NCTPS I SE MI circle AOH 25 26 BM Dn Unit II Flue Gas Duct B Pass Rectification of flue gas duct portions from APH outlet to chimney during annual overhaul for the year 2025 26
Renewal of metallic expansion joints. Work involves arresting the upstream and downstream of duct, cutting and removal of existing... positioning of new expansion joints, aligning with the duct channel and complete welding; Fabrication of protection plate, fixing inside the Expansion joints and full welding at gas flow ...
NCTPS I SE MI circle AOH 25 26 BM Dn Unit I II III Overhaul and load testing of ID FD PA Fan hoists assembly during annual overhaul for the year 2025 26
Overhaul of 10T & 12.5T capacity eclectically operated wire rope Hoist in FD, PA & ID Fans: Works involves dismantling and shifting of complete hoist assembly to ground floor from its... dismantling of all internals, inspection of electrical control panel switches, wiring, cables & mechanical components attending minor faults, renewal of wornout spares. Assembling, lifting, aligning ...
NCTPSI SE MI Circle AOH 25 26 BM Dn Unit III Dismantling Rectification and Transporting of Ignitor Scanner air fan impeller assembly to the work shop Dynamic balancing commissioning and overhauling of its dampers flaps and strengthening
Charges for dismantling of A.C/ D.C scanner / Ignitor air fan end cover plate, motor, impeller etc overhaul works and assembling the same fan and normalizing. Including consumables and T&P’s.
NCTPS I SE MI circle AOH 25 26 BM Dn Unit III Renewal Rectification of Insulation in Air Pre Heater A B Pass casing and its Auxiliaries system including supply during Annual Overhaul 2025 26
Clearing of released wool from the works spot: This work involves collection of released waste wool, debris and other unwanted insulation materials from the work spot, gathered in one place and clear, transport for away from the site as per the instruction of Engineer in-charge.
NCTPS I SE MI circle AOH 25 26 BM Dn Unit III Repair Rectification of eroded tubes in LTSH coil and other allied works during Annual Overhaul 2025 26
Charges for Repair /Renewal of defective boiler tubes of size 44.5mm OD in LTSH inclusive of transportation, cutting of defective tubes, edge/spool preparation, welding with IBR welder and assisting for hydraulic test.Including consumable and hire charges for T&P's.
NCTPS I SE MI Circle AMC 26 27 BM Dn Unit I II III Attending of Steam Feed Water Leaks in Valve glands pipes punctures valve flange bonnet in PRDS System soot blowing system by ON LINE SEALING METHOD
Arresting of steam leak in Pipe welding joints, Pin hole Puncture, Cracks etc., by On Line Sealing method. Including consumables and T&P's. Size Up to 50mm O.D.Pipe.