MTPS I Mill Plant Unit II Removal of worn out thinned out wall plates of bunkers 2A 2D 2E and erection of new wall plates of 12 mm thick MS plates and supporting beams and other related works
MTPS I Mill Plant Unit II Hard facing of MS bend and multiple port outlets in coal flow lines Fabrication of MS bend 15 deg 11 deg 10 deg to suit dia 508 mm 12 7 mm thick coal pipe line during AOH 2025 26
MTPS I Mill Plant Unit III Dismantling the damaged Mill outlet Elbows Orifices Transition pieces fabrication of spool pieces Mill port outlet 90deg bend and renewing with new from Coal mill outlet up to Mill floor in coal mill 3A 3B 3C 3F
MTPS I BM Unit I AOH 2025 26 FG Duct A and B sides Renewal of Deflector plates renewal of duct supports renewal of guard plates over the expansion joints etc
MTPS I BM Unit IV Boiler Pressure parts AOH 2025 Servicing of various size actuators and allied works
MTPS I Boiler Rotating parts Units I and II Preventive and Breakdown maintenance Works and other allied works as and when required basis for the period of 365 days from the date of commencement of work for the year 2026 27
MTPS I Mill Plant Unit III Overhauling of classifier assemblies Replacement Repairing of eroded inner cone inner cone drum section Venture vanes venturi Collars during AOH 2025 26
MTPS I Mill Plant A C Plant Unit IV AOH 2025 26 Air Washer System Epoxy painting of blowers and its auxiliaries enamel painting of AWCW Pumps pipe lines Spray nozzles flushing works renewal of bellows in discharge ducts W type eliminator
MTPS I BM Unit IV AOH 2025 26 Flue Gas duct A and B sides Patch up works and other repair works between APH out let to ESP inlet
MTPS I BM Unit IV Boiler Pressure parts AOH 2025 Maintenance of Burners and replacement of worn out fasteners at cover plates
MTPS I BM Unit IV Boiler pressure parts Replacement of most overheated Hot Reheat coil rear side bend in Boiler inter pass area Circuit No 29 to 48
MTPS I BM Unit I Boiler pressure parts AOH 2025 Overhauling of Secondary Air Dampers Scanner Air Fans and its damper flap gate etc
MTPS I Mill Plant Unit III Overhauling of gravimetric feeders and Clean out conveyor and cleaning clearing the coal dust and ash deposited from bunker platforms feeder floor feeder discharge platforms coal pipes mill floor
MTPS I Mill Plant Unit III Dismantling of existing elliptical feeder discharge chutes mill 3A 3B reconditioning of released SS elliptical feeder discharge chutes and reassembling the same during AOH 2025 26
MTPS I BM AOH 2025 26 Unit I Complete overhaul of APH A and B Sides and other related works
MTPS I BM Unit IV Boiler Pressure Parts AOH 2025 Cleaning of boiler structures from 0 to 52 m Level etc
MTPS I BM Unit IV AOH 2025 26 A and B stream Boiler PA fans FD Fans ID Fans and its isolation dampers and APH gear box
MTPS I M I CA CWS I Overhauling of sludge disposal pump and Cold and hot water tunnel vent valves Air Vent valves gate valves including Painting of CT safety grills etc
MTPS I MI CA CWS I Cooling Tower I Overhauling of Flow Control Valves and including reconditioning of worn out spares during AOH 2025 2026 of Unit I
MTPS I Mill Plant Unit IV Reconditioning the eroded worn out Patch welded areas of Mill outlet elbow MOE removing the eroded worn out portion of the released MOE by gas cutting and preparation of new coal pipes M S plates to the required
MTPS I Mill Plant Unit IV Coal flow system to boiler Rotating the existing eroded straight coal pipes to Boiler corner 1 to Corner 4 for 180 deg rotating at 16 meter level near Boiler area during Annual overhaul 2025 26
MTPS I Mill Plant Unit IV Dismantling of Fuel inlet elbow short Fuel inlet elbows long renewal of eroded FIE short Hard facing of released Fuel inlet Elbows long short and then assembling of fuel inlet Elbows during Annual overhaul 2025 26
MTPS I BM Unit II COH 2024 25 ID fan 2A Reconditioning of the eroded discharge spiral portion in the ID fan top casing renewal of casing wear liner and other related works
MTPS I CA CWS II Overhauling of existing ID fan Gearbox for 5 Nos including static balancing of fan blades painting of gear box fan blades hub and arm sleeves etc in Cooling Tower Stage II
MTPS I CA CWS II Replacement of existing eroded CWP ring guards and its intake screen safety grills and painting of Unit III and IV etc
MTPS I BM Unit I Boiler Pressure parts AOH 2026 54 mtr Elevation Cutting and removal of heavily wornout top roof sheet of penthouse and patch work on the eroded portion of top roof sheet with new decking sheet and allied works
MTPS I BM Unit I Boiler pressure parts AOH 2026 Rectification Replacement of defective Boiler tubes in 9th header and Economizer Coils at Boiler IInd pass area and Radiography testing of welded joints
MTPS I BM UNIT I Boiler pressure parts AOH 2026 Rectification of buck stay beam and supports renewal of worn out buck stay pin and allied works
MTPS I TM Unit III Inspection of Condenser tubes flaring and torque setting by using special tools Tube sheets Cleaning degreasing and Epoxy coating to the thickness of 1500 Microns on Condenser tube sheets of the condenser
MTPS I BM Unit I Boiler pressure parts AOH 2026 27 Water Washing of Boiler Ist and IInd pass area Removal of heavy particle of soot deposited on Water wall tube Platen SH coil and allied works
MTPS I BM Unit I AOH 2026 27 FG Duct A and B sides Renewal of Deflector plates renewal of duct supports renewal of guard plates over the expansion joints etc
MTPS I TM Alignment of Gantry rails with reference to Piano wire for 125 30 Tonnes Station EOT Cranes During 2025 26 for Unit I to IV area
MTPS I BM AOH 2026 27 Unit I Complete overhaul of APH A and B Sides and other related works
MTPS I BM Unit I AOH 2026 27 Flue Gas duct A and B side Patch up works and other repair works between APH outlet to ESP inlet
MTPS I BM Unit I Boiler Pressure parts AOH 2026 Maintenance of Burners and replacement of worn out fasteners at cover plates
MTPS I BM Unit I Boiler pressure parts AOH 2026 Rectification Replacement of defective tubes in water wall area S panel area Water wall reducer tubes etc
MTPS I TM Unit I to IV Dismantling Cleaning and assembling of Main oil Tank filters and Centrifuges bowl assembly during 2026 27 for a period of One year from the date of commencement
MTPS I BM Pressure parts Units III and IV Boiler Annual maintenance of Boiler Pressure Parts for Oil gun cleaning soot blower operation cleaning and air washing of Boiler structures floor and allied works for the period of one year
MTPS I BM Pressure parts Units I and II Boiler Breakdown maintenance of Boiler For rectification of boiler tube puncture at various location HP LP Valves etc
MTPS I Mill Plant Unit IV Complete dismantling and assembling of Mill internals reconditioning renewal of worn out parts bearings replacement of worn out worm wheel with worm shaft and renewal of worm gear hub etc in any one mill from 4A to 4F
MTPS I BM Unit I Boiler pressure parts AOH 2026 Rectification Replacement of defective tubes in LTSH Coils Economizer hanger tubes steam cooled side walls and fin welding in boiler IInd pass area
MTPS I BM Lift Operation of Boiler Lifts I to IV and attending routine maintenance and Minor repair works of Boiler Lift II and its accessories for one year from the date of commencement of works for 2026 27
MTPS I BM Unit I Annual maintenance 2026 27 A and B stream Boiler PA fans FD Fans ID Fans and its isolation dampers and APH gear box
MTPS I BM AOH 2026 Unit I Boiler pressure parts Replacing overheated HRH stub bends and other circuit bends at penthouse area and allied works
MTPS I BM Unit I Boiler pressure parts AOH 2026 Overhauling of Secondary Air Dampers Scanner Air Fans and its damper flap gate Reconditioning of damaged wind Box compartment etc
MTPS I BM Unit I AOH 2026 27 Emergency works Renewal of damaged support bearing in APH 1A and other related works
MTPS I BM Unit I Boiler pressure parts AOH 2026 Erection and operation of sky climbers for assisting various maintenance works and dismantling of sky climbers
MTPS I BM Unit I Boiler Pressure parts AOH 2026 Servicing of various size actuators and allied works
MTPS I BM Unit I Boiler Pressure parts AOH 2026 Reconditioning and Hard facing of used and Wornout square coal nozzle tips and checking of deformation and matching with nozzle
MTPS I BM unit I Inspection and rectification of dislocated platen super heater coil assembly removal and bring back to its original position and rectification of defective tube and allied works