MTPS I BM Unit II AOH 2021 22 FG Duct A side Renewal of Deflector plates renewal of duct supports renewal of guard plates over the expansion joints etc
MTPS I TM Unit I Renewal of Gasket at water box side tube nest side condensate inlet and outlet flange inspection and cleaning of tube nest and hydraulic testing of LPH 3 and 4 GC 1 Ejector 1A Vent condenser and allied works
MTPS I BM Unit I AOH 2024 25 Bend removal by hot correction of collecting electrodes Replacing of eroded snapped emitting electrode Resume of frequent failure of Field in ESP and other allied works of ESP AB CD pass
Mill Plant Unit I overhauling of gravimetric feeders and Clean out conveyor and cleaning clearing the coal dust and ash deposited from bunker platforms feeder floor feeder discharge platforms coal pipes mill floor and mill gearbox of mill 1A to 1F
MTPS I BM Unit III Boiler pressure parts AOH 2021 Disposal of Ash from Eco hoper deflection slope rear arch room and boiler roof area and strengthening of Eco hopper supports with new pipes and allied works
MTPS I - Civil Circle - Replacing the damaged ACC roof sheet by new color coated sheet with false ceiling in EM II office in front of railway track at MTPS I
MTPS I BM Unit IV Boiler Pressure parts AOH 2025 Tube thickness survey Water wall buffing providing platform renewal of shroudings and allied works
MTPS I Civil Circle Providing micro concrete to the structural support in the sides of hot water line in the stack floor, stair case protection hand rails and other allied Civil works in Cooling Tower-III
MTPS I BM Unit IV AOH 2024 2025 Renewal of Sacrificing heating elements E F and G27 in APH A and B Sides and other related works
MTPS I TM Alignment of Gantry rails with reference to Piano wire for 125 30 Tonnes Station EOT Cranes During 2022 23 for Unit III and IV area
MTPS I Mill Plant Unit I Clearing the Mill rejects from Unit I Mill Feeder area weighing in departmental weigh bridge and transporting to rejects yard G switch yard area coal yard by using contractors vehicle and unloading the same and return
MTPS I BM Unit IV Boiler Pressure parts AOH 2022 Overhauling of HP LP valves and replacement of defective valves
MTPS I TM UNIT II Overhauling Arresting of Steam passing in LP Bypass Valve LHS Model No NR 64 500 EK
MTPS I TM I Lifting of spare HP IP LP Turbine Rotors from Rotor box Rotating 180 degree and kept in Rotor box and etc Once in six months during IInd phase of 2020
MTPS I TM Unit I and Unit II Preventive Breakdown maintenance works and Repairing works of Air Compressors Make KG Khosla Model No 2HA2QT and Air Dryers Make Khosle on as and when required basis for a period of 120 days in the year 2022 2023
MTPS I BM Unit III AOH 2022-23 Flue Gas duct B side Patch up works and other repair works between APH outlet to ESP inlet
MTPS I TM Unit IV Overhauling of Valves in Feed Water Main Condensate and Extraction Steam lines during Annual Overhauling 2021 22
MTPS I TM Unit II Overhauling of TLOCBPs H2CBPs Hydrazine Dozing Pumps and Phosphate Dozing Pumps during AOH of 2021 22
MTPS I Mill Plant Unit III Complete inspection of Mill internals reconditioning renewal of worn out parts and bearings replacement of eroded worm wheel with worm shaft if necessary and renewal of worm gear hub
MTPS I - Civil Circle - Construction of toilet room with colour coated sheet roof for the use of Trainees on the rear side of security cum time office at MTPS I
MTPS I BM Unit IV Boiler pressure parts AOH 2021 22 Maintenance of Burners and replacement of worn out fasteners at cover plates
MTPS I BM Unit I Removal of deteriorated and peeled off insulation and re insulation with new same insulation materials on the Portion in FG duct Chimney area and ID fan casing area and other related works
MTPS I CA CWS I Complete Overhauling of 10Ton Electrical hoist and Load testing of 10Ton Electrical hoist 1 No and 15 Ton Electrical hoist 1 No in cooling water system Stage I
MTPS I BM Unit III Boiler pressure parts AOH 2021 Overhauling of secondary air dampers Scanner Air Fans and its damper flap gate Reconditioning of damaged wind Box compartment dampers guide plates insulation etc
MTPS I Mill Plant A C Plant Unit I AOH 2024 25 Air Washer System Epoxy painting of blowers discharge duct spray system air filter platform area and enamel painting of AWCW Pumps pipe lines W type eliminator chemical cleaning Overhauling the AWCWP
MTPS I TM UNIT I changing the eroded control valves reducers Expanders pipes and bends and defective 1 and 2 drain line and vent line valves by IBR and Non IBR welding in Unit I during high bearing vibration problem r
MTPS I BM Unit III Boiler pressure parts AOH 2023 Erection and operation of sky climbers for assisting various maintenance works and dismantling of sky climbers
MTPS I TM I Unit III Annual Maintenance work in Main Turbine and its Auxiliaries during 2021 22
MTPS I BM Unit II Boiler pressure parts AOH 2023 Erection and operation of sky climbers for assisting various maintenance works and dismantling of sky climbers
MTPS I BM Unit IV Rotating parts AOH 2024 25 Overhauling Reconditioning of CERM and EERM gear boxes ID PA FD fans gate actuators and other related works etc
MTPS I MP AC Plant Preventive Breakdown maintenance of Voltas make water cooled screw chiller No 1 and 4 Model No EGWFXR3002ML at MTPS I For a period of one year from the date of commencement of work
MTPS I TM I Unit I Annual Maintenance work in Main Turbine and its Auxiliaries during 2021 22
MTPS 1 BM Unit IV Inspection Renewal of Guide bearing in Air pre Heater A and B sides and dismantling cleaning inspection and reassembling of air seal assembly etc and other related works during AOH 2024 25
MTPS I TM Unit I to IV Attending Breakdown maintenance works of tube puncture and gasket renewal work in LP Heaters, Gland coolers, Main Ejectors and attending defects in re-generative system as and when required basis for a period of one year
MTPS I BM Unit III Boiler Pressure Parts AOH 2023 Cleaning of boiler structures from 0 to 52 m Level etc
MTPS I BM Unit III Boiler Pressure parts Replacing the overheated HRH coil header stub bends inside the pent house and allied works
MTPS I BM Unit I Boiler pressure parts AOH 2023 Rectification Replacement of defective Boiler tubes in 9th header and Economizer Coils at Boiler IInd pass area and Radiography testing of welded joints
E-tender for the procurement of consumables of Phosphor bronze bushes for Wagon tipplers - 3 items as per Annexure enclosed
MTPS I TM Unit I Overhauling of Turbine Lub Oil Cooler Booster Pumps Overhauling of Hydrazine Dozing Pumps and Phosphate Dozing Pumps during Boiler license renewal 2020 2021
MTPS I TMI Unit III Annual Maintenance work in Main Turbine and its Auxiliaries during 2024 25
MTPS I Mill Plant Unit II Dismantling and assembling of fuel inlet elbow during Annual overhaul 2023 24
MTPS I BM Unit II Boiler pressure parts AOH 2023 Inspection Rectification of worn out lines bends of Super heater header drain lines Blow down lines and water wall drain lines and Removal of insulation and refixing over drain line pipes etc
MTPS I TM Unit IV Overhauling renewal of worn out spares Bearings Dynamic balancing of Heater drip pump 4A 4B and a spare pump and commissioning of Pumps 4A and 4B during AOH of 2024 25
MTPS I BM Unit III AOH 2021 Flue Gas duct A side Patch up works and other repair works between APH out let to ESP inlet
MTPS I CA Overhauling of Fire hydrant pumps 2 nos and its valves at Fire Water Pump House
MTPS I Mill Plant Unit I Dismantling and assembling of Coal pipe bends ceralin bends and Patch welding the eroded portions of Coal bends and pipelines between Mill Outlet Elbow and Fuel Inlet Elbow during Annual overhaul 2021 22
MTPS I Mill Plant Unit II Dismantling patch welding and assembling of Mill outlet elbows orifices Transition pieces fabrication of spool piece Multiple port outlets etc during Annual overhaul 2021 22
MTPS I Mill Plant Unit III Overhaul of hot air dampers cold air dampers and Renewal of hot air gate seals during Annual overhaul 2021 22
MTPS I BM Unit I Boiler pressure parts AOH 2023 Erection and operation of sky climbers for assisting various maintenance works and dismantling of sky climbers
MTPS I Mill Plant Unit IV Overhaul of hot air dampers cold air dampers cold air gates and Renewal of hot air gate seals during Annual overhaul 2021 22