Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Tender Value
₹70.6 L
EMD Value
₹1.4 L
Closing Date
20 Oct 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
EE CD PWD Guptkashi
Office of EE CD PWD Guptkashi
Construction of a folding pedestrian bridge at Garudchatti, located on Sh Kedarnath Dham bridle yatra route- to connect various amenity buildings and facilitate the smooth conduct of the pilgrimage.
2026_pwd_100980_8
1264/06AC-Tender Dated 06.10.2026
Open Tender
Civil Works - Bridges
Item Rate
180 days
Garurchatti
Please refer Tender documents.
2 documents required · 2 mandatory
₹4,720
EE CD PWD Guptkashi
₹1.4 L
6 Oct 2026
6 Oct 2026
20 Oct 2026
6 Oct 2026
20 Oct 2026
12 Oct 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 2 | Excavation in foundation for retaining & breast walls in all types
of soils and rocks including lead, lift and disposal of surplus material as per direction of engineer - in -charge. | 130.89 | Cum | - | - |
| 3 | Providing concrete for plain concrete in open foundations
complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203. P.C.C grade M 10. Nominal mix 1:3.6 (Hand mixing) | 6.89 | Cum | - | - |
| 4 | Providing concrete for plain concrete in open foundations
complete as per drawings and technical specifications Clause 802, 803, 1202 & 1203. R.C.C grade M 20 | 18.27 | Cum | - | - |
| 5 | Supplying, fitting and placing HYSD bar reinforcement in
foundation complete as per drawings and technical specifications Clauses 1000 and 1202. | 0.98 | M.T. | - | - |
| 6 | Random Rubble Stone Masonry laid in 1:6 cement and coused
sand mortar, in breast walls,retaining walls, parapets, scuppers, etc. including supply of all material, labour, T&P and royaltiies etc. Comlete as per drawing and technical specifications. Clauses 702, 704, 1202 & 1203 of MORD Specifiction. | 126.92 | Cum | - | - |
| 7 | Hand Packed stone filling in back of wallls including cost of all
materials, royality, T&P etc. complete as per direction of
Engineer-in charge. (As per PWD Uttarakhand specifications) | 18 | Nos | - | - |
| 8 | Cement plum Masonry with 40% plum & 60% 1:3:6 cement
concrete including supply of all material, labour, T&Petc.
required for proper completion of thework. as per drawings and
technical specifications Clause 802, 803, 1202 & 1203 of MORD
Specifiction. | 54 | Rmt | - | - |
| 9 | Providing and Laying of Mechanically Woven Double Twisted
Hexagonal shaped Gabions (Zinc plus PVC coated), of size
3mX1mX1m with two diaphragms at 1m interval, having mesh
opening 100mmx120 mm, mesh wire diameter 2.7mm/3.7mm,
edge/selvedge wire diameter 3.4/4.4 mm and lacing wire diameter 2.2/3.2 mm. (The work includes filling boulders in the gabions). | 16 | Nos | - | - |
| 10 | Supply and fabrication of steel truss bridge as per detailed
drawing attached including supply of all structural steel E-350
confirming IS 226 - 1969 required for proper completion of the
bridge including ground errection of the bridge and one coat of
approved quality anticirrosive (red oxide) paint of confirming IS
5660, all T&P, nuts and bolts, washers and also including supply
and fixing of shop rivets required as per drawing, required
equipment shall be arranged by the contractor athis own cost
which shall be taken back by the contractor after satisfactory
execution of the job, the rates shall include ground errection in the workshop and its dismentling after inspection, approval and
removing defects, match marking of all parts, numbering and
proper stacking in the premises of workshop before cartage to site of work. The work shall be executed in accordance to IS - 1915. The rates shall include cost of all material, its wastage, cutting, bending if required, welding, making holes, shop riveting, labour, T&P etc. required for proper completion of the work.including cost of cartage from workshop to Bridge Site including safe stacking of parts | 14.67 | M.T. | - | - |
| 11 | Erection of Steel Truss (Girder) Bridge (up to 60m span) as
per drawing with required camber including cartage of
fabricated parts from the place of stack near site including
submission of launching plan by the contractor, (duly
vetted by a recognised reputable institution/ consultant if
required) and approved by the engineer-in-charge. Service
bolts to used shall be of approved make. The rate including
of cost of all labour, T&P, equipments, civil work and
consumables, cost of arranging, fabricating, errecting and
dismantling of erection scheme including the cost of its
designing, revising, supervision by contractor's designeer at
site during erection, also including cost of all safety
measures and necessary insurances of bridge and labours
for proper completion of the work as per MORTH
specification no. 1905with due regard of mansoon and as per
directions of the engineer-in-charge. | 14.67 | M.T. | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.91 MB
Coditions.pdf
Tender Documents • 0.25 MB
BOQ_119024.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .