALL RESPECT.
1.5 SQ MM WIRE ( POLYCAB FRLS )
2.5 SQ MM WIRE ( POLYCAB FRLS )
10 SQ MM COPPER CABLE
MCB BOX ( HAVELLS )
65 APM MCB ( HAVELLS )
MODULAR BOXES
16 AMP SWITCHES ( HAVELLS )
16 AMP SOCKETS ( HAVELLS )
FAN REGULATORS ( HAVELLS )
CONDUITS
POWER SWITCHES & SOCKET SET ( HAVELLS )
LED LIGHTS & HOLDERS ( HAVELLS )
HALOGENS 1500 WATT
FANS ( CROMPTON GREAVES )
CHANGE OVERS WITH CUTOUTS
25 SQ MM GREEN CABLE FOR EARTHING
LABOUR ELECTRIFICATION WORK
PART-B, ESTIMATE FOR THE CONSTRUCTION OF TRANSFER STATION AT PILIBHIT BYE PASS NEAR ROHILKHAND UNIVERSITY LOCATION ( BAREILLY NAGAR NIGAM ) AS PER DRAWING
DISMENTALLING OF EXISTING REINFORCED CONCRETE FLOOR / PAEDESTALS ETC AS PER REQUIREMENTS BEFORE STARTING THE EXCAVATION AND ALL COMPLETE ( 15.3 )
DISMENTALLING OF EXISTING 9" THK BRICK WALLS ETC AS PER REQUIREMENTS BEFORE STARTING THE EXCAVATION AND ALL COMPLETE ( 15.7.4 )
EXCAVATION IN FOUNDATION IN ORDINARY SOIL IN FOUNDATION & SUPERSTRUCTUREAS MENTIONED IN THE DRAWING ( 2.1 )
SUPPLY & LAYING OF PLAIN CEMENT CONCRETE WITH 40 MM BRICK BALLAST OR STONE BALLAST AND COARSE SAND 1:4:8 IN FOUNDATION AND FLOORS COMPLETED INCLUDING ALL MATERIAL AND LABOUR. ( 4.1.8 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS FOOTINGS & COLUMNS BELOW PLINTH ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE EXCLUDING CENTERING , SHUTTERING, & REINFORCEMENT STEEL ( 5.1.2 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS, FLOORS ABOVE PLINTH LEVEL ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE SHUTTERING, CENTERING & BINDING OF STEEL BUT EXCLUDING THE SUPPLY CUTTING & BENDING OF STEEL ( 5.2.2 )
CENTERING & SHUTTERING WORK IN COLUMNS FOOTING INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.1 )
SUPPLY AND FIXING OF 450 X 450 X 12 THK ANCHOR PLATES WITH SUITABLE SIZE OF HOLD FAST, EMBEDDED IN CONCRETE OF COLUMN AND BEAM PORTIONS TO ATTACH THE 50 X 50 SQUARE PIPE SUPPORT ( 10.16.1 )
SUPPLY & FIXING OF 25 MM DIA & 750 LONG FOUNDATION BOLTS WITH 03 NOS NUTS TO BE FIXED DURING CONCRETING WITH THE HELP OF TAME PLATE COMPLETE WITH ALL MATERIAL & REQUIRED LABOUR. ( 10.16.1 )
SUPPLY & LAYING OF BRICK WORK 450 THICK WITH 1:4 CEMENT SAND MORTAR IN FOUNDATION AND PLINTH INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.1.1 )
SUPPLY & LAYING OF BRICK WORK THICK WITH 1:4 CEMENT SAND MORTAR IN SUPERSTRUCTURE AND INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.4.1 )
12 MM THICK PLASTER WITH 1:4 CEMENT SAND MORTAR ON WALLS INCLUDING THE SUPPLY OF ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER & SMOOTH FINISHING OF WORK. ( 13.4.1 )
SUPPLY, CUTTING & BENDING OF REINFORCEMENT STEEL IN COLUMNS , FOOTINGS , FLOORS & SLABS ALL COMPLETE AT ITS PROPER LOCATION AS PER DRAWING ( 5.22.6 )
SUPPLY FEBRICATION & FIXING OF MS SQ PIPE 200 X 200 & 50 X 50 SIZE TO PREPARE STRUCTURAL COLUMNS & BEAMS ( 200 X 200 ) , TRUSS, PURLINS , MAIN GATES ETC INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK. ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 300 X 300 ) SIZE AT COLUMNS & BEAMS JUNCTION POINT INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY OF PPGI / CGS SHEETS FOR COVERING ALL AROUND THE PORT STATION WALLS & ALSO FOR ROOF COVERING ABOVE TRUSS PORTION INCLUDING PROPER OVERLAPPING COMPLETE IN ALL RESPECT AS PER REQUIREMENTS ( 12.1.3 )
SUPPLY , FEBRICATION AND FIXING OF 12 MM THK M.S PLATES FOR MOVING PORTABLE COMPACTOR INSIDE THE PORT STATION ( 10.16.1 )
SUPPLY AND GROUTING OF CHEMICAL ANCHOR FASTENERS TO HOLD THE CHEQURED PLATES AT ITS PLACE AS PER DRAWING COMPLETE IN ALL RESPECTS
SUPPLY FEBRICATION AND FIXING OF GRATING ( 25 X 5 ) MS FLATS WITH GRATING SUPPORTS ( MS 50 X 50 X 5 ANGLE ) FOR LEACHATE DRAIN INSIDE PORT STATION ( 10.16.1 )
SUPPLY , FEBRICATION AND FIXING OF MS PLATE ( 2 M X 2 M ) COVER WITH ITS SUPPORT ( MS 50 X 50 X 5 ANGLE ) OVER MAIN HOLE OF PORT STATION ( 10.16.1 )
PAINTING ALL AROUND PORT STATION OVER PLASTERED SURFACE WITH 2 COATS OF WATER PROOF CEMENT PAINT FOR PROVIDING SMOOTH FINISH INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR PROPER COMPLETION OF WORK ( 13.44 )
ELECTRICAL WORK INSIDE THE PORT STATION / OFFICE / GUARD ROOM / TOILET ETC INCLUDING THE SUPPLY AND FIXING OF PANELS / MCB / CHANGEOVER / OPEN WIRING / PREPARING OF CIRCUITS / ALL LIGHTS & FANS ETC COMPLETE IN ALL RESPECT.
1.5 SQ MM WIRE ( POLYCAB FRLS )
2.5 SQ MM WIRE ( POLYCAB FRLS )
10 SQ MM COPPER CABLE
MCB BOX ( HAVELLS )
65 APM MCB ( HAVELLS )
MODULAR BOXES
16 AMP SWITCHES ( HAVELLS )
16 AMP SOCKETS ( HAVELLS )
FAN REGULATORS ( HAVELLS )
CONDUITS
POWER SWITCHES & SOCKET SET ( HAVELLS )
HALOGENS 1500 WATT
FANS ( CROMPTON GREAVES )
CHANGE OVERS WITH CUTOUTS
25 SQ MM GREEN CABLE FOR EARTHING
LABOUR ELECTRIFICATION WORK
PART-C, ESTIMATE FOR THE CONSTRUCTION OF TRANSFER STATION AT BADAYUN ROAD LOCATION ( BAREILLY NAGAR NIGAM ) AS PER DRAWING
EXCAVATION IN FOUNDATION IN ORDINARY SOIL IN FOUNDATION & SUPERSTRUCTUREAS MENTIONED IN THE DRAWING ( 2.1 )
SUPPLY & LAYING OF PLAIN CEMENT CONCRETE WITH 40 MM BRICK BALLAST OR STONE BALLAST AND COARSE SAND 1:4:8 IN FOUNDATION AND FLOORS COMPLETED INCLUDING ALL MATERIAL AND LABOUR. ( 4.1.8 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS FOOTINGS & COLUMNS BELOW PLINTH ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE EXCLUDING CENTERING , SHUTTERING, & REINFORCEMENT STEEL ( 5.1.2 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS, FLOORS ABOVE PLINTH LEVEL ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE SHUTTERING, CENTERING & BINDING OF STEEL BUT EXCLUDING THE SUPPLY CUTTING & BENDING OF STEEL ( 5.2.2 )
CENTERING & SHUTTERING WORK IN COLUMNS FOOTING INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.1 )
