Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹2.5 L
EMD Value
₹5,000
Closing Date
17 Oct 2026, 11:00 am6d left
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Engineer HPPWD Division Gohar
Executive Engineer HPPWD Division Gohar
RRD on Chail Moviseri Road km 0/00 to 11/200 (SH C/o B/wall at RD 5/900 to 5/910, Edge wall at km. 7/800 to 7/810 and cutting 7/810 to 7/850)
2026_PWD_145402_15
NIT No. 5350-57 dated 29-09-2026
Open Tender
Civil Works - Roads
Percentage
60 days
Gohar
Please refer Tender documents.
8 documents required · 8 mandatory
₹350
₹5,000
9 Oct 2026
9 Oct 2026
17 Oct 2026
9 Oct 2026
17 Oct 2026
9 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earth work in excavation for structure as per drawing and technical specification clause 305.1 i/c setting out construction of shoring and bracing removal of stumps and other deletarious material and disposal up to any lead dressing of sides and bottom and back filling in trenches with excavated suitable material ordinary soil including carriage of material with in all leads and lifts and other incidentals and as per the direction of the Engineer-in Charge. | 32.3 | Per Cubic meter | 230 | ₹7,429 |
| 2 | Providing and laying cement concrete 1:5:10 (one cement : five sand ten graded crashed stone aggregate) 40mm (forty millimeter) size for plain / reinforced concrete in open foundation complete as per drawings and technical specification clause 802,803,1202 & 1203 within all leads , lifts and carriage of materials and other incidentals . as per direction of Engineer –in –Charge completer in all respect. | 47.25 | Per Cubic meter | 4,350.2 | ₹2,05,546.95 |
| 3 | Back filling behind abutment, wing wall and return wall complete as per drawing and technical specification clause 1204.3.8 granular material within all leads , lifts and carriage of materials and other incidentals .as per direction of Engineer –in –Charge completer in all respect. | 7 | Per Cubic meter | 1,050.6 | ₹7,354.2 |
| 4 | Providing weep hole in brick masonry / stone masonry /plain reinforced concrete abutment wing wall return wall with 100 mm ( one hundred millimetre ) dia PVC pipe extended through the full width of the structures with slope of 1 (v) :20 (H) towards drawing face complete as per drawing and technical specification clause 614,709& 1204.3.7 with in all leads, lifts and other incidentals as per direction of Engineer –in –Charge complete in all respect. | 16 | Each | 380.7 | ₹6,091.2 |
| 5 | Excavation in soil in hill area in all heights and depths in all kinds of soil including saturated soil comprising of pick, jumper blasting work both in soft and hard rock with chiseling / wedging out side of rock ( where blasting is prohibited ) and their intermediate classification of soil including dewatering where required setting out to the required line grades , side slopes trimming bottom and level as shown on drawings as directed by the Engineer -in charge at site according to technical clause 1603.1 and 1603.2 sorting useful / un-useful materials and stacking the same in all leads and lifts and transportation of the un-useful materials for filling in roads ways , embankments for grades improvements and leveling to the require grade and then disposing of surplus excavated earth in acquired width of road or on approved dumping sites through all modes of transportation including head load animal load or mechanical means along with its leveling fine dressing and all labour, machineries , materials , tools equipment’s and sefety measures and incidentals necessary to complete the work by all means ( if any required ) recovery for 8.47 cubic metre @ Rs. 300.00 per cubic metre amount Rs.2,541/- shall be done on prorata basis for the quantity of cutting in earth work effected . Any loss to the public and private property during the course of execution shall be the absolute responsibility of the contractor , which shall have to be duly compensated by him in all respect including all leada and lifts and materials and as per direction of Engineer in charge . | 109.76 | Per Cubic meter | 206.5 | ₹22,665.44 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 2.78 MB
15.pdf
Tender Documents • 9.31 MB
BOQ_216658.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .