MTPS I BM Unit III Boiler COH 2019 Overhauling of secondary air Dampers Scanner Air Fans and its damper flap gate etc
MTPS I Boiler Rotating parts Units III and IV Preventive Breakdown maintenance Works and other allied works as and when required basis
MTPS I BM Unit III COH 2019 Renewal Reconditioning of various saw tooth expansion joints in FG ducts and Air ducts and other related works etc in both A and B Sides
MTPS I BM Unit III Boiler Pressure parts COH 2019 Maintenance of boiler drum and all safety valves
MTPS I BM Unit III Inspection Renewal of guide bearing in Air Pre Heater A and B sides and Dismantling Cleaning Inspection and Reassembling of air seal assembly etc
MTPS I BM Unit III Capital Overhauling 2019 20 Overhaul of ESP AB Pass Internals and related works
MTPS I Mill Plant Unit III Fabrication of MS bend 10 degree 15 degree and 22 degree 8 Nos to suit dia 508mm X 12.7mm thick coal pipe line and hard facing of existing New MS bends 19 Nos during COH 2019 20
MTPS I BM Unit III Capital Overhauling 2019 20 Overhaul of ESP CD Pass Internals and related works
MTPS I BM Unit III Boiler COH 2019 Arresting the air ingress ash leakage in Ist pass Penthouse area with an advanced ceramic fiber sealing system and allied works
MTPS I BM Unit III COH 2019 Tube thickness survey Water wall buffing providing platform Renewal of shrouding and allied works etc
MTPS I Mill Plant Unit III Hard facing of Fuel inlet elbows Long and short during COH 2019 20
Mettur TPS I Mill Pant Unit III Renewal Reconditioning of the Worn out Mill under bowl Door frames and Doors in Mills 3A to 3F during Capital Overhaul 2019 20
MTPS I Mill Plant Unit III Overhaul of Hot air gates and Cold air gates Hot air damper and Reconditioning of Hot air gate power cylinder during Capital overhaul 2019 20
MTPSI BM Unit III Boiler COH 2019 Arresting the air ingress ash Leakage in Interpass IInd pass Penthouse area rear arch room S panel Enclosed area with an advanced ceramic fiber sealing system and allied works
MTPS I Boiler Rotating parts Units I and II Preventive and Breakdown maintenance Works and other allied works as and when required basis
MTPS I Mill Plant Unit III Reconditioning of mill outlet elbow 4nos and various sizes of ceraline bends 4 Nos by applying ceramic wear coat Eromat released from Unit III during COH 2019 20
MTPS I Mill Plant Unit III Dismantling hard facing and assembling of 1mtr length coal pipes after MOE in Mills 3A to 3F during COH 2019 20
MTPS I Mill Plant Unit III Inspection and replacing inverting of 8 Nos eroded Orifices dia 415 mm 2 Nos dia 406mm 1No dia 400mm 2Nos dia 410mm 2Nos dia 396mm 1No in coal pipes at boiler side 8 locations during COH 2019 20
MTPS I Mill Plant Unit III Dismantling reconditioning overhauling assembling of seal air damper assembly deflector flap gate and allied works
MTPS I Mill Plant Unit III Renewal of eroded worn out Expansion joints in hot air duct during COH 2019 20
MTPS I Mill Plant Unit III Renewal of Existing New Insulation and GI sheets in Hot air ducts during COH 2019 20
MTPS I Mill Plant Unit III Hard facing of SpoolPieces below the Fuel inlet elbow in Mill 3A to 3F during COH 2019 20
MTPS I CA CWS II Lifting the intake screens positioning cleaning the screens from debris algae removing the rust and old paint from the intake screens frame Structures etc of Cooling Water Pumps 3A 3B and 3C of Unit III during COH 2019 20
MTPS I Mill Plant Unit III Strengthening Rectification of raw coal bunkers 3B 3D and 3F leak arresting work by patch welding and Providing stiffeners during COH 2019 20
MTPS I Mill Plant Unit III Dismantling patch welding and assembling of Mill outlet elbows Mill discharge valve bodies orifices Transition pieces and fabrication of spool piece etc
MTPS I BM Unit III Rotating Parts COH 2019 Flue Gas Duct B side Patch up works and other repair works between FG duct 45 degree slope to ESP inlet including cost of materials
MTPS I TM Unit III Removal and ReInsulation of 210MW LMW Design Turbine and its auxiliaries during COH 2019 20
MTPS I Mill Plant Unit III Renewal of damaged Coal pipe bends ceralin bends and Patch welding the eroded portions of Coal bends and pipe lines
MTPS I CA CWS II Dewatering complete cleaning and sludge removal cleaning with bleaching powder painting the structure of clarifier III and Overhaul of sludge disposal pump during COH 2019 20
MTPS I BM Unit III Rotating Parts COH 2019 Flue Gas Duct B side Renewal of Deflector plates renewal of duct supports renewal of guard plates
MTPS I BM Unit III Capital Maintenance 2019 20 Complete overhaul of APH B side and other related works
MTPS I BM Unit III Rotating Parts COH 2019 Flue Gas Duct A side Renewal of Deflector plates renewal of duct supports renewal of guard plates over the expansion joints
MTPS I Mill Plant Unit III Dismantling reconditioning and assembling of fuel inlet elbows and Spool pieces Coal pipes during Capital overhaul 2019 20
MTPS I BM Unit III Rotating Parts COH 2019 Flue Gas Duct Patch up works and other repair works between APH outlet to 45 degree slope end both A and B sides including cost of materials
MTPS I BM Unit III Capital Maintenance 2019 20 Complete overhaul of APH A side and other related works
MTPS I Mill Plant Unit III Overhauling of classifier assemblies replacement repairing of eroded inner cones inner cone drum section
MTPS I BM Unit III Rotating Parts COH 2019 Flue Gas Duct A side Patch up works and other repair works between FG duct 45 degree slope to ESP inlet including cost of materials
MTPS I Mill Plant III Complete overhauling of gearbox Mechanical face seal assembly worm shaft assembly replacing the worn out bulged insulation cover plate assembly scrapper etc
MTPS I BM Unit III COH 2019 Disposal of Ash from the pent house S panel area rear arch room and roof area and Eco hopper
MTPS I BM Unit III Boiler COH 2019 Rectification Replacement of Defective tubes in LTSH Coils and Economizer hanger tubes at boiler II pass area
MTPS I BM Unit III Boiler Pressure parts COH 2019 Maintenance of Burners and Replacement of worn out fasteners at cover plates
MTPS 1 Mill Plant Unit III Overhauling load testing and certifying of lifting tools
MTPS I BM Unit III Boiler pressure parts COH 2019 Water Washing of Complete boiler Removal of heavy particle of soot deposited on Water wall tube Platen SH coil and Reheater coil Overhauling of water wall soot blowers and LRSB and allied wo
MTPS I BM Unit III Boiler COH 2019 Rectification Replacement of Defective tubes in water wall area S panel area Water wall reducer tubes Inter pass area steam cooled wall tubes and fin welding
MTPS I Mill Plant Unit III Overhauling of tramp iron chute knife edge gate valves and laying of pneumatic line in mills 3A to 3F during COH 2019 20
MTPS I TM Unit III Cleaning and Hydraulic Testing of Lub oil Coolers and Working oil coolers Dismantling cleaning and assembling of Suction Strainers of BFPs and CEPs etc
MTPS I Mill Plant Providing 1 No Diesel driven Tata Sumo Chevrolet Tavera or an equivalent Vehicle on hire basis including driver for the official use of EE MP for the period of one year from 01.09.2019 to 31.08.2020
MTPS I BM DM Plant Providing new rubber lining and refixing the Frontal piping system of Stream I Ion Exchangers in Stage II DM Plant
MTPS I TM Unit III Overhauling and commissioning of Heater Drip Pump 3A and 3B during COH of 2019 20
MTPS I TM Carrying out Bullet cleaning of LHS and RHS of condenser tubes in Unit III condenser during COH of 2019 20