CENTERING & SHUTTERING WORK IN FLOORS & SLABS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.3 )
CENTERING & SHUTTERING WORK IN COLUMNS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.6 )
SUPPLY AND FIXING OF 450 X 450 X 12 THK ANCHOR PLATES WITH SUITABLE SIZE OF HOLD FAST, EMBEDDED IN CONCRETE OF COLUMN AND BEAM PORTIONS TO ATTACH THE 50 X 50 SQUARE PIPE SUPPORT ( 10.16.1 )
SUPPLY & FIXING OF 25 MM DIA & 750 LONG FOUNDATION BOLTS WITH 03 NOS NUTS TO BE FIXED DURING CONCRETING WITH THE HELP OF TAME PLATE COMPLETE WITH ALL MATERIAL & REQUIRED LABOUR. ( 10.16.1 )
SUPPLY & LAYING OF BRICK WORK 450 THICK WITH 1:4 CEMENT SAND MORTAR IN FOUNDATION AND PLINTH INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.1.1 )
SUPPLY & LAYING OF BRICK WORK THICK WITH 1:4 CEMENT SAND MORTAR IN SUPERSTRUCTURE AND INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.4.1 )
12 MM THICK PLASTER WITH 1:4 CEMENT SAND MORTAR ON WALLS INCLUDING THE SUPPLY OF ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER & SMOOTH FINISHING OF WORK. ( 13.4.1 )
SUPPLY, CUTTING & BENDING OF REINFORCEMENT STEEL IN COLUMNS , FOOTINGS , FLOORS & SLABS ALL COMPLETE AT ITS PROPER LOCATION AS PER DRAWING ( 5.22.6 )
SUPPLY FEBRICATION & FIXING OF MS SQ PIPE 50 X 50 SIZE TO PREPARE STRUCTURAL COLUMNS & BEAMS ( 200 X 200 ) , TRUSS, PURLINS , MAIN GATES ETC INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK. ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 300 X 300 ) SIZE AT COLUMNS & BEAMS JUNCTION POINT INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 200 X 200 ) SIZE AT FOR JOINING ALL 4 PIPES OF COLUMNS & BEAMS FROM OUTER SIDE INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY OF PPGI / CGS SHEETS FOR COVERING ALL AROUND THE PORT STATION WALLS & ALSO FOR ROOF COVERING ABOVE TRUSS PORTION INCLUDING PROPER OVERLAPPING COMPLETE IN ALL RESPECT AS PER REQUIREMENTS ( 12.1.3 )
SUPPLY , FEBRICATION AND FIXING OF 12 MM THK M.S PLATES FOR MOVING PORTABLE COMPACTOR INSIDE THE PORT STATION ( 10.16.1 )
SUPPLY AND GROUTING OF CHEMICAL ANCHOR FASTENERS TO HOLD THE CHEQURED PLATES AT ITS PLACE AS PER DRAWING COMPLETE IN ALL RESPECTS
SUPPLY FEBRICATION AND FIXING OF GRATING ( 25 X 5 ) MS FLATS WITH GRATING SUPPORTS ( MS 50 X 50 X 5 ANGLE ) FOR LEACHATE DRAIN INSIDE PORT STATION ( 10.16.1 )
SUPPLY , FEBRICATION AND FIXING OF MS PLATE ( 2 M X 2 M ) COVER WITH ITS SUPPORT ( MS 50 X 50 X 5 ANGLE ) OVER MAIN HOLE OF PORT STATION ( 10.16.1 )
PAINTING ALL AROUND PORT STATION OVER PLASTERED SURFACE WITH 2 COATS OF WATER PROOF CEMENT PAINT FOR PROVIDING SMOOTH FINISH INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR PROPER COMPLETION OF WORK ( 13.44 )
ELECTRICAL WORK INSIDE THE PORT STATION / OFFICE / GUARD ROOM / TOILET ETC INCLUDING THE SUPPLY AND FIXING OF PANELS / MCB / CHANGEOVER / OPEN WIRING / PREPARING OF CIRCUITS / ALL LIGHTS & FANS ETC COMPLETE IN ALL RESPECT.
1.5 SQ MM WIRE ( POLYCAB FRLS )
2.5 SQ MM WIRE ( POLYCAB FRLS )
10 SQ MM COPPER CABLE
MCB BOX ( HAVELLS )
65 APM MCB ( HAVELLS )
MODULAR BOXES
16 AMP SWITCHES ( HAVELLS )
16 AMP SOCKETS ( HAVELLS )
FAN REGULATORS ( HAVELLS )
CONDUITS
POWER SWITCHES & SOCKET SET ( HAVELLS )
LED LIGHTS & HOLDERS ( HAVELLS )
HALOGENS 1500 WATT
FANS ( CROMPTON GREAVES )
CHANGE OVERS WITH CUTOUTS
25 SQ MM GREEN CABLE FOR EARTHING
LABOUR ELECTRIFICATION WORK
PART-D, ESTIMATE FOR THE CONSTRUCTION OF PORT STATION AT BADAYUN ROAD LOCATION ( BAREILLY NAGAR NIGAM ) AS PER DRAWING
EXCAVATION IN FOUNDATION IN ORDINARY SOIL IN FOUNDATION & SUPERSTRUCTUREAS MENTIONED IN THE DRAWING ( 2.1 )
SUPPLY & LAYING OF PLAIN CEMENT CONCRETE WITH 40 MM BRICK BALLAST OR STONE BALLAST AND COARSE SAND 1:4:8 IN FOUNDATION AND FLOORS COMPLETED INCLUDING ALL MATERIAL AND LABOUR. ( 4.1.8 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS FOOTINGS & COLUMNS BELOW PLINTH ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE EXCLUDING CENTERING , SHUTTERING, & REINFORCEMENT STEEL ( 5.1.2 )
SUPPLY & LAYING OF R.C.C IN M-20 GRADE ( 1:1.5:3 ) IN COLUMNS, FLOORS ABOVE PLINTH LEVEL ETC INCLUDING ALL MATERIALS & LABOUR WITH COMPLETE SHUTTERING, CENTERING & BINDING OF STEEL BUT EXCLUDING THE SUPPLY CUTTING & BENDING OF STEEL ( 5.2.2 )
CENTERING & SHUTTERING WORK IN COLUMNS FOOTING INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.1 )
CENTERING & SHUTTERING WORK IN FLOORS & SLABS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.3 )
CENTERING & SHUTTERING WORK IN COLUMNS INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THR PROPER COMPLETION OF WORK ( 5.9.6 )
SUPPLY AND FIXING OF 450 X 450 X 12 THK ANCHOR PLATES WITH SUITABLE SIZE OF HOLD FAST, EMBEDDED IN CONCRETE OF COLUMN AND BEAM PORTIONS TO ATTACH THE 50 X 50 SQUARE PIPE SUPPORT ( 10.16.1 )
SUPPLY & FIXING OF 25 MM DIA & 750 LONG FOUNDATION BOLTS WITH 03 NOS NUTS TO BE FIXED DURING CONCRETING WITH THE HELP OF TAME PLATE COMPLETE WITH ALL MATERIAL & REQUIRED LABOUR. ( 10.16.1 )
SUPPLY & LAYING OF BRICK WORK 450 THICK WITH 1:4 CEMENT SAND MORTAR IN FOUNDATION AND PLINTH INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.1.1 )
SUPPLY & LAYING OF BRICK WORK THICK WITH 1:4 CEMENT SAND MORTAR IN SUPERSTRUCTURE AND INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK.. ( 6.4.1 )
12 MM THICK PLASTER WITH 1:4 CEMENT SAND MORTAR ON WALLS INCLUDING THE SUPPLY OF ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER & SMOOTH FINISHING OF WORK. ( 13.4.1 )
SUPPLY, CUTTING & BENDING OF REINFORCEMENT STEEL IN COLUMNS , FOOTINGS , FLOORS & SLABS ALL COMPLETE AT ITS PROPER LOCATION AS PER DRAWING ( 5.22.6 )
SUPPLY FEBRICATION & FIXING OF MS SQ PIPE 50 X 50 SIZE TO PREPARE STRUCTURAL COLUMNS & BEAMS ( 200 X 200 ) , TRUSS, PURLINS , MAIN GATES ETC INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK. ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 300 X 300 ) SIZE AT COLUMNS & BEAMS JUNCTION POINT INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY, FEBRICATION & FIXING OF M.S PLATES ( 200 X 200 ) SIZE AT FOR JOINING ALL 4 PIPES OF COLUMNS & BEAMS FROM OUTER SIDE INCLUDING ALL MATERIAL & LABOUR REQUIRED FOR THE PROPER COMPLETION OF WORK ( 10.16.1 )
SUPPLY OF PPGI / CGS SHEETS FOR COVERING ALL AROUND THE PORT STATION WALLS & ALSO FOR ROOF COVERING ABOVE TRUSS PORTION INCLUDING PROPER OVERLAPPING COMPLETE IN ALL RESPECT AS PER REQUIREMENTS ( 12.1.3 )
SUPPLY , FEBRICATION AND FIXING OF 12 MM THK M.S PLATES FOR MOVING PORTABLE COMPACTOR INSIDE THE PORT STATION ( 10.16.1 )
SUPPLY AND GROUTING OF CHEMICAL ANCHOR FASTENERS TO HOLD THE CHEQURED PLATES AT ITS PLACE AS PER DRAWING COMPLETE IN ALL RESPECTS
SUPPLY FEBRICATION AND FIXING OF GRATING ( 25 X 5 ) MS FLATS WITH GRATING SUPPORTS ( MS 50 X 50 X 5 ANGLE ) FOR LEACHATE DRAIN INSIDE PORT STATION ( 10.16.1 )
SUPPLY , FEBRICATION AND FIXING OF MS PLATE ( 2 M X 2 M ) COVER WITH ITS SUPPORT ( MS 50 X 50 X 5 ANGLE ) OVER MAIN HOLE OF PORT STATION ( 10.16.1 )
PAINTING ALL AROUND PORT STATION OVER PLASTERED SURFACE WITH 2 COATS OF WATER PROOF CEMENT PAINT FOR PROVIDING SMOOTH FINISH INCLUDING SUPPLY OF ALL MATERIAL AND LABOUR REQUIRED FOR PROPER COMPLETION OF WORK ( 13.44 )
ELECTRICAL WORK INSIDE THE PORT STATION / OFFICE / GUARD ROOM / TOILET ETC INCLUDING THE SUPPLY AND FIXING OF PANELS / MCB / CHANGEOVER / OPEN WIRING / PREPARING OF CIRCUITS / ALL LIGHTS & FANS ETC COMPLETE IN ALL RESPECT.
1.5 SQ MM WIRE ( POLYCAB FRLS )
2.5 SQ MM WIRE ( POLYCAB FRLS )
10 SQ MM COPPER CABLE
MCB BOX ( HAVELLS )
65 APM MCB ( HAVELLS )
MODULAR BOXES
16 AMP SWITCHES ( HAVELLS )
16 AMP SOCKETS ( HAVELLS )
FAN REGULATORS ( HAVELLS )
CONDUITS
POWER SWITCHES & SOCKET SET ( HAVELLS )
LED LIGHTS & HOLDERS ( HAVELLS )
HALOGENS 1500 WATT
FANS ( CROMPTON GREAVES )
CHANGE OVERS WITH CUTOUTS
25 SQ MM GREEN CABLE FOR EARTHING
LABOUR ELECTRIFICATION WORK
10.5 CUM PORABLE COMPACTOR
HOOK LOADER
DETAILS OF CAPEX & OPEX AGAINST TRANSFER STATIONS FOR BAREILLY NAGAR NIGAM OPEX ( OPERATIONAL EXPENSES ) APPROX. SOLID WASTE IN AREA ( MT )
DELA PEER TRANSFER STATION
PILIBHIT BYPASS NEAR ROHILKHAND UNIVERSITY
BADAYUN ROAD - 1 TRANSFER STATION
BADAYUN ROAD - 2 TRANSFER STATION
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 24.41 MB
BOQ_2054060.xls
BOQ • 0.43 MB
Download all tender documents and submit your bid