Loading…
Loading…
308 live1,238 closing this weekmost from Northern Railway and South Eastern Railway
308 results • Best match
1) Solapur Division- various types of track works under the Yard Improvement umbrella at Shendri, Barshi Town, Pajari, Dharashiv, Yedshi, Dhoky, Ausa Road, Harangul, Latur, Modlimb, Pandharpur, Sangola, Jath Road, Dhalgaon, Kavathe Mahankal, Salgare ... imp works like ... TWR work in ...
... will be property of the Railways. (iii)Cut trees shall be property of Railways and to be deposited in the... and to be deposited in the railway godown unless specified otherwise ...
Construction of Pit Lines in the Furnishing Shop (Roads 3 & 4) and Paint Shop (Road 3), including other miscellaneous works and Electrical Works, with a maintenance period of two (02) years, at Carriage Repair Workshop, Hubballi - 580020.
... fixing new bearing plates supplied by Railways in pit lines, duly breaking ...
Track work: Provision of additional goods line with increasement in existing goods wharf at New Lalitpur town station of Jhansi Division, N.C. Railway.
... Joggled fish plates shall be supplied by Railway at nearest P. Way Stores ...
10089802 RAILWAY YARD MATERIAL
MISCELLANEOUS TRACK WORK IN THE JURISDICTION OF ADEN/MTD
... Plates with bolt / clamp (supplied by Railway from nearest SSE Store) ...
Augmentation and Up-gradation of Wagon maintenance facilities in Wagon Repair Shop, Kharagpur
... prerequisites prescribed in Indian Railway Track Machine Manual for deployment ...
KPAW : Conversion of Railway tracks to Zero Level track in TR Lines
... at-Site. MCI insert shall be supplied by Railway free of cost.
R and M Work of Railway Siding Track in HEEP
... BY COMBING THE BALLAST IN RAILWAY TRACK AND DRESSING AS PER REQUIRED ...
Safety work related misc. track works in the section of SSE/P.way/DPR under ADEN/NBD.
... latest edition of Indian Railways Permanent Way Manual
Random testing of track fittings at Northern Railway, Track Supply Depot, Ghaziabad.
Safety work related misc. track works in the section of SSE/P.way/BSC under ADEN/HPU.
... latest edition of Indian Railways Permanent Way Manual
New Coochbehar - Chapaguri (SL) - TBCSR (H-Beam) on Torsa Bridge - 1204, & Ghoksadanga - Sajerpar (UP)-TBCSR (H-Beam) on bridge No.116-815 Nos.
2019.00 sleepers with all Railway supplied fittings complete for TBTR ...
Safety work related misc. track works in the section of SSE/P.way/AMRO under ADEN/GJL.
... latest edition of Indian Railways Permanent Way Manual
DEN/E/JP Section: - Miscellaneous track works in the jurisdiction of ADEN/AWR.
... / worn-out fittings with Railway's fittings for track/Points & Crossings sleepers ...
Safety work related misc. track works in the section of SSE/P.way/KNT under ADEN/NBD.
... latest edition of Indian Railways Permanent Way Manual
1. S&T work in connection with provision of Track Renewal Jabalpur division of West Central Railway (Signalling Work). 2. S&T work in connections with turnout renewal in JBP-KTE Section of Jabalpur Division on West Central Railway (Signalling work).
... complete for 18 approval of Railways. Railway will return one set of circuit ...
Track work in connection with Enhancement of freight stock examination & maintenance facilities at GMC (Phase-I) under ADEN/Line/CNB.
Indian Railway Track Machine Manual for
Comprehensive 3 Years Maintenance Contract for Upkeep/Cleaning and Track Maintenance of Railway Track of MCW Railway Siding,Upkeep/Cleaning of Railway Track of KKC Main Siding and Upkeep/Cleaning of Railway Track of Keshargarh Siding under B-II Area
... as per standard of Indian Railway viz Ministry instruction ...
Safety work related misc. track works in the section of SSE/P.way/GJL under ADEN/GJL.
... latest edition of Indian Railways Permanent Way Manual
Transportation of Railway Material by road covering all the feeding units/ Railway Work Shops on Indian Railways
A-Transportation of Railway Material by road covering all the feeding
Work contract for regular engagement of operator of gates at various crossing along railway track from ATPS MPPGCL Chachai to sangma siding
... gate operation at 06 Nos. Railway Crossings namely (i) Amma ...
Engineering, Procurement and Construction (EPC) Agreement for Construction of New BG Rail line including earth work, blanketing, minor bridges, major bridges, Track works, Station building, buildings and other miscellaneous works for 25T Indian ... Indian Railway Standard ... Central Railway in ...
Composite work of Survey, Design, Supply, Installation, Testing & Commissioning of Automatic Signalling work using Multi Section Digital Axle counter for continuous track circuiting along with Electronic Interlocking in Auto huts and alteration in ... associated works including ... Central Railway
... complete for approval of Railways. Railways will return one set to the... complete for approval of Railways. Railways will return one set of circuit ...
Safety work related misc. track works in the section of SSE/P.way/HPU under ADEN/HPU.
... latest edition of Indian Railways Permanent Way Manual
Work of enhancement of existing 200KVA to 630KVA Railway Track Transformer centre in New Vaddem under the jurisdiction of SD-I ( U), Div XI,Vasco
Jeypore-Malkangiri New BG Railway Line: Design & Construction of New BG Railway line from KM 41.50 to Km 69.60 (including Nunkhari Station) involving Earthwork in formation, Embankment/Cutting, Blanketing, Side Drains, Catch Water Drains, Minor ... Protection works , ... BLT works , ... P.Way Track works with ... Water Supply , ... Power Supply Arrangements ... Coast Railway .
by Railways & specifications or as
work: Supply, Installation, Testing, Commissioning, Integration with Existing VSS Infra, Operation and Maintenance of IP based Video Surveillance System (VSS) at Railway Stations under Western Region of RailTel for and on behalf of Indian Railways
S&T work in c/w (1) Repl. of steel girder with RCC slab of Bridge No.102 UP&DN, 111 UP&DN, 119 UP on JUC-ASR sec., B.no.180 on ASR-ATT & br. no.103 on VKA- DBNK section. (ii) Construction of LHS of internal size 5 m X 3.5 m LHS in lieu of LC C-7 at KM 4/13-14 on JUC-NRO section under ADEN-JUC over firozpur division. (iii) Construction of LHS of internal size 5.0 X 5.0m at manned L-xings No.A-5 on VKA- DBNK section by pushing method in the section under ADEN-I/ASR. (iv) Construction of RCC box (2 nos. twin boxes) bridge in lieu of steel trough bridge no.158 in PHR-LNK section.
the Railways. It includes Meggering of... contractor and submitted to Railways. (Inspection: Site engineer)
Supply, erection, testing & commissioning of 25KV OHE electrification and modification works at HTE Electric Loco Trip Shed including General Services work in connection with the Construction of new Electric Loco Trip Shed at Hatia in Ranchi Division ... Eastern Railway .
Erection of overhead equipment, including Per Track catenary (Railway Supply), contact (Railway KM Supply), jumper and dropper wires.
Supply, erection of Electrical works related to upgradation of 10 GB Ethernet network & PA system in Blue line Metro Railway, Kolkata.
Signalling work in c/w (i) Ambala Division -TTR(TWS+CMSC) -40 sets, TTR(FS+TWS+WCMSC)-13 sets, TTR(TWS)- 65 sets, TTR(TSR)-110 sets & TTR( CMSC)-25 sets.(ii) Yard improvement of KLK yard under jurisdiction of ADEN/SML. (iii) RPJ-DUI (DN)-TSR(P) ... Km work over ... improvement works in ...
... machine as per direction of railway representative at site.... contractor as directed by railways representative at site. Cable will be supplied by railway. (d) It includes drilling ...
Electrical (General) work in connection with Landscaping development, horticulture works & other ancillary works at railway premises of Howrah under AEN/SPL/HWH.
... of cable ( Cable will be supplied by Railway ) Above/
EXECUTION OF BALLAST LESS TRACK WORKS FROM SHIVALINGAPURAM STATION KM. 45.483 TO BORRAGUHALU STATION KM. 72.550 IN CONNECTION WITH KOTTAVALASA KORAPUT DOUBLING PROJECT OF RAYAGADA DIVISION, EAST COAST RAILWAY ON EPC MODE
... Rayagada Division, East Coast Railway on EPC Mode
Sr. DEN (N)/JP section - Miscellaneous track safety works in the jurisdiction of ADEN-RGS.
6000.00 by layer filled with Railway Sand/railway quarry dust in Contractor's ...
Supplying of 60000 Cum of machine crushed track ballast 50mm size conforming to RDSO's specification of track ballast (February - 2023 edition with upto date correction slips) and loading the same into any type of Railway Wagon, F.O.R. Pakur /Bakudih/Barharwa for Sonpur Division.
Composite Work (Civil, Electrical & S&T) comprising formation, viaducts, minor/major bridges, RUBs/Subways, station buildings, staff quarters, platforms, passenger amenities, supply & spreading of ballast, track linking and P-Way works, along with ... Design, Supply , ... and Supply , ... the track , ... associated works between ... Western Railway .
... of one no. bearing from Railway approved firms and all fixing... the drawing approved from Railway and cost of inspection during manufacturing from railway approved organization.Note ...
Supplying including loading, transportation, unloading of 2,00,000 cum machine crushed track ballast (Pakur/Sahibganj area) as per Railway/RDSO's specification of track ballast IRS: GE-1, June'2004 with up-to-date correction slips and stacking the ... B.G. Railway Track & ... of railway wagons ...
... all leads, lifts, crossing railway lines if required and levelling ...
Electrification of OHE depots and electrification of Tower Wagon Sheds at Tiruturaipundi and Pattukottai including power supply arrangements. - Railway Electrification of Thiruvarur - Karaikudi section - Works contract
Drilling of 500mm dia Horizontal borehole for water main pipeline under the railway tracks under TAPI BULK LINE PROJECT WTP MAINTENANCE
water main pipeline under the railway tracks incl.
Dismantling Formation Work Civil and Allied Ancillary Works at Prayagraj Yard Phase-5 for Construction of 4th Line between Bamhrauli and Prayagraj with Rail Flyover RFO-2 at Subedarganj under North Central Railway Ministry of Railways Govt of India
Electrical balance works in connection with Development/Redevelopment/Major Upgradation of Ghaziabad Railway Station of Northern Railway.
Laying, underground/road/Railway track, recessing in platform /wall ...
Electrical General Services Work in connection with "Developmental works at RHA stations under Amrit Station Scheme in SDAH Divn. of Eastern Railway"
PROCUREMENT OF P.W. MATERIALS, FITTINGS and FIXTURES AND P.W. TOOLS FOR MAINTENANCE OF RAILWAY TRACKS OF HALDIA DOCK COMPLEX, HALDIA.
Design, Supply, Installation, Testing and Commissioning of ElectronicInterlocking (E.I) system along with other Indoor and outdoor Signalling works at Sanjan, Dungri ,Amalsad, Bhilad, and Bililmora stations of Mumbai Division,Western Railway.
... complete for approval of Railways. Railways will return one set to the... complete in all respects to the Railways along with PENDRIVE & 4 ...
Proposal for Miscellaneous P.Way works, Repairs to track, scattered renewal and repair under SSE(P-Way) Wani under ADEN(Warora) Under Sr.DEN(South)NGP jurisdiction in Nagpur division for 2 years.
... broken / missing fittings supplied by Railway; (7) Correcting displaced ...
Open e-tender for the work of Pre & Post tamping track measurement survey using Trimble gedo vorsys trolley system or similar and development of updated scale map Under the Jurisdiction of Sr. Divisional Engineer-I/Eastern Railway/Malda.
Electrical General Services work in connection with "Balanced Developmental works at DDJ and BP stations under Amrit Station Scheme in SDAH Divn. of Eastern Railway".
Safety work related misc. track works in the section of SSE/P.way/BJO under ADEN/GJL.
... latest edition of Indian Railways Permanent Way Manual
Construction of 4th BG Line from Itarsi (Km 745.130) to Bina (Km 982.130) including Earthwork, Tunnels, Bridges, Road over Bridge (ROB), Road under Bridge (RUB), station buildings, track works, Electrification, Signaling & Telecommunication works, ... miscellaneous works in ... Central Railway in ...
... any other place outside Railway land/premises, including... including crossing of nallah, railway tracks, making/repairing approach ...
Gunupur-Theruvali New BG line project : Design and Construction of New BG Railway line from Km 122.750 to Km 141.940 (Excluding RCC BOX, ROB Br. No 388 from km 137.725 to 137.925 but including P Way & OHE works) involving 08 Nos of Tunnels (T-2 to ... BLT Works & ... Protection Works , ... P.Way Track Works with ... material supplies including ... including supply of ... of Track Ballast, ... foundations, Supply and ... Water Supply , ... Electrification works etc ... Coast Railway .
approved by Railways & specifications