Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.9 CrAccepted-AOC | ₹3.9 Cr | L1 | Accepted-AOC Overall L1 bideer |
| 2 | L2₹4.2 CrRejected-Finance | ₹4.2 Cr | L2 | Rejected-Finance Not overall L1 bidder |
| 3 | L3₹4.7 CrRejected-Finance PLOT NO 87 SECTOR 24 ATAL NAGAR NAVA RAIPUR RAIPUR CHHATTISGARH 492018 INDIA | RAIPUR | CHHATTISGARH | 492018 | ₹4.7 Cr | L3 | Rejected-Finance Not overall L1 bidder |
| 4 | Rejected-Technical VILL ADISAPTAGRAM PO MOGRA | - | - | Rejected-Technical technically disqualified as neither of the contracts submitted satisfy technical criteria of NIT |
Tender Value
₹4.5 Cr
EMD Value
₹8.9 L
Closing Date
4 Dec 2025, 3:00 pmClosed
The General Manager, SGTPP WBPDCL
The General Manager, SGTPP WBPDCL PO-Manigram, Dist- Murshidabad, Pin-742237
Biennial Maintenance Contract Mechanical Maintenance for TMD-OPH area water package for StgI Stg II and Stage III Units Stg I 2X300MW StgII 2X 500 MW Stage III U5 1x660MW Units SgTPP WBPDCL
2025_WBPDC_932619_1
WBPDCL/SGTPP/NIT/E3736/25-26
Open Tender
Support/Maintenance Service
730 days
SgTPP
Qualification required as per NIT and Tender documents signed and stamped in each page as a token of acceptance
3 documents required · 3 mandatory
₹0
₹8.9 L
Yes
Contract Cell, SGTPP
10 Feb 2026
27 Oct 2025
8 Dec 2025
7 Nov 2025
4 Dec 2025
7 Nov 2025
18 Nov 2025
BMC- Mandatory Jobs
Mechanical Maintenance of all equipments /Systems under TM-OPH area of Stg-I & Stg-II Units (Stg-I, 2X300MW & Stg-II, 2X 500 MW Units), SgTPP including Tools-Tackles & consumables.
Mechanical Maintenance of all equipments /Systems under TM-OPH area of Stg-III Unit (1 X 660 MW Unit), SgTPP including Tools-Tackles & consumables.
BMC- Optional Jobs
Complete overhauling of Stg-I CW pump.
Complete overhauling of Stg-I ACW Pump.
Complete overhauling of Stg-I intake water pump.
Complete overhauling of Stg-I travelling water screen.
Complete overhauling of Stg-I trash rack and all associated systems of intake pump house.
Complete overhauling of stg-I raw water pump.
Complete overhauling of Stg-I service water pump.
Complete overhauling of Stg-I CT make up pump.
Complete overhauling of Drinking Water Pump.
Complete overhauling of Stg-I filter water pump.
Alignment of Stg-I CW pump along with blue matching (if required).
Alignment of Stg-I ACW pump along with blue matching (if required).
Complete overhauling of Stg-I CW trash rack.
Complete overhauling of Stg-I clariflocculator (Mechanical related job).
Complete overhauling of Stg-I jockey pump of fire system.
Complete overhauling of Stg-I hydrant pump of fire system.
Complete overhauling of Stg-I spray pump of fire system.
Complete overhauling of Stg-I reciprocating compressor and pneumatic tank of fire system.
Acid Proof Painting (one coat Epilux 610 Epoxy primer and then two coat Linosol Chlorinated Rubber paint, Berger Pains make).
Synthetic Enamel Painting (one coat Red Oxide primer and then two coat Synthetic enamel paint, Berger make Pains).
Underwater/Wet Zone Painting (one coat epilux 610 epoxy primer and then two coat Epilux 5 Col Tar Epoxy paint, Berger make Pains).
Tit Bit Maintenance of Fire Tender Cooling Tower(U-1,2) area, Chlorination system ( Welding & fittings related).
HDPE pipe joining/Leakage repairing
CPU MB INLET/OUTLET VALVE SERVICING
CPU MB RASIBE INLET/OUTLET VALVE SERVICI
Complete overhauling of stg-II ACW pump.
Stg-II CW Motor Removing Lifting, Placement, Alignment & Blue-matching.
Stg-II ACW Motor Removing,Lifting, Placement, Alignment & Blue-matching.
Complete overhauling of Stg-II Intake water pump.
Complete over hauling of Stg-II Raw Water Pump.
Complete overhauling of Stg-II CTMU Pump.
Complete overhauling of Stg-II DMF Pump.
Complete overhauling of Stg-II jockey pump of fire system.
Complete overhauling of Stg-II hydrant pump of fire system.
Complete overhauling of Stg-II spray pump of fire system.
Tit-Bit maintenance jobs at Stg-II Chlorination system (Welding & Fittings related).
Complete overhauling of trash rack and all associated systems of intake pump house.
Complete overhauling of Stg-II Service Water Pump.
Complete internal checking & repairing of Stg-II DMF.
Internal checking & Servicing of Stg-II RO Plant MB.
ACW line Self cleaning Strainer Cleaning/ Servicining.
Complete overhauling of Stg-II clariflocculator (Mechanical related job).
Complete overhauling of HP Pump,RO pump.
Complete overhauling of stg-II Backwash Pit Transfer Pump.
Complete overhauling of Stg-II N-Pit Transfer Pump.
Complete overhauling of Stg-II Sludge Transfer Pump.
Complete overhauling of Stg-II Sludge Thickner Transfer Pump.
Complete overhauling of Sludge Thickner
BMC- Safety PPE
For 1st yr Safety PPE of Stg-I &II units
For 2nd yr Safety PPE of Stg-I &II units
For review of the condition of Tool & Tackles @ 1.2% of Wages for Stg-I & II units.
GPA for 2 years of 36 Persons (Rs.130 per person per year).
GPA for 2 years of 12 Persons
MUNESHWAR NAVIN CONSTRUCTION (BID ID -7486193)
Imperial Construction (BID ID -7529411)
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid