Performance security (PS) is a financial guarantee that the winning bidder must deposit before signing the contract. Typically 5–10% of contract value, it protects the government against contractor default during contract execution. Managing performance security is a critical part of your cash flow and compliance strategy.
Key Facts
- Amount — 5–10% of contract value (specified in the tender document). GFR 2017 Rule 170 specifies the range.
- Deposit deadline — typically within 15–30 days of receiving the Letter of Intent (LOI)
- Validity — contract completion date plus 60–90 days (defect liability period)
- Forms accepted — bank guarantee (most common), fixed deposit receipt, demand draft, or government securities
- Failure to deposit — EMD is forfeited and the award may be cancelled. Contract offered to L2 at L1's rate.
Performance Security vs EMD
- EMD (Bid Security) — deposited at bid stage. 2–5% of estimated value. Released when PS is deposited. Protects against bid withdrawal.
- Performance Security — deposited at contract stage. 5–10% of contract value. Released after contract completion. Protects against execution default.
- Key difference — EMD is pre-award and smaller. PS is post-award and larger. EMD exemption (for MSEs) does not mean PS exemption.
When PS Can Be Encashed
- Contractor fails to perform within the contract period
- Contractor abandons the work midway
- Quality of deliverables is below specified standards and contractor doesn't rectify
- Contractor becomes insolvent or goes into liquidation
- Defects found during the defect liability period that the contractor fails to repair
Getting PS Released
- Apply for release — after the defect liability period ends, submit a formal request for PS release to the procuring department
- Completion certificate — obtain the completion certificate or satisfactory performance certificate from the department
- No pending claims — PS won't be released if there are pending disputes, LD claims, or defect rectification issues
- Timeline — departments should release PS within 60 days of the defect liability period ending, but delays are common. Follow up actively.
- Partial release — for long contracts, some departments allow partial PS release as work milestones are completed
Tips for Managing PS Costs
- Use bank guarantee instead of FDR to avoid locking cash
- Negotiate PS validity aligned with realistic completion timelines — overestimating contract duration increases BG costs
- Track PS release dates actively — unreleased PS blocks your BG limit for future tenders
- For MSMEs, CGTMSE guarantees can reduce the cash margin needed for PS bank guarantees
Search Government Contracts
Find government tenders with clear performance security terms on Tenderkart.
Search Tenders