| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.3 CrAccepted-AOC | ₹1.3 Cr | L1 | Accepted-AOC Being L1 |
| 2 | L2₹1.4 Cr+₹9.6 L (7.61%)Rejected-Finance | ₹1.4 Cr+₹9.6 L (7.61%) | L2 | Rejected-Finance Rejected being L2 |
| 3 | Rejected-Technical | - | - | Rejected-Technical As per recommendtions of BOO |
Tender Value
₹1.2 Cr
EMD Value
₹2.0 L
Closing Date
9 Mar 2024, 12:00 pmClosed
Chief Engineer Project Swastik
O/O Chief Engineer Project Swastik C/o 99 APO Pin 931717 BRO
EXECUTION OF SURFACING WORK FOR PROVIDING, LAYING AND COMPACTION OF WMM, DBM AND BC WORKS AS PER MORTH SPEC FOR RD AND BRIDGE WKS AT HOME AND FAR BANK OF THENG TUNNEL FOR APPROX 650 MTR ON G-C ROAD UNDER 107 RCC /758 BRTF/PROJECT SWASTIK JOB NO 303/5
2024_BRO_643867_1
NIT No CE (P)SWTK/22/2023-24
Open Tender
Civil Works - Roads
Item Rate
90 days
AT HOME AND FAR BANK OF THENG TUNNEL ON G-C ROAD
As per tender documents
8 documents required · 8 mandatory
₹0
₹2.0 L
Yes
HQ CE (P) Swastik
13 Apr 2024
23 Feb 2024
11 Mar 2024
23 Feb 2024
9 Mar 2024
29 Feb 2024
23 Feb 2024 - 28 Feb 2024
28 Feb 2024
Amount
WMM Work at home and far bank of Theng Tunnel for approx 650 mtr on Gangtok-Chungthang road
Providing, Laying and Compaction of 75 mm thick (compacted) WMM (Wet Mix Macadam) layer confirming to grading as per table 400-13 and clause 406 of MORT&H specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
Providing, Laying and Compaction of 100 mm thick (compacted) WMM (Wet Mix Macadam) layer confirming to grading as per table 400-13 and clause 406 of MORT&H specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
Prime Coat at home and far bank of Theng Tunnel for approx 650 mtr on Gangtok-Chungthang road
Providing and applying of primer coat with bitumen emulsion on prepared surface of granular base including clearing of road surface and spraying primer @ 0.60 kg per sqm (using BPD) and all complete as per clause 502 of MORT&H specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
DBM Works at home and far bank of Theng Tunnel for approx 650 mtr on Gangtok-Chungthang road
Providing, Laying and Compaction of 50 mm thick (compacted) DBM (Dense Bituminous Macadam) layer to satisfying the requirement as per clause 505 of MORTH specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
BC Works at home and far bank of Theng Tunnel for approx 650 mtr on Gangtok-Chungthang road
Providing, Laying and Compaction 30 mm thick (Compacted) BC (Bituminous concrete) on dense bituminous macadam layer to satisfying the requirement as per clause 507 of MORTH specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
TACK COAT at home and far bank of Theng Tunnel for approx 650 mtr on Gangtok-Chungthang road
Providing and applying of tack coat with bitumen emulsion using bitumen emulsion pressure distributor (BPD) @ 0.20 Kg/Sqm on prepared bituminous surfaces as per clause 503 of MORTH specifications for road and bridge works (fifth revision) and as specified in particular specifications and as directed by Engineer-in-Charge.
M/s Santosh Kumar Agarwal
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .