TTPS ES Circle EM II Core lifting inspection and internal cleaning of all 20 Nos Rectifier Transformers in ESP I during the overhauling period of 2025 26
TTPS ES Circle EM II Cleaning with emery sheet on Rusted area and soap Water Washing the external body of HVR Transformer Duct and Field Disconnecting Switch box with two coats of painting with Enamel smoke Gray Aluminium color paint in ESP I duri
TTPS ES Circle EM II Major overhauling of 2 Nos fan motors 5 Nos Mill motors and Annual preventive maintenance of 4 Nos fan motor 1 No Mill motor during unit I capital overhauling period of 2025 2026
TTPS ES Circle EM II Annual Maintenance of LT SWGR Buses Breakers electronic controller panels auxiliary control panels and overhauling of LT motors in ESP I overhauling of the year 2025 2026
TTPS ES Circle MRT I Capital Overhauling works in Boiler side Valves Dampers DCS panels and ID FD PA fans lub oil panels in Unit I for the year 2025 26
TTPS ES Circle MRT I Capital Overhauling works in FSSS system in Unit I for the year 2025 26
TTPS ES Circle MRT I Capital overhauling works of digital Excitation System GRP 6 6kV System and LT system in Unit I for the Year 2025 26
TTPS ES Circle MRT I Unit I Capital Overhauling of turbine side valve actuator electrical portion limit switch torque switch assemblies in for the year 2025 26
TTPS ES Circle MRT I Capital Overhauling of CWP panels system 6 6kV HT LT switchgear system Generator Transformer System External Auxiliary LT Switchgear System in Unit I for the year 2025 2026
TTPS ES Circle Instn I Releasing Re fixing of Critical instruments of boiler Turbine and Mill area and also Cleaning of Secondary Air Aero foils Unit I during the period of Capital overhaul for the year of 2025 26
TTPS ES Circle Instn I Overhauling of 9 Nos sample coolers painting and replacement of 6 Nos 1/2 defective high pressure valves in sample lines of Unit I during the period of Capital overhaul for the year of 2025 26
TTPS ES Circle Inst I Unit I Capital Overhauling Releasing Transporting Overhauling Painting Re fixing and conducting functional test 4 nos Burner tilt Power cylinder Releasing Overhauling calibrating refixing and conducting load test on 44 Nos SADC
TTPS ES Circle EM I Charges for Hydrostatic testing of 240 nos of Hydrogen gas cylinders replacement of cylinder valves and painting the cylinders with 2 coats of recommended colour paint inclusive of transportation in respect of Hydrogen Plant I II
TTPS ES Circle EM I Hot oil circulation for improving the BDV value of Transformer oil in Generator Transformer R Y B phases UST I and UAT 1A and UAT 1B Dismantling over hauling and errection of 12 nos oil circulating pumps cleaning servicing and g
TTPS ES Circle EM I Complete Overhauling of 3 Nos HT Motors 6 6KV 4000 KW BHEL Make Boiler Feed Pump Motor 1A 1B and 1C in Unit I during Capital Overhauling Period for the year 2025 2026
TTPS ES Circle EM I Maintenance of Stator Water System painting of Hydrogen Gas system seal oil system and stator water system equipments and pipe lines during the Capital overhauling of the Unit I for the year 2025 2026
TTPS ES Circle EM I Cleaning Scrapping and painting of Generator Transformers R Y and B phases including drain oil pipe lines during Unit I Capital overhaul for the year 2025 2026
TTPS ES Circle EM I Charges for Scraping Cleaning and painting of two coats enamel paint in the Unit Auxiliary Transformer 1A 1B UST 1 SST 1 and Bus duct support columns of bus duct LAS and support insulators at 4 5mtr floor and at Transformer yard
TTPS ES Circle EM I Regeneration of polishing unit of Stator Water System in Unit I during Capital Overhauling for the year 2025 2026
Demolishing the existing Tamilnadu Civil Supply Corporation godown adjacent to Port Marshalling Yard of VOC Port.
TTPS ES Circle EM I Charges towards providing Temporary LT 3 Phase supply arrangement for various overhauling works connected with TM I and CMD I and other emergency lighting works in P H area and disconnection of power cables of various v
TTPS ES Circle EM I Capital Overhauling of 6 6kV 225 kW Kirlosker Electric Make HT Motors 3Nos pertaining to Main Condensate Pump 1A 1B 1C and 1No pertains to SOP in Unit I for the year 2025 and 2026
Providing Power Supply arrangement to the newly constructing Smart Bus Shelters
Supply of Various sizes of High Pressure Valves for Turbine in Unit 4 and 5
Tender for Supply of NPK 15 15 15
TTPS Mech II BM Unit I Overhauling of safety valves and High Pressure valves of Unit I Boiler during the year 2025 2026
Household Refrigerating Appliances as per IS 17550 (Q2) (3 (3 ))
TTPS Mech II BM Unit I Patch up works in ducts including supports and fixing of guide vanes splitter in flue gas ducts of B pass C path D path for the year 2025 2026
TTPS Mech II BM Unit I Patch up works in ducts including supports and fixing of guide vanes splitter in flue gas ducts of A pass A path B path for the year 2025 2026
TTPS Mech II BM Unit I Overhauling of ESP A B C D path of Unit I for the year 2025 2026
TTPS Operation Circle MPM I Unit I Attending to repair works in Bunkers and Overhauling of feeders 1A to 1F during forthcoming overhaul
TTPS Mech II BM Unit I Overhauling of Oil Heater Assembly OHS during the year 2025 2026
TTPS Operation Circle MPM I Unit I Replacement of eroded Coal pipe lines, bends and fittings between Mills D, E and F and Boiler during the forthcoming overhaul
TTPS Mech II BM Unit I Overhauling of ID fans A B for the year 2025 2026
TTPS Operation Circle MPM I Unit I Overhauling and reconditioning of hot and cold air dampers, gates, ducts, replacement of expansion joints, seal air fan and cleaning of accumulated fly ash deposited inside the horizontal portion of the hot air duct
TTPS Operation Circle MPM I Unit I Removal of all the damaged insulation in the Hot Primary Air ducts from Air preheaters to mills and insulating the ducts with LRB wool mattresses and cladding with G.I sheet of 0.63mm thickness and removal of ash an
TTPS Operation Circle MPM I Unit I Machining or reconditioning of R.C feeder spares
TTPS Operation Circle MPM I Unit I Inspection, overhauling and commissioning of actuators for both manual and electrical operation in Hot air dampers during the forthcoming overhaul.
TTPS Mech II TM I Unit I Overhauling of steam and condensate valves of Turbine Regeneration system during forthcoming overhaul
TTPS Mech II TM I Unit I Removal and Re fixing of wool mattress or Cera blanket insulation of Turbine Casing and their allied pipe lines valves during forthcoming overhaul
TTPS Operation Circle MPM I Unit I Replacement of eroded Coal pipe lines, bends and fittings between Mills A, B and C and Boiler during the forthcoming overhaul
TTPS Mech II TM I Unit I Overhauling of stator water primary secondary pumps Hydrogen cooler booster pump working oil coolers lub oil coolers of BFP and cooling water valves renewal of worn out BCW ACW cooling water pipes and renewal of gaskets i
TTPS Operation Circle MPM I Unit I Overhauling of worn out fuel inlet elbows special bends coal pipes and Orifices in boiler corner 3 and 4 during the forthcoming overhaul
TTPS Mech II TM I Unit I Reconditioning of Lub oil Seal oil cooler cooling water butterfly Gate valves of various sizes during forthcoming overhaul
TTPS Operation Circle MPM I Unit I Overhauling of worn out fuel inlet elbows special bends coal pipes and Orifices in boiler corner 1 and 2 during the forthcoming overhaul
TTPS Mech II TM I Unit I Condenser Repairing and arresting the leak points in the longitudinal bellows and side walls of LPT Exhaust hood during forthcoming overhaul
TTPS Mech II TM I Unit I Inspection overhauling and commissioning of condenser butterfly valves and steam line valves actuators during the forthcoming overhaul
TTPS Mech II AHP Unit I Annual overhauling works of pumps valves in sea water Booster Pumps during the forthcoming overhaul
TTPS Operation Circle CAD CWPH I Unit I Annual Overhauling of internal and external assembly and Reconditioning of C.W.P Internal spares 1A, 1B, 1C and 1D of Unit I
TTPS Mech II AHP Replacement of Regular make up jetting assembly connected pipe Lines flushing header assembly overhauling of valves cleaning and welding of seal trough in unit I BAH during forthcoming overhaul